Change of Use / Change of Occupancy — Golden, Colorado · Requirements sheet
Verified 2026-08-13 · Source: https://www.cityofgolden.gov/business/building_construction/required_building_permits_guide.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use / Change of Occupancy in Golden, Colorado
Golden requires a building permit before any construction or changes to a building, including a change of use, per the City's Required Building Permits Guide. No standalone 'change of use' application separate from the general building permit was found published. A Certificate of Occupancy will not be issued until authorization is granted by every City department or division with applicable regulations subject to inspection/approval, and until all associated fees, taxes, or other monies owed to the City are paid in full, per Municipal Code Chapter 15.08 (Building Code).
Verified 2026-08-13 · Source
When you need this permit
- A building permit is required before any construction or changes to a building, including projects that change its use, per the City's Required Building Permits Guide
- No standalone change-of-use application distinct from the general Building Permit Application was found published on the City's Permits & Licenses or Building Permits pages
- A Certificate of Occupancy shall not be issued until authorization is granted by ALL City departments/divisions with applicable regulations subject to inspection or approval, and until all fees, taxes, or other monies owed to the City are paid in full, per Municipal Code Chapter 15.08 (Building Code)
- Golden Fire Department review may apply if the new use triggers fire/life-safety requirements — see the fire-sprinkler-alarm-permit entry
- Contact the Building Division (303-384-8151, building@cityofgolden.net) to confirm requirements for a specific change-of-use project
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection / Certificate of Occupancy
Certificate of Occupancy withheld until every City department/division with applicable jurisdiction grants authorization and all fees/taxes owed to the City are paid in full, per Municipal Code § 15.08 (adopting IBC § 113.1 as amended)
See the full Golden inspection guide — scheduling & re-inspection fees →
Tips
- Golden's Certificate of Occupancy requires sign-off from EVERY City department or division with applicable regulations — not just the Building Division — so a change-of-use project touching zoning, fire, utilities, etc. may need multiple departments' approval before a CO is issued.
- Outstanding fees or taxes owed to the City of any kind can hold up Certificate of Occupancy issuance, per Municipal Code § 15.08 — resolve any account balances before your final inspection.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-13.
Checklists & handouts
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Golden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Golden's permit history is searchable by address
1,439 permits in our copy of Golden's register — searchable by street address, with permit type, status, issued date and valuation where the city publishes them. This is what we hold, not a statement of everything Golden has issued.
All 1,439 are dated 2026, from 2 January to 1 September — this is that year to date, not Golden's full permit history.
83% of Golden's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.
Other permits in Golden
Change of Use / Change of Occupancy in other cities
Compare change of use / change of occupancy fees across Colorado →
Look up this fee in a different city →
Now live
Build your Golden project checklist
Describe your project once and get every permit, document, and fee it triggers in Golden — in one checklist. Free, for any city and any number of projects.
Get started →