Required for room additions, remodels, and alterations to existing one- and two-family dwellings in the City of Winslow, reviewed against the 2018 IRC as adopted and amended by the City (Winslow Municipal Code § 15.04.040(B)).

Verified 2026-07-13 · Source

When you need this permit

  • Building permit required for additions and remodels affecting structural, electrical, plumbing, or mechanical systems
  • Detached one-story accessory structures (sheds, playhouses, similar) up to 200 sq ft (IRC) or 120 sq ft (IBC) do not require a building permit but still require zoning clearance and a zoning permit
  • Painting, papering, tiling, carpeting, cabinets, countertops, and similar finish work do not require a permit
  • Plans must comply with City of Winslow Climatic and Geographic Design Criteria (30 psf ground snow load; 115 mph wind speed, Exposure C; 18-inch frost depth)
  • Application must include a completed application and three (3) complete sets of scaled plans showing the addition/remodel scope

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeCity of Winslow Ordinance No. 637, Schedule 3, Section 3-4
Calculated per Table 1-A of the 1997 Uniform Building Code, plus 10%
Issuance FeeCity of Winslow Ordinance No. 637, Schedule 3, Section 3-4
$40.00
Residential Plan Review FeeCity of Winslow Ordinance No. 637, Schedule 3, Section 3-5
$100 due at submission (applied to final fee); total fee for up to three review sessions is 65% of the total building permit fee, or actual city/consultant cost, whichever is greater

Review timeline

Plan reviewWinslow’s published plan-review target
15–15 business days

How long did your Residential Addition / Remodel Permit permit actually take in Winslow?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Required before concrete pour for additions

  2. 2

    Framing

    Structural connections to the existing structure

  3. 3

    Final

    Completed work verified against approved plans

See the full Winslow inspection guide — scheduling & re-inspection fees →

Tips

  • The City's published plan review timeline (approximately 15 working days) is stated generally for building permits and is not published separately by permit subtype, so it is applied here as well.
  • One-story detached accessory structures up to 200 sq ft (IRC) do not need a building permit, but the City's own guidance clarifies they still require a zoning clearance and permit under Title 17 (Zoning).

Frequently asked questions

Yes, a building permit is required for room additions and remodels affecting structural, electrical, plumbing, or mechanical elements, per Winslow Municipal Code § 15.04.040(B) (2018 IRC as adopted and amended).

In Winslow, the published Building Permit Fee is: Calculated per Table 1-A of the 1997 Uniform Building Code, plus 10%. Additional published fees: Issuance Fee — $40.00; Residential Plan Review Fee — $100 due at submission (applied to final fee); total fee for up to three review sessions is 65% of the total building permit fee, or actual city/consultant cost, whichever is greater. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Winslow's published plan-review target for a residential addition / remodel permit is 15–15 business days.

You'll need: Building Permit Application; Site/Plot Plan. See the required-documents checklist on this page for details on each.

Winslow requires 3 inspection(s) for a residential addition / remodel permit, in order: Foundation/Footing, Framing, Final. Schedule each through City of Winslow Community Development Department (928-289-1476).

Apply through City of Winslow Community Development Department at 102 E. Third Street, Winslow, AZ 86047 (2025 AZBO Directory lists the department's own address as 21 Williamson Avenue, Winslow, AZ 86047; the City's live website header lists City Hall at 102 E. Third Street — both are cited here as the City has not published a single reconciled address). Phone: 928-289-1476, email: comdevelopment@winslowaz.gov. Office hours: Not separately published by the Community Development Department; general City Hall contact is Monday-Friday per the City's main Contact page (102 E. Third Street, phone 928-289-2422, fax 928-289-3742). Building-permit-specific questions are directed to 928-289-1476 or comdevelopment@winslowaz.gov, per the City's Community Development page.. Official information: https://www.winslowaz.gov/page/community-development.

