Required for placement of a manufactured home in the Town of Taylor. Only multi-section manufactured homes are a permitted use under the Town's Zoning Code; single-wide homes require a Conditional Use Permit and are allowed only on agricultural-zoned property. Both a Town of Taylor building permit and a State of Arizona Office of Manufactured Housing (OMH) installation permit are required.

Verified 2026-07-07 · Source

When you need this permit

  • Only multi-section manufactured homes are a permitted use Town-wide; single-wide (SW) homes are allowed only on agricultural-zoned property as a Conditional Use, requiring a Conditional Use Permit (CUP) and a mandatory public hearing before the Planning and Zoning Commission
  • Minimum 1,100 square feet
  • Home's tongue must be removed
  • Masonry block skirting on an appropriate foundation required, subject to Arizona Office of Manufactured Housing (OMH) approval of skirting plans
  • Special venting requirements apply in Special Flood Hazard Areas
  • For homes placed on privately owned lots outside a manufactured-home rental community, an affidavit of affixture (converting the home to real property) must be filed before a Certificate of Occupancy is issued
  • All Arizona OMH laws and rules must be complied with; Arizona no longer permits Owner-Builder permits for manufactured home installation — a licensed installer must apply for the permit Owner-builder
  • Home should be oriented with its wide side parallel to the front lot line; roof pitch not less than 3:12 with eaves of 6 inches or greater (Spanish-style architecture exempt from the eave rule); home must be securely anchored with an approved OMH anchoring system
  • Each exterior door must have a completed porch or deck of at least 32 sq ft before a Certificate of Occupancy will be issued
  • New and pre-owned home exteriors must be completely finished and in like-new condition; any garage, carport, or room addition must match the home's exterior material and roofing as closely as practicable

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Building Code Valuation Regional ModifierTown of Taylor Fee Schedule, effective April 5, 2025 (same modifier applied to residential/commercial building permits generally; no separate manufactured-home-specific fee line was found published)
75% of standard ICC/UBC valuation-based fee table
Conditional Use Permit (single-wide homes on agricultural zoning only)Town of Taylor Fee Schedule, effective April 5, 2025 (Planning & Zoning)
$150.00

Review timeline

Plan reviewTaylor’s published plan-review target
10–10 business days

How long did your Manufactured Home Installation Permit permit actually take in Taylor?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Anchoring

    Verify masonry block skirting foundation and OMH-approved anchoring system before enclosure

  2. 2

    Final

    Porch/deck (32 sq ft minimum per exterior door), exterior finish condition, and garage/carport/addition material match verified before Certificate of Occupancy

See the full Taylor inspection guide — scheduling & re-inspection fees →

Tips

  • Confirmed gap: no Town-published fee line item specific to 'Manufactured Home Installation' was found distinct from the general Building Permit Fee (75% valuation modifier); the standard residential building-permit fee structure is applied here as the best-available governing figure after an exhaustive check of the Town's current (2025) Fee Schedule, which itemizes Homes, Garage, Portable Sheds/Containers/Carports, Fences, and Plan Review but does not separately list manufactured homes.
  • This is a two-permit process: a Town of Taylor building permit AND a separate Arizona Office of Manufactured Housing (OMH) state installation permit are both required — the Town's own handout is explicit that OMH governs the technical installation/anchoring standards while the Town governs zoning, placement, and the local aesthetic-parity requirements (matching exterior material, roof pitch, porch/deck requirement).
  • Single-wide manufactured homes are geographically restricted: allowed ONLY on agricultural-zoned property via a discretionary Conditional Use Permit with a public hearing — they are not a permitted use anywhere else in Town.

Frequently asked questions

Yes. All Arizona Office of Manufactured Housing (OMH) laws and rules must be complied with in addition to the Town of Taylor's building and zoning requirements, and Arizona no longer allows Owner-Builder permits for manufactured home installation — a licensed installer must apply for the permit.

In Taylor, the published Building Permit Fee — Building Code Valuation Regional Modifier is: 75% of standard ICC/UBC valuation-based fee table. Additional published fees: Conditional Use Permit (single-wide homes on agricultural zoning only) — $150.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Taylor's published plan-review target for a manufactured home installation permit is 10–10 business days.

You'll need: Building Permit Application; Manufactured Homes Requirements in Taylor AZ (handout); Arizona Office of Manufactured Housing (OMH) Installation Permit; Affidavit of Affixture. Depending on your project, Taylor may also ask for: Conditional Use Permit Application. See the required-documents checklist on this page for details on each.

Taylor requires 2 inspection(s) for a manufactured home installation permit, in order: Foundation/Anchoring, Final. Schedule each through Town of Taylor Building / Zoning Department (Development Services Department) (928-536-7366).

