Residential Building Permit (New Construction / Additions) in Superior, Colorado

Required for construction of new single-family homes, additions, and similar new residential structures within the Town of Superior. Reviewed under the 2024 IRC/IBC (as locally amended) plus the Town's structural/wind design criteria, Green Building Program, and Municipal Code Section 18-14-40 construction-waste-recycling requirement. Applications are submitted through Community Core and reviewed by the Town's Planning & Building Department, whose Building Division is operated by SAFEbuilt; Mountain View Fire Protection District conducts an independent, separately-timed fire/sprinkler plan review for new residential construction.

Verified 2026-07-05 · Source

When you need this permit

  • Plans must comply with the 2024 IRC/IBC as adopted by Superior Municipal Code Chapter 18
  • Must meet the Town's structural/wind design criteria: 154 mph wind speed, 25 lbs/sq ft wind load, 30 lbs/sq ft roof live load, and 36-inch minimum frost line depth
  • New residential structures must demonstrate a minimum of 50% construction waste recycling (Municipal Code Section 18-14-40), with waste diversion tracking submitted to the Town at project completion
  • Must demonstrate sufficient Green Building Program points scaled to the home's square footage, and 2021 IECC energy-code compliance (via RES-Check, an energy-rating-company Energy Compliance Report, or full prescriptive IECC compliance)
  • A Mountain View Fire Protection District Application for Plan Review is required for each residential unit/riser sprinkler submittal, including modular homes; this fire district review is separate from the Town's own review track and may run on a different timeline
  • All contractors must hold a current Town of Superior Contractor License (Initial fee $200, obtained via Community Core) in addition to any required State (DORA) trade license Contractor
  • Combined building plan set (soils report, stamped foundation/structural plans, architectural/floor plans, combined electrical/mechanical plans, site/plot plan with grading and erosion-control BMPs) uploaded as a single set to Community Core
  • A large-format (22x34 or 24x36 inch) copy of the approved plan set must be kept on site until final inspections pass

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — total valuation $0.00 to $500.00Town of Superior 2026 Governmental Fee Schedule (Exhibit A, FINAL 2026 03/09/26)
$28.50
Building Permit Fee — total valuation $2,000.01 to $25,000.00
$81.00 for the first $2,000.00 plus $16.00 for each additional $1,000.00 or fraction thereof, to and including $25,000.00
Building Permit Fee — total valuation $1,000,000.01 and up
$8,424.00 for the first $1,000,000.00 plus $5.00 for each additional $1,000.00 or fraction thereof
Plan Review FeeDue when plans are submitted; based on estimated Permit Fees and adjusted if actual fees differ materially
65% of the Building Permit Fee
Town Use Tax
3.775% (2025 rate) of 50% of total project valuation
Boulder County Use Tax
1.335% (2026 rate) of 50% of total project valuation

Review timeline

Plan reviewSuperior’s published plan-review target
10–10 business days

How long did your Residential Building Permit (New Construction / Additions) permit actually take in Superior?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour, per 36-inch minimum frost depth and stamped foundation plans

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans; large-format approved plan set must be on site

See the full Superior inspection guide — scheduling & re-inspection fees →

Tips

  • Mountain View Fire Protection District reviews sprinkler/fire submittals on its own separate timeline from the Town's 10-business-day residential target — budget for both tracks running in parallel, not sequentially.
  • The Town's 10/15/5 business-day review periods are explicitly targets, not guarantees, and restart entirely if a resubmittal is required — build schedule buffer accordingly.
  • Construction waste recycling (minimum 50%) is a Municipal Code requirement for new residential structures, not just a recommendation — waste diversion tracking must be submitted to the Town at project completion.
  • Because the Building Division is operated by SAFEbuilt under contract, plan review correspondence and inspection scheduling come through superiorinspections@safebuilt.com and the Community Core portal rather than a generic Town government email.

Frequently asked questions

Superior requires a residential building permit (new construction / additions) for: Plans must comply with the 2024 IRC/IBC as adopted by Superior Municipal Code Chapter 18; Must meet the Town's structural/wind design criteria: 154 mph wind speed, 25 lbs/sq ft wind load, 30 lbs/sq ft roof live load, and 36-inch minimum frost line depth; New residential structures must demonstrate a minimum of 50% construction waste recycling (Municipal Code Section 18-14-40), with waste diversion tracking submitted to the Town at project completion; Must demonstrate sufficient Green Building Program points scaled to the home's square footage, and 2021 IECC energy-code compliance (via RES-Check, an energy-rating-company Energy Compliance Report, or full prescriptive IECC compliance); A Mountain View Fire Protection District Application for Plan Review is required for each residential unit/riser sprinkler submittal, including modular homes; this fire district review is separate from the Town's own review track and may run on a different timeline; All contractors must hold a current Town of Superior Contractor License (Initial fee $200, obtained via Community Core) in addition to any required State (DORA) trade license; Combined building plan set (soils report, stamped foundation/structural plans, architectural/floor plans, combined electrical/mechanical plans, site/plot plan with grading and erosion-control BMPs) uploaded as a single set to Community Core; A large-format (22x34 or 24x36 inch) copy of the approved plan set must be kept on site until final inspections pass. If your project isn't listed, confirm with Town of Superior Planning & Building Department, Building Division (operated by SAFEbuilt) at 303-381-2028 before starting work.

