Required for new commercial construction, additions, and remodels/tenant improvements in the Town of Clarkdale. There is no standalone Commercial Building Permit application, and no separate Tenant Improvement (TI) permit product at the Town level -- confirmed by inspecting the Town's own Building Permit Application (DocumentCenter View 1154), whose single 'TYPE OF PROJECT' checkbox grid lists 'COMMERCIAL' alongside 'REMODEL,' 'NEW CONSTRUCTION,' and 'DEMOLITION' as options on the same general-purpose form used for every other permit type in this file. A commercial tenant improvement is therefore filed as a Commercial and/or Remodel Building Permit, reviewed against the 2024 IBC (Town Code Article 7-1) or, for work/change of use in an existing building, the 2024 IEBC (Article 7-8). The Verde Valley Fire District (VVFD) runs a separate, Town-independent fire-code plan review track for commercial work, and charges its own distinct $250 fee specifically when a Tenant Improvement involves a Change of Use (see certificate-of-occupancy-permit entry) -- but that is a VVFD fire-review fee, not a second Town permit product, so it is not modeled as its own permitType.

Verified 2026-07-29 · Source

When you need this permit

  • Building permit required for new commercial construction, additions, and remodels/tenant improvements within Clarkdale town limits, applied for on the Town's single Building Permit Application by checking 'COMMERCIAL' and/or 'REMODEL,' 'NEW CONSTRUCTION,' or 'DEMOLITION' as applicable -- no distinct Commercial Building Permit form or Tenant Improvement permit product exists
  • Plans must comply with the 2024 IBC and Town of Clarkdale amendments (Town Code Article 7-1); a change of occupancy/use or alteration of an existing commercial building is separately governed by the 2024 IEBC (Article 7-8)
  • Per the Town's own 'How do I build a permit?' guide to its iWorQ online permitting portal (DocumentCenter View 1975), commercial submittals pass through the same three-stage review as other permits (Community Development Tech, then Public Works, then Building Official), but the guide explicitly states 'Commercial projects may have additional requirements' at the Public Works stage, and that 'separate review may be required from outside sources, Engineering, Soils report, Grading, Fire Sprinklers (as needed)' at the Building Official stage
  • All contractors on a commercial permit must hold a current Town of Clarkdale Business License, verified by Community Development during submittal review (per the Building Permit Application's license-information section and the 'How do I build a permit?' guide)
  • Automatic fire sprinkler systems are required under Town Code Article 7-1's amended IBC Section 903.2 for Assembly/Business/Educational/Factory/Mercantile occupancies where gross floor area exceeds 1,000 sq ft or available water supply is insufficient for required fire flow -- see this file's fire-sprinkler-alarm-permit entry for VVFD's separate sprinkler/alarm permitting and fees
  • All plans and specifications for new commercial construction, remodeling, or alterations within VVFD's district must be independently submitted to the Verde Valley Fire District for fire-code review and approval prior to any construction, per VVFD's own Permits & Fees page -- a parallel review track the Town's own permit does not substitute for
  • Construction must start within 180 days of permit issuance and may only proceed 6:00 a.m. to 9:00 p.m., per the Town-wide Section 105.5/105.5.1 rule applied to all building permit types
  • A commercial Tenant Improvement involving a Change of Use triggers VVFD's separate, named 'Tenant Improvement w/Change of Use (Commercial)' fire plan-review-and-inspection fee ($250) -- the Town itself has no distinct TI or Change-of-Use permit product; see the certificate-of-occupancy-permit entry in this file

