Required for installation of solar panel systems in Golden. The City holds a Silver SolSmart designation for streamlined solar permitting, but does not publish solar-specific fees, forms, or a dedicated review timeline separate from the general Building Permit Process — solar follows the standard building/electrical permit path.

Verified 2026-07-05 · Source

When you need this permit

  • Solar Panels are listed as requiring a permit under the Required Building Permits Guide's exterior projects list
  • No solar-specific application, checklist, or fee schedule is published on the City's Solar Energy Systems page; applicants are directed to the general Building Permit Process page
  • Follow standard building-permit valuation and, where applicable, electrical-permit requirements (state DORA electrical license plus City of Golden Contractor License) Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Permit fee — valuation-based (Building Permit Fee Table)No solar-specific flat fee is published; solar systems are billed under the same Building Permit Fee Table as other valuation-based work
$25.85 minimum, scaling per valuation tiers

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Permit permit actually take in Golden?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover, per standard electrical permit inspection sequence

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical connections verified

See the full Golden inspection guide — scheduling & re-inspection fees →

Tips

  • Golden holds a Silver SolSmart designation, meaning the City has committed to streamlined solar permitting — but as of this review it has not published a solar-specific fee sheet or checklist the way some Colorado jurisdictions have; contact the Building Department or Sustainability Coordinator (goldensustainabilty@cityofgolden.gov) directly to confirm current solar-specific requirements before applying.
  • Budget for both a building/valuation-based permit fee and, if applicable, a separate electrical trade permit — Golden's general fee structure (not solar-specific) will apply.

Frequently asked questions

Golden requires a solar pv permit for: Solar Panels are listed as requiring a permit under the Required Building Permits Guide's exterior projects list; No solar-specific application, checklist, or fee schedule is published on the City's Solar Energy Systems page; applicants are directed to the general Building Permit Process page; Follow standard building-permit valuation and, where applicable, electrical-permit requirements (state DORA electrical license plus City of Golden Contractor License). If your project isn't listed, confirm with City of Golden Building Department at (303) 384-8151 before starting work.

In Golden, the published Permit fee — valuation-based (Building Permit Fee Table) is: $25.85 minimum, scaling per valuation tiers. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Golden does not publish a plan-review timeline for this permit. Contact City of Golden Building Department at (303) 384-8151 for current turnaround.

You'll need: Building/Electrical Permit Application (Online Permitting Portal). See the required-documents checklist on this page for details on each.

Golden requires 2 inspection(s) for a solar pv permit, in order: Rough Electrical, Final Inspection. Schedule each through City of Golden Building Department ((303) 384-8151).

Apply through City of Golden Building Department at 911 10th Street, Golden, CO 80401 (Building Department); Planning Department at 1445 10th Street, Golden, CO 80401. Phone: (303) 384-8151, email: building@cityofgolden.net. Office hours: Monday-Friday, general City Hall hours (main line (303) 384-8000); Building Department direct line (303) 384-8151. Official information: https://www.cityofgolden.gov/business/building_construction/building_permit.php.

Golden, Colorado has adopted: 2024 International Building Code (IBC), with local Appendix G (Flood Flrp/flood-resistant construction) and Appendix I (Patio Covers) — City of Golden Building Permit Process page; 2024 International Residential Code (IRC), with local Appendix BE (Radon Control Methods) and Appendix CD (Piping Standards for Various Applications) — City of Golden Building Permit Process page; 2024 International Energy Conservation Code (IECC); 2024 International Fire Code (IFC); 2024 International Existing Buildings Code (IEBC); 2024 International Mechanical Code (IMC); 2024 International Plumbing Code (IPC) — note: Golden uses the International Plumbing Code, not the Uniform Plumbing Code; 2024 International Building Code Appendix K — Administrative Provisions for the National Electrical Code; 2023 National Electrical Code (NEC); Golden Wildfire Resiliency Code (GWRC), adopted by City Ordinance No. 2290 and codified as Chapter 15.80 of the Golden Municipal Code — applies to new construction, significant additions, repairs, and remodels on properties within Golden's designated Wildland-Urban Interface (WUI) areas (per the Official Golden Wildfire Map); establishes fire-resistant construction standards for two hazard classifications, Class I (low fire intensity) and Class II (medium and high fire intensity); enforcement begins June 10, 2026; Golden Municipal Code Title 15, Chapter 15.08 (Building Code) governs local amendments and adoption by reference; Chapter 15.01 (Contractor Registration) governs the city's separate contractor registration requirement. Local amendments apply — see the Golden overview page for the full list.

Golden holds a Silver designation from the national SolSmart Communities program, reflecting streamlined solar permitting practices, but the City has not published a solar-specific application, fee schedule, or review-timeline page distinct from its general Building Permit Process. Confirm current details directly with the Building Department.

Sources & verification

Verified against official sources. Last reviewed 2026-07-05.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Golden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.