In Superior, the published Building Permit Fee — total valuation $0.00 to $500.00 is: $28.50. Additional published fees: Building Permit Fee — total valuation $2,000.01 to $25,000.00 — $81.00 for the first $2,000.00 plus $16.00 for each additional $1,000.00 or fraction thereof, to and including $25,000.00; Building Permit Fee — total valuation $1,000,000.01 and up — $8,424.00 for the first $1,000,000.00 plus $5.00 for each additional $1,000.00 or fraction thereof; Plan Review Fee — 65% of the Building Permit Fee; Town Use Tax — 3.775% (2025 rate) of 50% of total project valuation; Boulder County Use Tax — 1.335% (2026 rate) of 50% of total project valuation. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town's own published target is 10 business days for residential permits, starting once the application is complete and fees are paid. The Town labels this a target, not a guarantee, and it restarts if resubmittal is required.

You'll need: Building Permit Application (Community Core); Residential Building Permit Application Checklist submittal package; Mountain View Fire Protection District Application for Plan Review; Green Building Program / 2021 IECC energy compliance documentation. See the required-documents checklist on this page for details on each.

Superior requires 4 inspection(s) for a residential building permit (new construction / additions), in order: Foundation/Footing, Framing, Rough Electrical / Plumbing / Mechanical, Final Inspection. Schedule each through Town of Superior Planning & Building Department, Building Division (operated by SAFEbuilt) (303-381-2028).

Apply through Town of Superior Planning & Building Department, Building Division (operated by SAFEbuilt) at 100 Superior Plaza Way, Suite 200, Superior, CO 80027. Phone: 303-381-2028, email: superiorinspections@safebuilt.com. Office hours: Town of Superior general office hours Monday-Friday, 8 a.m.-4 p.m. (per Town website footer); Planning direct line 303-499-3675 ext. 131; Building direct line 303-381-2028; Permit Fees line 720-738-7326. The Building Division is operated under contract by SAFEbuilt; permit applications, submittals, and inspection requests are handled via the Community Core online portal and the superiorinspections@safebuilt.com email address.. Official information: https://www.superiorcolorado.gov/Government/Departments/Planning-Building.

Superior, Colorado has adopted: 2024 International Building Code (IBC) — adopted per Chapter 18 of the Superior Municipal Code, per the Town's Building Codes and Zoning Regulations page; 2024 International Residential Code (IRC), with a local amendment adopting the 2018 IRC high-wind roof-covering criteria (ASTM D7158 Class G or H, or ASTM D3161 Class F) for reroofing, per the Town's Supplemental Roof Information page (2018 IRC edition adopted June 2020 specifically for the wind-region roofing requirement, ahead of the Town's broader 2024 code cycle); 2024 International Mechanical Code (IMC); 2024 International Plumbing Code (IPC); 2024 International Fire Code (IFC); 2024 International Fuel Gas Code (IFGC); 2024 International Existing Building Code (IEBC); 2024 International Private Sewage Disposal Code; 2024 International Property Maintenance Code; Metro Cohort Model Code, based on the 2024 International Energy Conservation Code (IECC) — per the Town's Building Codes and Zoning Regulations page; 2023 National Electrical Code (NEC); Superior Municipal Code Section 18-14-40 (Minimum Efficiency Requirement / Construction Waste Recycling) — requires an applicant for a new residential structure building permit to demonstrate a minimum of 50% of construction waste is recycled, with waste diversion tracking submitted to the Town at project completion; additions/remodels over 500 sq ft are encouraged (not required) to divert waste. Local amendments apply — see the Superior overview page for the full list.

The Town of Superior's own Planning & Building Department issues all building, electrical, mechanical, and plumbing permits within Town limits. Superior is a home-rule municipality, and its Building Division is operated under contract by SAFEbuilt — but the Town itself, not Boulder County, is the issuing authority. Boulder County's own Building Permits page confirms Superior maintains its own building department, separate from the county's unincorporated permitting program.

Sources & verification

Verified against official sources. Last reviewed 2026-07-05.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Superior building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.