Electrical Permit in Berthoud, Colorado

Required for installation, alteration, or repair of electrical systems in Berthoud. Governed by the 2023 NEC as adopted. Electricians must hold an active Colorado State Electrical Board (DORA) license, contemporaneously verified by the Town per its posted HB19-1086/SB19-156 procedure — Berthoud does not run a separate local electrical licensing board, and its own Trade Contractor license fee is explicitly waived for electrical contractors 'per State Statutes.'

Verified 2026-07-06 · Source

When you need this permit

  • Governed by the 2023 NEC as adopted by the Town of Berthoud
  • Electricians must hold a current Colorado State Electrical Board (DORA) license; verified contemporaneously by Town/SAFEbuilt staff at registration per the Town's posted 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' (required under SB19-156 / CRS Title 12 Article 115)
  • A Town of Berthoud Trade Contractor license is required for the business entity, but the Town charges NO separate license fee for Electrical Contractors specifically, per Ordinance No. 1376 Appendix A Contractor
  • Fee calculated either by residential living-area square footage (new living space) or by installation valuation ('All Other')
  • New residential construction and major renovations must satisfy Appendix RM/CK electric-ready and EV-ready provisions (dedicated branch circuits, reserved panel space, required labeling)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential Electrical Fee — new living space, 0 to 1,000 sq ft2026 Schedule of Rates, Charges and Fees; plus $25 Administration + $25 Technology fee where the electrical work is issued as an over-the-counter permit
$100.00
Residential Electrical Fee — 1,001 to 1,500 sq ft
$150.00
Residential Electrical Fee — 1,501 to 2,000 sq ft
$200.00
Residential Electrical Fee — each additional 100 sq ft over 2,000 sq ft
$10.00 per 100 sq ft
All Other Electrical Fee (by valuation) — $1.00 to $2,000.00
$100.00
All Other Electrical Fee (by valuation) — over $2,000.00
$200 + $10 for each additional $1,000 over $2,000
Residential Solar Electrical Fee
$500.00
Nonresidential Solar Electrical Fee (< 2MW)
$1,000.00
Nonresidential Solar Electrical Fee (> 2MW)
Per Table 1-A, 1997 UBC, plus Plan Review
Mobile Home/Travel Trailer Electrical Fee
$150.00 per space
Electrical Re-inspection Fee
$85.00
Temporary Construction Meter
$85.00
Permanent Meter Inspection
$85.00
Electrical Plan Review — Residential
50% of Electrical Permit Fee
Electrical Plan Review — Non-Residential
65% of Electrical Permit Fee
Electrical Violation Fee
2x the permit fee
Electrical Investigation Fee
$150.00 per hour

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit permit actually take in Berthoud?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

See the full Berthoud inspection guide — scheduling & re-inspection fees →

Tips

  • Berthoud does not charge its own Trade Contractor license fee to electrical contractors — Ordinance No. 1376 states this explicitly ('Fee is not charged for Electrical or Plumbing Contractors per State Statutes') — but your Colorado DORA Electrical Board license status IS actively verified by Town/SAFEbuilt staff at registration and via random job-site checks. Contractor
  • Residential solar installations are billed a flat $500 Electrical Fee (not the standard square-footage or valuation tables) — budget accordingly and separately from any Building Permit valuation fee that may also apply to the mounting structure.

Frequently asked questions

Berthoud requires an electrical permit for: Governed by the 2023 NEC as adopted by the Town of Berthoud; Electricians must hold a current Colorado State Electrical Board (DORA) license; verified contemporaneously by Town/SAFEbuilt staff at registration per the Town's posted 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' (required under SB19-156 / CRS Title 12 Article 115); A Town of Berthoud Trade Contractor license is required for the business entity, but the Town charges NO separate license fee for Electrical Contractors specifically, per Ordinance No. 1376 Appendix A; Fee calculated either by residential living-area square footage (new living space) or by installation valuation ('All Other'); New residential construction and major renovations must satisfy Appendix RM/CK electric-ready and EV-ready provisions (dedicated branch circuits, reserved panel space, required labeling). If your project isn't listed, confirm with Town of Berthoud Planning & Building Department at 970-532-2643 (option 3); alt. 970-344-5828 before starting work.