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee -- Based on ValuationDirectly verified against the Town's own 'Notice of Intention to Amend the Townwide Fee Schedule' (DocumentCenter View 2552, posted 07/06/2026), which reprints the actual per-square-foot commercial occupancy cost table (Exhibit C). Currently-effective (August 2007 basis) examples: Group B (Business) ranges $104.41/sq ft (Type VB) to $152.75/sq ft (Type IA); Group M (Mercantile) ranges $76.10/sq ft (Type VA) to $149.29/sq ft (Type IA); Group A-2 (restaurants/bars) ranges $109.46/sq ft (Type VB) to $146.10/sq ft (Type IA). A proposed update to the 2018 cost table (e.g., Group B $140.26-$192.02/sq ft; Group M $109.23-$140.27/sq ft) is scheduled for a September 8, 2026 Town Council hearing and is not yet in effect. The itemized Table 1-A dollar-bracket schedule (fee per valuation bracket, as opposed to these underlying per-square-foot cost inputs) was not independently located -- confirmed gap, not an assumption.
Calculated from ICC Building Safety Journal square-foot construction-cost tables (currently the AUGUST 2007 cost table) applied against Table 1-A, Building Permit Fees
Plan Review FeeStated directly in the Town's fee-schedule notice for the proposed table ('Permits will be charged a Plan Review fee of 65% of the building permit fee') and confirmed unchanged from the currently-effective table; non-refundable per the Building Permit Application
65% of the calculated Building Permit Fee
Revised/Resubmitted Plans Review FeeBuilding Permit Application: 'A twenty percent plan review fee may be applied to revised plans.'
20% of the plan review fee (as applicable)
VVFD Fire Plan Review (new commercial construction, remodeling, alterations)VVFD's Fee Schedule (Resolution #2025-12, adopted 9/23/2025) itemizes sprinkler/alarm system fees (see fire-sprinkler-alarm-permit entry) and the $250 TI w/Change of Use fee (see certificate-of-occupancy-permit entry), but no separate line item for a baseline commercial plan review untied to a fire-suppression/alarm system or change of use was found -- confirmed gap. Contact VVFD Fire Prevention at 928-634-2578 ext. 4.
Not independently located for a general commercial plan review distinct from VVFD's itemized sprinkler/alarm fees or its named $250 Tenant Improvement w/Change of Use fee

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Clarkdale?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    After excavation and reinforcing steel placement, and after any required third-party special inspections (geotechnical, retaining wall), prior to concrete placement

  2. 2

    Rough Combo

    After framing, and rough electrical/plumbing/mechanical are in place; special inspections (per amended IBC 1705.21-23, e.g. electrical equipment ≥1,000A/>600V) required where applicable; fire sprinkler/alarm systems (if applicable) must be separately inspected and approved by VVFD

  3. 3

    Insulation / Energy Efficiency

    Per 2018 IECC Chapter 13 provisions, prior to covering

  4. 4

    Final

    After all permitted work is complete and all other department/agency approvals (VVFD fire final, Public Works, etc.) are obtained; Certificate of Occupancy issued under the Town's adopted, locally unamended 2024 IBC Section 111

See the full Clarkdale inspection guide — scheduling & re-inspection fees →

Tips

  • As of this review (2026-07-29), the Town of Clarkdale does not publish a specific plan-review turnaround time for commercial building permits -- not even in its own 'How do I build a permit?' iWorQ guide, which describes the review workflow but no day-count. Call Community Development at 928-639-2500 for a current estimate.
  • Commercial submittals face two independent, parallel review/permitting tracks -- the Town of Clarkdale's Building Permit and the Verde Valley Fire District's fire-code plan review (which VVFD's own materials state must be completed 'prior to any construction') -- budget time and fees for both, not just the Town's.
  • No standalone Tenant Improvement or Change-of-Use permit exists at the Town level -- TI/remodel work is filed as a Commercial and/or Remodel Building Permit. If the TI involves a change of use, budget separately for VVFD's named $250 Tenant Improvement w/Change of Use fee.
  • The Town's own fee-schedule notice (posted 07/06/2026) confirms the currently-effective ICC valuation basis is an unusually old August 2007 cost table; a proposed update to the 2018 table is scheduled for a September 8, 2026 Town Council hearing -- confirm which table applies for the specific application date.
  • No commercial-specific checklist or application (e.g., a 'Commercial Building Checklist') could be located live on the Town's Forms page as of 2026-07-29, despite an earlier review (2026-07-06) flagging several 01.01.26-dated checklists, including commercial ones, as listed-but-404; a fresh re-check found no such checklist listed at all -- the Town's single general-purpose Building Permit Application remains the only located application.

