Residential Building Permit (New Construction) in Clarkdale, Arizona
Required for new single-family and two-family dwelling construction in the Town of Clarkdale. Reviewed against the 2024 IRC and Town of Clarkdale amendments (Town Code Article 7-2). Applications are submitted by mail, email, or in person to the Community Development Department.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required for new single-family and two-family dwelling construction within Clarkdale town limits
- Plans must comply with the 2024 IRC and Town of Clarkdale amendments, including Seismic Design Category C (amended R301.2.2.1)
- Construction must start within 180 days of the permit issue date; construction hours are limited to 6:00 a.m. to 9:00 p.m.
- Site plan required, drawn to a defined scale, showing size/location of new construction and existing structures, lot-line distances, grading/drainage, and utility line locations
- Application submitted via mail (PO Box 308, Clarkdale, AZ 86324), email (communitydevelopment@clarkdale.az.gov), or in person at 890 Main Street; application is reviewed for completeness prior to acceptance
- Applicant must disclose contractor licensing status (ROC license number and class) or claim an A.R.S. §32-1121A owner/builder or owner/developer exemption from contractor licensing Owner-builderContractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing/Foundation
After excavation and reinforcing steel placement, and after any required third-party special inspections (geotechnical, retaining wall), prior to concrete placement
- 2
Under-Slab Plumbing, Water, and Electric
Drain/waste/vent piping slope and test, water distribution and hot-water pipe insulation, proper bedding — prior to backfilling
- 3
Rough Combo / Exterior Lath
After framing, fire-blocking, windows, bracing, and rough electrical/plumbing/mechanical are in place; fire sprinkler systems (if applicable) must be inspected and approved by the fire district first
- 4
Insulation
After frame/exterior lath inspection and rough plumbing/mechanical/gas/electrical approval, prior to covering
- 5
Gypsum Board / Drywall / Fire-Rated Construction
Before joints and fasteners are taped and finished
- 6
Final
After all permitted work is complete and all other department/agency approvals (e.g., fire district, flood control) are obtained, prior to occupancy
See the full Clarkdale inspection guide — scheduling & re-inspection fees →
Tips
- As of this review, the Town of Clarkdale does not publish a specific plan-review turnaround time (a stated number of business/calendar days for 1st/2nd review) for residential building permits anywhere on its public website, in its Town Code amendments, or in its Building Permit Application. Arizona's A.R.S. § 9-835 requires municipalities to post an overall licensing/permit time frame on their website, but does NOT itself supply a numeric default if a municipality has not published one — it is silent on both a fallback figure and a penalty for non-compliance. No Clarkdale-specific time-frame policy document was found after an exhaustive search (Building Division page, Community Development page, Apply For page, News Flash/CivicAlerts, Town Code Chapter 7 articles, and Wayback Machine snapshots of the town.codes mirror). Call Community Development at 928-639-2500 or email the Building Official at bob.pipkin@clarkdale.az.gov for a current estimate.
- The Town's own Building Division webpage still describes the 2018 ICC codes and 2017 NEC as the adopted set, but the Town's actual, currently-published Article 7-1/7-2 ordinance PDFs show the 2024 IBC/IRC (2023 NEC, 2018 IECC) are now in force — the webpage summary text appears to be stale relative to the ordinance documents themselves; treat the ordinance PDFs as authoritative.
- A Notice of Intention to Amend the Townwide Fee Schedule was posted July 6, 2026 (60-day pre-hearing notice per A.R.S. § 9-499.15), proposing to update the building-valuation cost basis from the August 2007 to the 2018 ICC Building Safety Journal table; a Town Council hearing is scheduled for September 8, 2026. Confirm which valuation table is in effect at the time of any permit application near or after that date.
- Construction must start within 180 days of permit issuance and may only proceed 6:00 a.m.-9:00 p.m.; a lapsed permit can be renewed at half the original fee if plans are unchanged and the lapse is under 1 year.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Clarkdale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Clarkdale
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Clarkdale project checklist
Describe your project once and get every permit, document, and fee it triggers in Clarkdale — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →