Electrical Permit in Golden, Colorado

Required for installation, alteration, or repair of electrical systems in Golden. Governed by the 2023 NEC as adopted, with 2024 IBC Appendix K (Administrative Provisions for the NEC). Electrical contractors must hold a Colorado Electrical Board (DORA) state license AND a separate City of Golden Contractor License.

Verified 2026-07-05 · Source

When you need this permit

  • Permit required for any electrical work: installing, altering, or fixing electrical systems, per the Required Building Permits Guide
  • Contractors must hold a current Colorado Electrical Board (DORA) license AND a City of Golden Contractor License (Municipal Code Chapter 15.01) with its own annual registration fee Contractor
  • All contractors must be identified on the permit before issuance
  • Governed by the 2023 NEC plus 2024 IBC Appendix K administrative provisions

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Permit fee — when NOT attached to a valid Building PermitBuilding Permit Fee Table, Effective 05/01/11
Calculated per the Building Permit Fee Table valuation tiers ($25.85 minimum)
Plan Review FeeBuilding Permit Fee Table footnote **
Waived when the sub-permit is attached to a valid Building Permit and its valuation is included in the total building permit valuation; otherwise 65% of the permit fee
Reinspection Fee
$50.00

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit permit actually take in Golden?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Requested once wiring is installed and the main panel is completed, before concealment

  2. 2

    Final Inspection

    All devices installed, panel labeled, system energized and verified

See the full Golden inspection guide — scheduling & re-inspection fees →

Tips

  • Golden requires its OWN Contractor License in addition to the statewide DORA electrical license — do not assume a valid state license alone is sufficient to pull permits in Golden. Contractor
  • If the electrical work is bundled into a building permit's total valuation, you avoid a separate sub-permit plan review fee — a meaningful savings on larger remodels.

Frequently asked questions

Golden requires an electrical permit for: Permit required for any electrical work: installing, altering, or fixing electrical systems, per the Required Building Permits Guide; Contractors must hold a current Colorado Electrical Board (DORA) license AND a City of Golden Contractor License (Municipal Code Chapter 15.01) with its own annual registration fee; All contractors must be identified on the permit before issuance; Governed by the 2023 NEC plus 2024 IBC Appendix K administrative provisions. If your project isn't listed, confirm with City of Golden Building Department at (303) 384-8151 before starting work.

In Golden, the published Permit fee — when NOT attached to a valid Building Permit is: Calculated per the Building Permit Fee Table valuation tiers ($25.85 minimum). Additional published fees: Plan Review Fee — Waived when the sub-permit is attached to a valid Building Permit and its valuation is included in the total building permit valuation; otherwise 65% of the permit fee; Reinspection Fee — $50.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Golden does not publish a plan-review timeline for this permit. Contact City of Golden Building Department at (303) 384-8151 for current turnaround.

You'll need: Electrical Permit Application (Online Permitting Portal); City of Golden Contractor License. See the required-documents checklist on this page for details on each.

Golden requires 2 inspection(s) for an electrical permit, in order: Rough Electrical, Final Inspection. Schedule each through City of Golden Building Department ((303) 384-8151).

Apply through City of Golden Building Department at 911 10th Street, Golden, CO 80401 (Building Department); Planning Department at 1445 10th Street, Golden, CO 80401. Phone: (303) 384-8151, email: building@cityofgolden.net. Office hours: Monday-Friday, general City Hall hours (main line (303) 384-8000); Building Department direct line (303) 384-8151. Official information: https://www.cityofgolden.gov/business/building_construction/building_permit.php.

Golden, Colorado has adopted: 2024 International Building Code (IBC), with local Appendix G (Flood Flrp/flood-resistant construction) and Appendix I (Patio Covers) — City of Golden Building Permit Process page; 2024 International Residential Code (IRC), with local Appendix BE (Radon Control Methods) and Appendix CD (Piping Standards for Various Applications) — City of Golden Building Permit Process page; 2024 International Energy Conservation Code (IECC); 2024 International Fire Code (IFC); 2024 International Existing Buildings Code (IEBC); 2024 International Mechanical Code (IMC); 2024 International Plumbing Code (IPC) — note: Golden uses the International Plumbing Code, not the Uniform Plumbing Code; 2024 International Building Code Appendix K — Administrative Provisions for the National Electrical Code; 2023 National Electrical Code (NEC); Golden Wildfire Resiliency Code (GWRC), adopted by City Ordinance No. 2290 and codified as Chapter 15.80 of the Golden Municipal Code — applies to new construction, significant additions, repairs, and remodels on properties within Golden's designated Wildland-Urban Interface (WUI) areas (per the Official Golden Wildfire Map); establishes fire-resistant construction standards for two hazard classifications, Class I (low fire intensity) and Class II (medium and high fire intensity); enforcement begins June 10, 2026; Golden Municipal Code Title 15, Chapter 15.08 (Building Code) governs local amendments and adoption by reference; Chapter 15.01 (Contractor Registration) governs the city's separate contractor registration requirement. Local amendments apply — see the Golden overview page for the full list.

Only if they also hold a current City of Golden Contractor License under Municipal Code Chapter 15.01, in addition to their Colorado Electrical Board (DORA) license. Both are required before a permit can be issued.

Sources & verification

Verified against official sources. Last reviewed 2026-07-05.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Golden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.