Required for roofing and re-roofing work on residential and commercial buildings in Golden, unless the work is a minor repair/replacement of 10% or less. Governed by 2024 IRC/IBC local roofing amendments, with detailed local rules on ice barrier, overlay limits, fire rating, and mid-roof inspection.

Verified 2026-07-05 · Source

When you need this permit

  • Permit required for Roofing/Re-Roofing (exterior projects list, Required Building Permits Guide); Minor Roof or Siding Repairs or replacement of 10% or less do NOT require a permit
  • If a repair exceeds 25% of the total roof area, the ENTIRE roof must be replaced (not just the damaged section) — IEBC 2021/2024 Section 1501.2.1 per the City's roofing rules
  • Reroofing must include removal of ALL existing layers of roof covering down to the roof deck — IRC 2024 R908.3 / IBC 2024 1512.2
  • Only one overlay is allowed on existing asphalt or wood shingles; T-Lock shingles cannot be overlaid at all
  • Ice barrier required for ALL new and re-roofing applications (not a minimum-elevation trigger) — must extend from the lowest roof edge to at least 24 inches inside the exterior wall line, per IRC 2024 R905.1.2 / IBC 2024 (equivalent section)
  • Wood shakes and shingles must meet minimum Class A fire rating; all other roofing materials must meet at least Class C fire rating
  • Roof and attic ventilation must comply with IRC Section R806 and manufacturer guidelines
  • Commercial ballasted roofs must undergo an engineering evaluation for load capacity; structural roof components must meet IEBC 2021 Section 1501.2.1 standards
  • Mid-roof inspection required when 25% to 65% of new roof covering has been installed; a ladder must be secured and extended to at least 3 feet above the roofline for inspector access — failure to provide access may trigger reinspection fees

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Permit fee — valuation-based (Building Permit Fee Table)Building Permit Fee Table, Effective 05/01/11
$25.85 minimum, scaling per valuation tiers
Reinspection FeeApplies if a required inspection (e.g., mid-roof) cannot be completed due to inadequate access
$50.00

Review timeline

Plan review
Not published — contact the department

How long did your Roofing Permit (Reroof) permit actually take in Golden?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Mid-Roof

    Required when 25%-65% of new roof covering has been installed; secured ladder extended 3+ feet above roofline required for inspector access

  2. 2

    Final Inspection

    Completed roof — flashing, ice barrier, ventilation, and fire-rating compliance verified

See the full Golden inspection guide — scheduling & re-inspection fees →

Tips

  • Golden requires a full ice barrier on EVERY reroof, regardless of elevation — a stricter rule than jurisdictions that only trigger ice-barrier requirements above a certain elevation.
  • If your repair scope creeps past 25% of total roof area, code requires full roof replacement, not just patching the damaged section — plan and budget accordingly.
  • Don't skip the mid-roof inspection window (25%-65% coverage) — missing it or failing to provide ladder access triggers a $50 reinspection fee.
  • T-Lock shingles can never be overlaid in Golden — full tear-off is mandatory for that product.

Frequently asked questions

Yes, unless the work is a minor repair or replacement of 10% or less of the roof. Any reroof requires full removal of existing roof covering layers down to the deck and a new ice barrier, per the City's roofing amendments to the 2024 IRC/IBC.

In Golden, the published Permit fee — valuation-based (Building Permit Fee Table) is: $25.85 minimum, scaling per valuation tiers. Additional published fees: Reinspection Fee — $50.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Golden does not publish a plan-review timeline for this permit. Contact City of Golden Building Department at (303) 384-8151 for current turnaround.

You'll need: Roofing Permit Application (Online Permitting Portal). See the required-documents checklist on this page for details on each.

Golden requires 2 inspection(s) for a roofing permit (reroof), in order: Mid-Roof, Final Inspection. Schedule each through City of Golden Building Department ((303) 384-8151).

Apply through City of Golden Building Department at 911 10th Street, Golden, CO 80401 (Building Department); Planning Department at 1445 10th Street, Golden, CO 80401. Phone: (303) 384-8151, email: building@cityofgolden.net. Office hours: Monday-Friday, general City Hall hours (main line (303) 384-8000); Building Department direct line (303) 384-8151. Official information: https://www.cityofgolden.gov/business/building_construction/building_permit.php.

Golden, Colorado has adopted: 2024 International Building Code (IBC), with local Appendix G (Flood Flrp/flood-resistant construction) and Appendix I (Patio Covers) — City of Golden Building Permit Process page; 2024 International Residential Code (IRC), with local Appendix BE (Radon Control Methods) and Appendix CD (Piping Standards for Various Applications) — City of Golden Building Permit Process page; 2024 International Energy Conservation Code (IECC); 2024 International Fire Code (IFC); 2024 International Existing Buildings Code (IEBC); 2024 International Mechanical Code (IMC); 2024 International Plumbing Code (IPC) — note: Golden uses the International Plumbing Code, not the Uniform Plumbing Code; 2024 International Building Code Appendix K — Administrative Provisions for the National Electrical Code; 2023 National Electrical Code (NEC); Golden Wildfire Resiliency Code (GWRC), adopted by City Ordinance No. 2290 and codified as Chapter 15.80 of the Golden Municipal Code — applies to new construction, significant additions, repairs, and remodels on properties within Golden's designated Wildland-Urban Interface (WUI) areas (per the Official Golden Wildfire Map); establishes fire-resistant construction standards for two hazard classifications, Class I (low fire intensity) and Class II (medium and high fire intensity); enforcement begins June 10, 2026; Golden Municipal Code Title 15, Chapter 15.08 (Building Code) governs local amendments and adoption by reference; Chapter 15.01 (Contractor Registration) governs the city's separate contractor registration requirement. Local amendments apply — see the Golden overview page for the full list.

Wood shakes and shingles require a minimum Class A fire rating. All other roofing materials must meet at least a Class C fire rating.

Sources & verification

Verified against official sources. Last reviewed 2026-07-05.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Golden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.