Commercial Tenant Improvement (Interior Commercial Alteration) Permit — Golden, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.cityofgolden.gov/business/building_construction/building_permit.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Tenant Improvement (Interior Commercial Alteration) Permit in Golden, Colorado
Required for interior alterations to existing commercial spaces in Golden — tenant finishes, remodels of retail/restaurant/office space, and other interior commercial work. Golden does not publish a separate TI application form or fee schedule (the same Accela portal and valuation-based fee table apply), but the City's own Review Periods table treats 'Interior Commercial Alterations' as a distinct plan-review category with a materially faster 5-15 working-day goal than new commercial construction (20-30 days), and the Golden Fire Department offers a streamlined path for limited tenant improvement projects. Relevant to Golden's downtown retail/hospitality turnover along Washington Avenue.
Verified 2026-08-02 · Source
When you need this permit
- Interior commercial alterations are reviewed under the 2024 IBC and 2024 IEBC (International Existing Buildings Code) as adopted, with trade work under the 2024 IMC/IPC/IFGC and 2023 NEC
- Valuation = cost of labor and materials; permit fee includes prepayment of the City's 3% building-materials use tax (1.5% of total valuation)
- All contractors must be identified on the permit before issuance and must each hold a current City of Golden Contractor License (Municipal Code Chapter 15.01) in addition to any state DORA trade license Contractor
- Modifications to fire sprinkler, fire alarm, or kitchen hood suppression systems require separate permits through the Golden Fire Department Fire & Life Safety Division; Type I kitchen hoods (restaurant TIs) require a hood suppression system permit
- For limited tenant improvement projects, GFD allows a completed construction safety form to be submitted in lieu of a full fire plan — verify applicability with the Fire & Life Safety Division before submission
- Paint/spray booths installed as part of a TI require both a GFD suppression permit and separate Building Division approval of the booth structure
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Plumbing / Gas Pipe
New or relocated plumbing and fuel-gas piping before concealment
- 2
Rough Heating / Rough Electrical
Ductwork and wiring modifications before concealment
- 3
Rough Frame
New interior partitions and structural modifications before cover
- 4
Insulation
Where wall/ceiling assemblies are modified, per the 2024 IECC
- 5
Drywall
Attachment inspection before taping/finishing
- 6
Fire system acceptance tests (GFD, if applicable)
Sprinkler modifications (rough/hydro) and fire alarm 100% pretest with NFPA 72 Record of Completion; kitchen hood test (manual pull, fusible link, fuel/make-up-air shutdown, Class K extinguisher placement); request via portal 2+ business days ahead with stamped plans on-site
- 7
Final Inspections (Building, Plumbing, Heating, Electrical)
All work complete per approved plans before occupancy of the altered space
See the full Golden inspection guide — scheduling & re-inspection fees →
Tips
- Golden's TI review category is genuinely faster on paper — 5-15 working days versus 20-30 for new commercial — but it is not a separate permit product: same portal, same application, same valuation-based fee table. The distinction the City publishes is the review timeline, not the paperwork.
- Restaurant and bar TIs (common in downtown Golden's Washington Avenue corridor) almost always trigger separate GFD permits: any Type I kitchen hood requires a hood suppression system permit, and hood plans must show nozzle locations/distances, suppressant sizing, protected appliances, Class K extinguisher, and manual pull station.
- Ask GFD early whether your project qualifies as a 'limited tenant improvement' — if so, a completed construction safety form can substitute for a full fire plan submittal, saving meaningful review time.
- If your TI modifies sprinkler or alarm systems, the GFD review (3-4 week initial-review goal) can outlast the Building Division's 5-15 day TI review — sequence your submittals so fire review isn't the surprise critical path.
- Interior non-structural demolition ahead of a build-out is a flat $25 permit — one of the cheapest items in the fee table — but partial structural demo is $50 and triggers structural review considerations.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Golden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Golden.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Golden
Commercial Tenant Improvement (Interior Commercial Alteration) Permit in other cities
Compare commercial tenant improvement (interior commercial alteration) permit fees across Colorado →