EV Charger / EVSE Installation Permit — Berthoud, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.berthoud.org/DocumentCenter/View/7219/2026-Fee-Schedule
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Installation Permit in Berthoud, Colorado
Berthoud has no distinct EV charger/EVSE permit category or fee line. A retrofit EV charging circuit is billed under the Electrical Permit's general 'All Other' valuation-based fee table. Separately, new residential construction in Berthoud must satisfy the Colorado Model Electric and Solar Ready Code (Appendix RM), which requires a dedicated EV-ready garage circuit even when a charger is not installed at time of construction.
Verified 2026-07-20 · Source
When you need this permit
- A retrofit/standalone EV charger circuit is billed under the Electrical Permit's 'All Other Electrical Fee (by valuation)' table, not the residential square-footage table (which applies only to new living-space wiring) — governed by the 2023 NEC as adopted by the Town of Berthoud
- New residential construction and major renovations must independently satisfy the Colorado Model Electric and Solar Ready Code (Appendix RM/CK): a designated EV-ready garage circuit (dedicated branch circuit, reserved panel space, required labeling) is required even if an EV charger is not being installed at time of construction — confirmed on the Town's own Residential Building Permit entry ('budget for ... an EV-ready garage circuit even if you aren't installing ... an EV charger at time of construction')
- Electricians must hold a current Colorado State Electrical Board (DORA) license, verified contemporaneously by Town/SAFEbuilt staff at registration
- Apply via the Town's online permitting portal (CommunityCore)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical / Final Inspection
Same sequence as any electrical permit: wiring and panel/circuit installed before concealment, then final device/connection verification
See the full Berthoud inspection guide — scheduling & re-inspection fees →
Tips
- Berthoud does not publish a distinct EV charger/EVSE fee line for retrofit installs — apply for a standard electrical permit and it will be billed under the 'All Other Electrical Fee' valuation table.
- For NEW construction specifically, Berthoud's adoption of the Colorado Model Electric and Solar Ready Code (Appendix RM) already mandates an EV-ready garage circuit be roughed in regardless of whether a charger is installed — this is a design requirement baked into the Residential Building Permit, not a separate EV charger permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Berthoud building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Berthoud
EV Charger / EVSE Installation Permit in other cities
Compare ev charger / evse installation permit fees across Colorado →
Look up this fee in a different city →