Required for heating, cooling, and ventilation equipment installation or replacement in Berthoud. Governed by the 2024 International Mechanical Code (IMC) and 2024 International Fuel Gas Code (IFGC) as locally amended.

Verified 2026-07-06 · Source

When you need this permit

  • Governed by the 2024 IMC (Chapters 1-15) and 2024 IFGC (Chapters 1-8) as adopted
  • Plastic fuel gas piping must be buried a minimum of 18 inches below grade; fuel gas test pressure amended to 10 psig (from base code's 3 psig)
  • Contractor must hold a Town of Berthoud Trade Contractor license (Mechanical, ICC G29 pathway) plus any applicable Colorado state trade credential Contractor
  • New buildings/major renovations must provide dedicated electric-ready infrastructure for combustion HVAC equipment per Appendix CK/RM (reserved panel space, labeled circuit, condensate drain provision) even when the primary system is gas-fired

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Mechanical Permit Fee (part of the general valuation-based Building Permit Fee)2026 Schedule of Rates, Charges and Fees
Per the 2024 IRC Appendix AB valuation-based fee table, plus $50 Administration + $50 Technology fee
Air Conditioning (over-the-counter)
$150.00 + $25 Administration + $25 Technology fee
Furnace Replacement (over-the-counter)
$150.00 + $25 Administration + $25 Technology fee
Gas Piping (over-the-counter)
$150.00 + $25 Administration + $25 Technology fee
Hot Water Boiler (over-the-counter)
$150.00 + $25 Administration + $25 Technology fee
Hot Water Heater (over-the-counter)
$150.00 + $25 Administration + $25 Technology fee
Plan Review Fee
65% of Permit Fee

Review timeline

Plan review
Not published — contact the department

How long did your Mechanical / HVAC Permit permit actually take in Berthoud?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

See the full Berthoud inspection guide — scheduling & re-inspection fees →

Tips

  • Air Conditioning, Furnace Replacement, Gas Piping, and Hot Water Boiler/Heater all fall under the Town's 'Over the Counter One-Stop' flat-fee track ($150 base + $25 admin + $25 tech = $200 total each) rather than the full valuation-based Building Permit Fee schedule — this is typically faster and cheaper for straightforward like-for-like replacements.
  • Even a straight gas-furnace replacement in new construction should account for the Electric Ready code's dedicated branch-circuit and panel-space requirements for future electrification, per Appendix RM/CK.

Frequently asked questions

Berthoud requires a mechanical / hvac permit for: Governed by the 2024 IMC (Chapters 1-15) and 2024 IFGC (Chapters 1-8) as adopted; Plastic fuel gas piping must be buried a minimum of 18 inches below grade; fuel gas test pressure amended to 10 psig (from base code's 3 psig); Contractor must hold a Town of Berthoud Trade Contractor license (Mechanical, ICC G29 pathway) plus any applicable Colorado state trade credential; New buildings/major renovations must provide dedicated electric-ready infrastructure for combustion HVAC equipment per Appendix CK/RM (reserved panel space, labeled circuit, condensate drain provision) even when the primary system is gas-fired. If your project isn't listed, confirm with Town of Berthoud Planning & Building Department at 970-532-2643 (option 3); alt. 970-344-5828 before starting work.

Furnace Replacement is billed under the Town's Over-the-Counter One-Stop Fees: $150.00 base permit fee plus a $25 Administration Fee and $25 Technology Fee, for $200.00 total, per the 2026 Schedule of Rates, Charges and Fees.

Berthoud does not publish a plan-review timeline for this permit. Contact Town of Berthoud Planning & Building Department at 970-532-2643 (option 3); alt. 970-344-5828 for current turnaround.

You'll need: Mechanical/Building Permit Application (CommunityCore); Town of Berthoud Trade Contractor License (Mechanical). See the required-documents checklist on this page for details on each.

Berthoud requires 2 inspection(s) for a mechanical / hvac permit, in order: Rough Mechanical, Final Inspection. Schedule each through Town of Berthoud Planning & Building Department (970-532-2643 (option 3); alt. 970-344-5828).

Apply through Town of Berthoud Planning & Building Department at 807 Mountain Ave, Berthoud, CO 80513 (PO Box 1229, Berthoud, CO 80513). Phone: 970-532-2643 (option 3); alt. 970-344-5828, email: building@berthoud.org. Office hours: Main line 970-532-2643 option 3 (fax 970-532-0640). Inspections are performed under contract by SAFEbuilt/ProCode — phone 970-305-3161 ext. 1, online scheduling via the Town's CommunityCore portal; inspection requests must be received by 4 p.m. for next-business-day completion.. Official information: https://www.berthoud.org/169/Building-Department.

Berthoud, Colorado has adopted: 2024 International Building Code (IBC) — Chapters 1-33 and Appendix Chapter I, adopted by reference with local amendments (Berthoud Municipal Code Chapter 11.1); 2024 International Residential Code (IRC) — Chapters 1-43 and Appendix AB, adopted by reference with local amendments (Chapter 11.2). Fee schedule is explicitly keyed to '2024 IRC Appendix AB' as the valuation-based fee table.; 2024 International Existing Building Code (IEBC) — Chapters 1-16 (Chapter 11.3); 2024 International Energy Conservation Code (IECC) — Commercial Chapters 1-6, Residential Chapters 1-6, INCLUDING Appendix CK (Colorado Model Electric and Solar Ready Code — Commercial) and Appendix RM (Colorado Model Electric and Solar Ready Code — Residential) (Chapter 11.4); 2023 National Electrical Code (NEC / NFPA 70) (Chapter 11.5); 2024 International Plumbing Code (IPC) — Chapters 1-13 (Chapter 11.10); 2024 International Mechanical Code (IMC) — Chapters 1-15 (Chapter 11.16); 2024 International Fuel Gas Code (IFGC) — Chapters 1-8 (Chapter 11.17); Colorado State Regulation 86 (Graywater Systems) — Town of Berthoud is the designated local agency for graywater oversight (Chapter 11.18); 2024 International Swimming Pool and Spa Code (ISPSC) — Chapters 1-11 (Chapter 11.19); 2024 International Property Maintenance Code (IPMC) — Chapters 1-8 (Chapter 11.20); HB22-1362 statewide energy code floor: Berthoud's 2024 IECC adoption explicitly incorporates Appendix CK and Appendix RM (the Colorado Energy Office's model Electric Ready / Solar Ready / EV Ready code), satisfying HB22-1362's statewide low-energy/electric-and-solar-ready requirement. Confirmed directly from the Town's own 2024 I-Code Amendment ordinance text (Berthoud Municipal Code Chapter 11.4), not inferred.. Local amendments apply — see the Berthoud overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Berthoud building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.