In Berthoud, the published Residential Electrical Fee — new living space, 0 to 1,000 sq ft is: $100.00. Additional published fees: Residential Electrical Fee — 1,001 to 1,500 sq ft — $150.00; Residential Electrical Fee — 1,501 to 2,000 sq ft — $200.00; Residential Electrical Fee — each additional 100 sq ft over 2,000 sq ft — $10.00 per 100 sq ft; All Other Electrical Fee (by valuation) — $1.00 to $2,000.00 — $100.00; All Other Electrical Fee (by valuation) — over $2,000.00 — $200 + $10 for each additional $1,000 over $2,000; Residential Solar Electrical Fee — $500.00; Nonresidential Solar Electrical Fee (< 2MW) — $1,000.00; Nonresidential Solar Electrical Fee (> 2MW) — Per Table 1-A, 1997 UBC, plus Plan Review; Mobile Home/Travel Trailer Electrical Fee — $150.00 per space; Electrical Re-inspection Fee — $85.00; Temporary Construction Meter — $85.00; Permanent Meter Inspection — $85.00; Electrical Plan Review — Residential — 50% of Electrical Permit Fee; Electrical Plan Review — Non-Residential — 65% of Electrical Permit Fee; Electrical Violation Fee — 2x the permit fee; Electrical Investigation Fee — $150.00 per hour. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Berthoud does not publish a plan-review timeline for this permit. Contact Town of Berthoud Planning & Building Department at 970-532-2643 (option 3); alt. 970-344-5828 for current turnaround.

You'll need: Electrical Permit Application (CommunityCore); Colorado State Electrical Board (DORA) License. See the required-documents checklist on this page for details on each.

Berthoud requires 2 inspection(s) for an electrical permit, in order: Rough Electrical, Final Inspection. Schedule each through Town of Berthoud Planning & Building Department (970-532-2643 (option 3); alt. 970-344-5828).

Apply through Town of Berthoud Planning & Building Department at 807 Mountain Ave, Berthoud, CO 80513 (PO Box 1229, Berthoud, CO 80513). Phone: 970-532-2643 (option 3); alt. 970-344-5828, email: building@berthoud.org. Office hours: Main line 970-532-2643 option 3 (fax 970-532-0640). Inspections are performed under contract by SAFEbuilt/ProCode — phone 970-305-3161 ext. 1, online scheduling via the Town's CommunityCore portal; inspection requests must be received by 4 p.m. for next-business-day completion.. Official information: https://www.berthoud.org/169/Building-Department.

Berthoud, Colorado has adopted: 2024 International Building Code (IBC) — Chapters 1-33 and Appendix Chapter I, adopted by reference with local amendments (Berthoud Municipal Code Chapter 11.1); 2024 International Residential Code (IRC) — Chapters 1-43 and Appendix AB, adopted by reference with local amendments (Chapter 11.2). Fee schedule is explicitly keyed to '2024 IRC Appendix AB' as the valuation-based fee table.; 2024 International Existing Building Code (IEBC) — Chapters 1-16 (Chapter 11.3); 2024 International Energy Conservation Code (IECC) — Commercial Chapters 1-6, Residential Chapters 1-6, INCLUDING Appendix CK (Colorado Model Electric and Solar Ready Code — Commercial) and Appendix RM (Colorado Model Electric and Solar Ready Code — Residential) (Chapter 11.4); 2023 National Electrical Code (NEC / NFPA 70) (Chapter 11.5); 2024 International Plumbing Code (IPC) — Chapters 1-13 (Chapter 11.10); 2024 International Mechanical Code (IMC) — Chapters 1-15 (Chapter 11.16); 2024 International Fuel Gas Code (IFGC) — Chapters 1-8 (Chapter 11.17); Colorado State Regulation 86 (Graywater Systems) — Town of Berthoud is the designated local agency for graywater oversight (Chapter 11.18); 2024 International Swimming Pool and Spa Code (ISPSC) — Chapters 1-11 (Chapter 11.19); 2024 International Property Maintenance Code (IPMC) — Chapters 1-8 (Chapter 11.20); HB22-1362 statewide energy code floor: Berthoud's 2024 IECC adoption explicitly incorporates Appendix CK and Appendix RM (the Colorado Energy Office's model Electric Ready / Solar Ready / EV Ready code), satisfying HB22-1362's statewide low-energy/electric-and-solar-ready requirement. Confirmed directly from the Town's own 2024 I-Code Amendment ordinance text (Berthoud Municipal Code Chapter 11.4), not inferred.. Local amendments apply — see the Berthoud overview page for the full list.

No separate Berthoud electrical license/fee exists. Electricians must hold an active Colorado State Electrical Board (DORA) license, which the Town verifies contemporaneously per its posted HB19-1086/SB19-156 procedure. A Town of Berthoud Trade Contractor registration is still required for the business, but Ordinance No. 1376 explicitly waives the Town's own license fee for electrical contractors.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Berthoud building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.