Electrical Permit in Superior, Colorado

Required for electrical wiring, service, and equipment work in the Town of Superior. Governed by the 2023 NEC as adopted, and billed under a dedicated Electrical Permit Fee table (separate from the general Building Permit Fee valuation schedule) based on either enclosed living area (for new/remodeled/added single-family, duplex, condo, or townhouse wiring) or dollar valuation (for service hookups, modular home connections, and other electrical work).

Verified 2026-07-05 · Source

When you need this permit

  • Contractors must hold a current Town of Superior Electrical Contractor License, requiring active State and Master License copies plus a Certificate of Insurance uploaded via Community Core Contractor
  • New/remodeled/added residential wiring is billed by enclosed living area (not project valuation)
  • Other electrical work (service hookups, modular home connections, temporary construction meters) is billed on the dollar value of the electrical installation, including time and materials
  • Governed by the 2023 NEC as adopted

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential wiring (new/remodel/addition) — not more than 1,000 sq ft enclosed living areaTown of Superior 2026 Governmental Fee Schedule (Exhibit A), Electrical Permit Fees table
$46.00
Residential wiring — 1,001 to 1,500 sq ft
$51.75
Residential wiring — 1,501 to 2,000 sq ft
$63.25
Residential wiring — per additional 100 sq ft over 2,000 sq ft
$3.45
Other electrical work (service hookups, modular home connections) — valuation $2,001 to $50,000
$19.55 per $1,000 or fraction thereof
Mobile homes / travel trailer parksPlus $51.75 for re-inspections
$46.00 per space

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit permit actually take in Superior?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

See the full Superior inspection guide — scheduling & re-inspection fees →

Tips

  • Standalone residential wiring is billed by square footage of enclosed living area, not project valuation — a different calculation basis than the general Building Permit Fee schedule.
  • Service hookups and modular home connections are billed on dollar valuation of the electrical work itself, following a separate valuation table from both the residential-square-footage table and the general Building Permit Fee table.

Frequently asked questions

Superior requires an electrical permit for: Contractors must hold a current Town of Superior Electrical Contractor License, requiring active State and Master License copies plus a Certificate of Insurance uploaded via Community Core; New/remodeled/added residential wiring is billed by enclosed living area (not project valuation); Other electrical work (service hookups, modular home connections, temporary construction meters) is billed on the dollar value of the electrical installation, including time and materials; Governed by the 2023 NEC as adopted. If your project isn't listed, confirm with Town of Superior Planning & Building Department, Building Division (operated by SAFEbuilt) at 303-381-2028 before starting work.

For new, remodeled, or added wiring in a single-family home, duplex, condo, or townhouse, the fee is based on enclosed living area (e.g., $46.00 for up to 1,000 sq ft). For other electrical work such as service hookups or modular home connections, the fee is based on the dollar valuation of the electrical installation instead.

Superior does not publish a plan-review timeline for this permit. Contact Town of Superior Planning & Building Department, Building Division (operated by SAFEbuilt) at 303-381-2028 for current turnaround.

You'll need: Building Permit Application (Community Core); Town of Superior Electrical Contractor License. See the required-documents checklist on this page for details on each.

Superior requires 2 inspection(s) for an electrical permit, in order: Rough Electrical, Final Inspection. Schedule each through Town of Superior Planning & Building Department, Building Division (operated by SAFEbuilt) (303-381-2028).

Apply through Town of Superior Planning & Building Department, Building Division (operated by SAFEbuilt) at 100 Superior Plaza Way, Suite 200, Superior, CO 80027. Phone: 303-381-2028, email: superiorinspections@safebuilt.com. Office hours: Town of Superior general office hours Monday-Friday, 8 a.m.-4 p.m. (per Town website footer); Planning direct line 303-499-3675 ext. 131; Building direct line 303-381-2028; Permit Fees line 720-738-7326. The Building Division is operated under contract by SAFEbuilt; permit applications, submittals, and inspection requests are handled via the Community Core online portal and the superiorinspections@safebuilt.com email address.. Official information: https://www.superiorcolorado.gov/Government/Departments/Planning-Building.

Superior, Colorado has adopted: 2024 International Building Code (IBC) — adopted per Chapter 18 of the Superior Municipal Code, per the Town's Building Codes and Zoning Regulations page; 2024 International Residential Code (IRC), with a local amendment adopting the 2018 IRC high-wind roof-covering criteria (ASTM D7158 Class G or H, or ASTM D3161 Class F) for reroofing, per the Town's Supplemental Roof Information page (2018 IRC edition adopted June 2020 specifically for the wind-region roofing requirement, ahead of the Town's broader 2024 code cycle); 2024 International Mechanical Code (IMC); 2024 International Plumbing Code (IPC); 2024 International Fire Code (IFC); 2024 International Fuel Gas Code (IFGC); 2024 International Existing Building Code (IEBC); 2024 International Private Sewage Disposal Code; 2024 International Property Maintenance Code; Metro Cohort Model Code, based on the 2024 International Energy Conservation Code (IECC) — per the Town's Building Codes and Zoning Regulations page; 2023 National Electrical Code (NEC); Superior Municipal Code Section 18-14-40 (Minimum Efficiency Requirement / Construction Waste Recycling) — requires an applicant for a new residential structure building permit to demonstrate a minimum of 50% of construction waste is recycled, with waste diversion tracking submitted to the Town at project completion; additions/remodels over 500 sq ft are encouraged (not required) to divert waste. Local amendments apply — see the Superior overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-05.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Superior building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.