Apply through Town of Taylor Building / Zoning Department (Development Services Department) at Taylor Town Hall, 425 Papermill Road (P.O. Box 158), Taylor, AZ 85939. Phone: 928-536-7366, email: geri@tayloraz.gov. Office hours: Town Hall is currently open Monday - Thursday, 7:30 a.m. - 5:30 p.m. (closed Fridays and all major holidays), per the Town's current live website. An older (2014) Town of Taylor 'Homeowner's Guide to Permits' handout lists Development Services Department hours as Monday - Friday, 8:30 a.m. - 5:00 p.m.; the Town Hall-wide 4-day/10-hour schedule on the current tayloraz.gov site is treated as the more current figure for permit-counter purposes. The single Building Official/Zoning Administrator position (reporting directly to the Town Manager as part of the executive leadership team, per the Town's 2024 AZBO job posting) administers both building permits and zoning/planning for the Town.. Official information: https://www.tayloraz.gov/departments/building/.

Taylor, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/town authority under state enabling statutes (A.R.S. Title 9). The Town of Taylor independently adopts and administers its own construction codes through its own Building/Zoning Department (Development Services Department) at Taylor Town Hall; it does not defer building permitting to Navajo County. Verified independence: Taylor maintains its own Municipal Code Chapter 15.05 (Building and Construction Codes), its own Fee Schedule (effective April 5, 2025), its own Building Permit Application, and a dedicated Building Official/Zoning Administrator position reporting to the Town Manager. The Town shares only Fire/EMS (Taylor-Snowflake Fire) and Police (Snowflake-Taylor Police Department) with the adjacent Town of Snowflake — building/zoning permitting is NOT a shared program between the two towns. Source: Town of Taylor Municipal Code § 15.05 (codepublishing.com/AZ/Taylor/html/Taylor15/Taylor1505.html); tayloraz.gov Building Department and Permits pages; Town of Taylor Fee Schedule effective 4/5/2025; Town of Taylor Building Official/Zoning Administrator job posting (AZBO, 2024).; 2015 International Building Code (IBC), published by the International Code Council, adopted by reference with Appendices C and I, as amended by the Town of Taylor (Taylor Municipal Code § 15.05). Source: Town of Taylor Municipal Code § 15.05.040 (codepublishing.com/AZ/Taylor/html/Taylor15/Taylor1505.html).; 2015 International Residential Code (IRC) for One- and Two-Family Dwellings, adopted by reference with Appendices A, B, H, M, N, R, and S, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Plumbing Code (IPC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Mechanical Code (IMC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Fuel Gas Code (IFGC), adopted by reference with Appendices A, B, and C, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2009 International Energy Conservation Code (IECC) — notably one code family behind the Town's otherwise-2015 ICC set. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Existing Building Code (IEBC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Fire Code (IFC), adopted by reference as the Town's uniform fire code, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2014 National Electrical Code (NEC/NFPA 70), published by the National Fire Protection Association, adopted by reference, as amended by the Town of Taylor — one edition behind the otherwise-2015 ICC family set (the same one-cycle-behind pattern seen in other Navajo County towns, e.g. Show Low's 2017 NEC alongside 2018 ICC codes). Source: Town of Taylor Municipal Code § 15.05.; Residential fire sprinklers: IRC Section R313 is deleted in its entirety and replaced with a cross-reference directing compliance to Arizona Revised Statute § 9-807 (the state statute governing municipal authority to require or not require residential fire sprinklers) rather than the model code's own prescriptive sprinkler trigger. Source: Town of Taylor Municipal Code § 15.05 (IRC Chapter 3 amendment).; Manufactured homes, mobile homes, and factory-built buildings: construction/installation standards are regulated directly by the State of Arizona (Arizona Department of Housing, Office of Manufactured Housing (OMH); A.R.S. § 41-4001 et seq.). The Town of Taylor's own Building/Zoning Department governs on-site placement, foundation/tie-down, and zoning compliance, and imposes its own additional zoning-based requirements (see localAmendments). As of the Town's published guidance, Arizona no longer allows Owner-Builder permits for manufactured home installation — a licensed installer must apply for the permit. Source: Town of Taylor 'Manufactured Homes Requirements in Taylor AZ' handout (Taylor Building/Zoning Department); A.R.S. § 41-4001 et seq.. Local amendments apply — see the Taylor overview page for the full list.

Only on agricultural-zoned property, and only via a Conditional Use Permit ($150 fee) requiring a public hearing before the Planning and Zoning Commission. Multi-section manufactured homes are a permitted use Town-wide, subject to the Town's 1,100-sq-ft minimum and other zoning/aesthetic requirements.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Taylor building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.