Winslow, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9). The City of Winslow independently adopts and administers its own construction codes through its Community Development Department; it does not defer permitting to Navajo County. Source: Winslow Municipal Code Title 15 (Buildings and Construction), Chapter 15.04 (ecode360.com/49538196, code current through legislation effective 10-28-2025).; 2018 International Building Code, including Appendix K, adopted by reference with City of Winslow amendments (Winslow Municipal Code § 15.04.040(A)). Source: Winslow Municipal Code § 15.04.040 (ecode360.com/49538207).; 2018 International Residential Code for One- and Two-Family Dwellings, including Appendix Q (Tiny Houses) and Appendix K, adopted by reference with City of Winslow amendments (§ 15.04.040(B)). Source: Winslow Municipal Code § 15.04.040.; 2018 International Plumbing Code, adopted by reference with City of Winslow amendments (§ 15.04.040(C)). Source: Winslow Municipal Code § 15.04.040.; 2018 International Fuel Gas Code, adopted with City of Winslow amendments (§ 15.04.040(D)). Source: Winslow Municipal Code § 15.04.040.; 2018 International Mechanical Code, adopted by reference with City of Winslow amendments (§ 15.04.040(E)). Source: Winslow Municipal Code § 15.04.040.; 2017 National Electrical Code (NFPA 70), adopted by reference with City of Winslow amendments (§ 15.04.040(F)) — one edition behind the 2018 ICC family set. Source: Winslow Municipal Code § 15.04.040.; 2018 International Property Maintenance Code, adopted with City of Winslow amendments (§ 15.04.040(G)); enforcement/violations/notices/appeals cross-reference Winslow Municipal Code § 8.20 (Nuisances). Source: Winslow Municipal Code § 15.04.040.; 2018 International Existing Building Code, adopted by reference, applying to repair, alteration, change of occupancy, addition, and relocation of existing buildings (§ 15.04.040(A), IBC 101.4.10). Source: Winslow Municipal Code § 15.04.040.; 2018 International Fire Code is referenced within the adopted IBC (§ 15.04.040(A), IBC 101.4.5) for matters of fire prevention, suppression, and alarm systems. Source: Winslow Municipal Code § 15.04.040.; Confirmation of currency: the City of Winslow's live Community Development page (as captured by the Wayback Machine, snapshot dated 1/24/2025) independently lists the identical current code set — '2018 International Building Code Including Appendix K, 2018 International Existing Building Code, 2018 International Residential Code Including Appendix Q and K, 2018 Plumbing Code, 2018 International Mechanical Code, 2018 International Fuel Gas Code, 2018 Property Maintenance Code, 2017 National Electric Code' — matching Winslow Municipal Code § 15.04.040 verbatim. Source: City of Winslow Community Development page, Wayback Machine capture (web.archive.org/web/20250124090125/https://www.winslowaz.gov/page/community-development).; Fee-calculation basis is separately codified and uses OLDER code editions' valuation tables than the substantive codes above: the City of Winslow's Schedule of Rates, Fees and Charges (Ordinance No. 637, as amended, current edition July 2026) calculates Building, Mechanical, and Plumbing permit fees using Table 1-A of the 1997 Uniform Building Code / 1997 Uniform Mechanical Code / 1997 Uniform Plumbing Code (each plus 10%), and Electrical permit fees using Table 3-A of the 1999 National Electrical Code (plus 10%) — this valuation-table-only reference is distinct from, and does not supersede, the substantive 2018 IBC/IRC/IMC/IPC/IFGC and 2017 NEC construction requirements adopted in Title 15. Source: City of Winslow Ordinance No. 637, Schedule of Rates, Fees and Charges (July 2026), Schedule 3, Sections 3-1 through 3-4; Winslow Municipal Code §§ 15.04.040(C) 106.6, 15.04.040(D) 106.6.2, 15.04.040(E) 106.5.2 (each cross-referencing 'the fee schedule, as adopted in City of Winslow Ordinance Number 637').; Manufactured/mobile homes and factory-built buildings: the City of Winslow Schedule of Rates, Fees and Charges publishes dedicated permit fees for Mobile/Manufactured Home ($650/home, includes 3 inspections), Factory Built Building - Residential ($650/story), Factory Built Building - Commercial ($6.00/LF per story) and Classroom ($3.00/LF per story), each including 3 inspections; a 6-month permit extension is $100; Factory Built Building Special Use is $250 (1 inspection); Rehabilitation - Mobile Home is $49 (income below Area Median Income) or $306 (income at/above AMI), including 2 inspections; and Installation/Re-inspection/Additional not covered by permit is $175 each. Source: City of Winslow Ordinance No. 637, Schedule 3, Section 3-7.. Local amendments apply — see the Winslow overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Winslow building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.