Frequently asked questions

Clarkdale requires a commercial building permit for: Building permit required for new commercial construction, additions, and remodels/tenant improvements within Clarkdale town limits, applied for on the Town's single Building Permit Application by checking 'COMMERCIAL' and/or 'REMODEL,' 'NEW CONSTRUCTION,' or 'DEMOLITION' as applicable -- no distinct Commercial Building Permit form or Tenant Improvement permit product exists; Plans must comply with the 2024 IBC and Town of Clarkdale amendments (Town Code Article 7-1); a change of occupancy/use or alteration of an existing commercial building is separately governed by the 2024 IEBC (Article 7-8); Per the Town's own 'How do I build a permit?' guide to its iWorQ online permitting portal (DocumentCenter View 1975), commercial submittals pass through the same three-stage review as other permits (Community Development Tech, then Public Works, then Building Official), but the guide explicitly states 'Commercial projects may have additional requirements' at the Public Works stage, and that 'separate review may be required from outside sources, Engineering, Soils report, Grading, Fire Sprinklers (as needed)' at the Building Official stage; All contractors on a commercial permit must hold a current Town of Clarkdale Business License, verified by Community Development during submittal review (per the Building Permit Application's license-information section and the 'How do I build a permit?' guide); Automatic fire sprinkler systems are required under Town Code Article 7-1's amended IBC Section 903.2 for Assembly/Business/Educational/Factory/Mercantile occupancies where gross floor area exceeds 1,000 sq ft or available water supply is insufficient for required fire flow -- see this file's fire-sprinkler-alarm-permit entry for VVFD's separate sprinkler/alarm permitting and fees; All plans and specifications for new commercial construction, remodeling, or alterations within VVFD's district must be independently submitted to the Verde Valley Fire District for fire-code review and approval prior to any construction, per VVFD's own Permits & Fees page -- a parallel review track the Town's own permit does not substitute for; Construction must start within 180 days of permit issuance and may only proceed 6:00 a.m. to 9:00 p.m., per the Town-wide Section 105.5/105.5.1 rule applied to all building permit types; A commercial Tenant Improvement involving a Change of Use triggers VVFD's separate, named 'Tenant Improvement w/Change of Use (Commercial)' fire plan-review-and-inspection fee ($250) -- the Town itself has no distinct TI or Change-of-Use permit product; see the certificate-of-occupancy-permit entry in this file. If your project isn't listed, confirm with Town of Clarkdale Community Development Department — Building Safety Unit (Building Division) at 928-639-2500 before starting work.

In Clarkdale, the published Building Permit Fee -- Based on Valuation is: Calculated from ICC Building Safety Journal square-foot construction-cost tables (currently the AUGUST 2007 cost table) applied against Table 1-A, Building Permit Fees. Additional published fees: Plan Review Fee — 65% of the calculated Building Permit Fee; Revised/Resubmitted Plans Review Fee — 20% of the plan review fee (as applicable); VVFD Fire Plan Review (new commercial construction, remodeling, alterations) — Not independently located for a general commercial plan review distinct from VVFD's itemized sprinkler/alarm fees or its named $250 Tenant Improvement w/Change of Use fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Clarkdale does not publish a plan-review timeline for this permit. Contact Town of Clarkdale Community Development Department — Building Safety Unit (Building Division) at 928-639-2500 for current turnaround.

You'll need: Building Permit Application (PDF); Site/Plot Plan; Construction Drawings and Structural Calculations; Verde Valley Fire District Permit Application Form (PDF). See the required-documents checklist on this page for details on each.

Apply through Town of Clarkdale Community Development Department — Building Safety Unit (Building Division) at 890 Main Street, Clarkdale, AZ 86324 (mail: PO Box 308, Clarkdale, AZ 86324). Phone: 928-639-2500, email: communitydevelopment@clarkdale.az.gov. Office hours: Community Development Department: Monday - Thursday, 8:00 a.m. to 5:30 p.m.; Friday, 8:00 a.m. to 12:00 p.m. Building permit applications are mailed or emailed to communitydevelopment@clarkdale.az.gov, or submitted in person at 890 Main Street. Inspection requests must be made 24 hours in advance by calling 928-639-2500 or emailing inspections@clarkdale.az.gov; the Building Official can be reached directly for application questions.. Official information: https://www.clarkdale.az.gov/179/Building-Division.

No. The Town uses one general-purpose Building Permit Application for every permit type in this file; 'COMMERCIAL' is simply one checkbox among several project types (alongside Residential, Remodel, New Construction, Demolition, etc.) on that same form.

No. There is no standalone Tenant Improvement or Change-of-Use permit at the Town level -- a TI is filed as a Commercial and/or Remodel Building Permit under the Town's adopted 2024 IEBC (for existing buildings). However, if the TI involves a change of use, the Verde Valley Fire District charges its own separate, named $250 'Tenant Improvement w/Change of Use (Commercial)' fire plan-review-and-inspection fee.

Yes. The Verde Valley Fire District (VVFD) independently reviews and approves plans and specifications for new commercial construction, remodeling, or alterations before construction may begin -- this is separate from, and required in addition to, the Town's own Building Permit review.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Clarkdale.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.