Solar Photovoltaic (PV) Permit in Winslow, Arizona

Required for installation of rooftop residential or commercial solar photovoltaic systems in the City of Winslow. There is no dedicated solar/PV permit type or fee line item in City of Winslow Ordinance No. 637, Schedule of Rates, Fees and Charges (July 2026) — confirmed by a full-text search of the 44-page fee schedule for 'solar,' 'photovoltaic,' and 'renewable,' which returned zero results. A solar installation is processed as a standard building permit (structural/racking) plus electrical permit (wiring/interconnection), billed under the same 1997 UBC Table 1-A / 1999 NEC Table 3-A valuation-based fee tables used for other construction, and is subject to Arizona's statewide solar construction permit statute (A.R.S. § 9-468).

Verified 2026-07-20 · Source

When you need this permit

  • Building permit required for the structural/racking portion, reviewed against the 2018 IRC/IBC as adopted and amended by the City (Winslow Municipal Code § 15.04.040)
  • Electrical permit required for the PV wiring/interconnection portion, governed by the 1999 NEC as adopted for fee purposes (see this file's electrical-permit entry)
  • Application must include a completed Building Permit Application and three (3) complete sets of scaled plans and specifications, per the City's general residential building permit submittal requirements
  • Per A.R.S. § 9-468, the City's total fee for a solar construction permit may not exceed the actual cost of issuance, and the City must provide an itemized cost breakdown upon request

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (structural/racking portion)City of Winslow Ordinance No. 637, Schedule of Rates, Fees and Charges (July 2026), Schedule 3, Section 3-4; confirmed via full-text search that no solar-specific fee is published
Calculated per Table 1-A of the 1997 Uniform Building Code, plus 10% — no dedicated solar/PV line item exists
Electrical Permit Fee (wiring/interconnection portion)City of Winslow Ordinance No. 637, Schedule 3, Section 3-2
Calculated per Table 3-A of the 1999 National Electrical Code, plus 10%
Issuance Fee (each permit)City of Winslow Ordinance No. 637, Schedule 3, Sections 3-2 and 3-4
$40.00
Residential Plan Review FeeCity of Winslow Ordinance No. 637, Schedule 3 — same fee applied to other residential building permits per this file's residential-building-permit entry
$100 due at submission

Review timeline

Plan review
Not published — contact the department

How long did your Solar Photovoltaic (PV) Permit permit actually take in Winslow?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final

    Racking, roof penetrations, and electrical connections verified

See the full Winslow inspection guide — scheduling & re-inspection fees →

Tips

  • Winslow has no dedicated solar/PV fee line item — confirmed by a full-text search of the City's entire 44-page Ordinance No. 637 fee schedule for 'solar,' 'photovoltaic,' and 'renewable' (zero hits). A solar installation is billed under the same 1997 UBC / 1999 NEC valuation-based tables used for any other building/electrical permit.
  • Arizona's statewide A.R.S. § 9-468 still caps whatever total fee Winslow charges for a solar construction permit at the City's actual cost of issuance — ask Community Development for an itemized cost breakdown if the calculated valuation-based fee seems high.

Frequently asked questions

Winslow requires a solar photovoltaic (pv) permit for: Building permit required for the structural/racking portion, reviewed against the 2018 IRC/IBC as adopted and amended by the City (Winslow Municipal Code § 15.04.040); Electrical permit required for the PV wiring/interconnection portion, governed by the 1999 NEC as adopted for fee purposes (see this file's electrical-permit entry); Application must include a completed Building Permit Application and three (3) complete sets of scaled plans and specifications, per the City's general residential building permit submittal requirements; Per A.R.S. § 9-468, the City's total fee for a solar construction permit may not exceed the actual cost of issuance, and the City must provide an itemized cost breakdown upon request. If your project isn't listed, confirm with City of Winslow Community Development Department at 928-289-1476 before starting work.

No. A full-text search of the City's Ordinance No. 637 Schedule of Rates, Fees and Charges (July 2026) found no solar, photovoltaic, or renewable energy line item. Solar installations are billed as a standard building permit (1997 UBC Table 1-A, plus 10%) for the structural/racking portion and a standard electrical permit (1999 NEC Table 3-A, plus 10%) for the wiring/interconnection portion, each with a separate $40 issuance fee.

Winslow does not publish a plan-review timeline for this permit. Contact City of Winslow Community Development Department at 928-289-1476 for current turnaround.

You'll need: Building Permit Application; Construction Drawings (3 complete sets). See the required-documents checklist on this page for details on each.

Winslow requires 2 inspection(s) for a solar photovoltaic (pv) permit, in order: Rough Electrical, Final. Schedule each through City of Winslow Community Development Department (928-289-1476).

Apply through City of Winslow Community Development Department at 102 E. Third Street, Winslow, AZ 86047 (2025 AZBO Directory lists the department's own address as 21 Williamson Avenue, Winslow, AZ 86047; the City's live website header lists City Hall at 102 E. Third Street — both are cited here as the City has not published a single reconciled address). Phone: 928-289-1476, email: comdevelopment@winslowaz.gov. Office hours: Not separately published by the Community Development Department; general City Hall contact is Monday-Friday per the City's main Contact page (102 E. Third Street, phone 928-289-2422, fax 928-289-3742). Building-permit-specific questions are directed to 928-289-1476 or comdevelopment@winslowaz.gov, per the City's Community Development page.. Official information: https://www.winslowaz.gov/page/community-development.

Winslow, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9). The City of Winslow independently adopts and administers its own construction codes through its Community Development Department; it does not defer permitting to Navajo County. Source: Winslow Municipal Code Title 15 (Buildings and Construction), Chapter 15.04 (ecode360.com/49538196, code current through legislation effective 10-28-2025).; 2018 International Building Code, including Appendix K, adopted by reference with City of Winslow amendments (Winslow Municipal Code § 15.04.040(A)). Source: Winslow Municipal Code § 15.04.040 (ecode360.com/49538207).; 2018 International Residential Code for One- and Two-Family Dwellings, including Appendix Q (Tiny Houses) and Appendix K, adopted by reference with City of Winslow amendments (§ 15.04.040(B)). Source: Winslow Municipal Code § 15.04.040.; 2018 International Plumbing Code, adopted by reference with City of Winslow amendments (§ 15.04.040(C)). Source: Winslow Municipal Code § 15.04.040.; 2018 International Fuel Gas Code, adopted with City of Winslow amendments (§ 15.04.040(D)). Source: Winslow Municipal Code § 15.04.040.; 2018 International Mechanical Code, adopted by reference with City of Winslow amendments (§ 15.04.040(E)). Source: Winslow Municipal Code § 15.04.040.; 2017 National Electrical Code (NFPA 70), adopted by reference with City of Winslow amendments (§ 15.04.040(F)) — one edition behind the 2018 ICC family set. Source: Winslow Municipal Code § 15.04.040.; 2018 International Property Maintenance Code, adopted with City of Winslow amendments (§ 15.04.040(G)); enforcement/violations/notices/appeals cross-reference Winslow Municipal Code § 8.20 (Nuisances). Source: Winslow Municipal Code § 15.04.040.; 2018 International Existing Building Code, adopted by reference, applying to repair, alteration, change of occupancy, addition, and relocation of existing buildings (§ 15.04.040(A), IBC 101.4.10). Source: Winslow Municipal Code § 15.04.040.; 2018 International Fire Code is referenced within the adopted IBC (§ 15.04.040(A), IBC 101.4.5) for matters of fire prevention, suppression, and alarm systems. Source: Winslow Municipal Code § 15.04.040.; Confirmation of currency: the City of Winslow's live Community Development page (as captured by the Wayback Machine, snapshot dated 1/24/2025) independently lists the identical current code set — '2018 International Building Code Including Appendix K, 2018 International Existing Building Code, 2018 International Residential Code Including Appendix Q and K, 2018 Plumbing Code, 2018 International Mechanical Code, 2018 International Fuel Gas Code, 2018 Property Maintenance Code, 2017 National Electric Code' — matching Winslow Municipal Code § 15.04.040 verbatim. Source: City of Winslow Community Development page, Wayback Machine capture (web.archive.org/web/20250124090125/https://www.winslowaz.gov/page/community-development).; Fee-calculation basis is separately codified and uses OLDER code editions' valuation tables than the substantive codes above: the City of Winslow's Schedule of Rates, Fees and Charges (Ordinance No. 637, as amended, current edition July 2026) calculates Building, Mechanical, and Plumbing permit fees using Table 1-A of the 1997 Uniform Building Code / 1997 Uniform Mechanical Code / 1997 Uniform Plumbing Code (each plus 10%), and Electrical permit fees using Table 3-A of the 1999 National Electrical Code (plus 10%) — this valuation-table-only reference is distinct from, and does not supersede, the substantive 2018 IBC/IRC/IMC/IPC/IFGC and 2017 NEC construction requirements adopted in Title 15. Source: City of Winslow Ordinance No. 637, Schedule of Rates, Fees and Charges (July 2026), Schedule 3, Sections 3-1 through 3-4; Winslow Municipal Code §§ 15.04.040(C) 106.6, 15.04.040(D) 106.6.2, 15.04.040(E) 106.5.2 (each cross-referencing 'the fee schedule, as adopted in City of Winslow Ordinance Number 637').; Manufactured/mobile homes and factory-built buildings: the City of Winslow Schedule of Rates, Fees and Charges publishes dedicated permit fees for Mobile/Manufactured Home ($650/home, includes 3 inspections), Factory Built Building - Residential ($650/story), Factory Built Building - Commercial ($6.00/LF per story) and Classroom ($3.00/LF per story), each including 3 inspections; a 6-month permit extension is $100; Factory Built Building Special Use is $250 (1 inspection); Rehabilitation - Mobile Home is $49 (income below Area Median Income) or $306 (income at/above AMI), including 2 inspections; and Installation/Re-inspection/Additional not covered by permit is $175 each. Source: City of Winslow Ordinance No. 637, Schedule 3, Section 3-7.. Local amendments apply — see the Winslow overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Winslow building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.