Solar Photovoltaic (PV) Permit — Winslow, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.winslowaz.gov/page/community-development
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Photovoltaic (PV) Permit in Winslow, Arizona
Required for installation of rooftop residential or commercial solar photovoltaic systems in the City of Winslow. There is no dedicated solar/PV permit type or fee line item in City of Winslow Ordinance No. 637, Schedule of Rates, Fees and Charges (July 2026) — confirmed by a full-text search of the 44-page fee schedule for 'solar,' 'photovoltaic,' and 'renewable,' which returned zero results. A solar installation is processed as a standard building permit (structural/racking) plus electrical permit (wiring/interconnection), billed under the same 1997 UBC Table 1-A / 1999 NEC Table 3-A valuation-based fee tables used for other construction, and is subject to Arizona's statewide solar construction permit statute (A.R.S. § 9-468).
Verified 2026-07-20 · Source
When you need this permit
- Building permit required for the structural/racking portion, reviewed against the 2018 IRC/IBC as adopted and amended by the City (Winslow Municipal Code § 15.04.040)
- Electrical permit required for the PV wiring/interconnection portion, governed by the 1999 NEC as adopted for fee purposes (see this file's electrical-permit entry)
- Application must include a completed Building Permit Application and three (3) complete sets of scaled plans and specifications, per the City's general residential building permit submittal requirements
- Per A.R.S. § 9-468, the City's total fee for a solar construction permit may not exceed the actual cost of issuance, and the City must provide an itemized cost breakdown upon request
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before cover
- 2
Final
Racking, roof penetrations, and electrical connections verified
See the full Winslow inspection guide — scheduling & re-inspection fees →
Tips
- Winslow has no dedicated solar/PV fee line item — confirmed by a full-text search of the City's entire 44-page Ordinance No. 637 fee schedule for 'solar,' 'photovoltaic,' and 'renewable' (zero hits). A solar installation is billed under the same 1997 UBC / 1999 NEC valuation-based tables used for any other building/electrical permit.
- Arizona's statewide A.R.S. § 9-468 still caps whatever total fee Winslow charges for a solar construction permit at the City's actual cost of issuance — ask Community Development for an itemized cost breakdown if the calculated valuation-based fee seems high.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Winslow building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Winslow
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Winslow project checklist
Describe your project once and get every permit, document, and fee it triggers in Winslow — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.