Building Permit — Addition, Remodel, Deck, Guard Replacement in Dillon, Colorado

Required for additions, remodels, decks, and guard replacements to existing structures in Dillon. Same two-step process as new construction: a Town of Dillon Development Permit first, then the building permit through Summit County Building Inspection Department.

Verified 2026-07-06 · Source

When you need this permit

  • Town of Dillon Development Permit required first — the Town's own guidance explicitly lists 'building additions,' 'remodels,' 'tenant finish,' and 'large sheds' among projects requiring this permit
  • Decks and guard replacements require a Summit County building permit per the department's own Building Permits page
  • Submit in person at the Summit County Building Inspection Department, Frisco office, before 4:30 p.m.
  • Plan review fee of 65% of the building permit fee due at submittal when plans are required
  • Affordable Housing Development Impact Fee applies to additions to existing detached single-family structures at the same tiered rates as new construction

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (same valuation tiers as new construction)Summit County Building Permit Fee Schedule — same table used for new construction, additions, and remodels
$50.00 minimum (valuation $1-$500) up to $6,332.22 for the first $1,000,000 plus $3.90 per additional $1,000
Plan Review Fee
65% of the Building Permit Fee
Affordable Housing Development Impact FeeApplies to new additions to existing detached single-family structures per Summit County's fee schedule
$0/sq ft up to 1,499 sq ft, scaling to $2.00/sq ft at 5,000+ sq ft

Review timeline

Plan review
Not published — contact the department

How long did your Building Permit — Addition, Remodel, Deck, Guard Replacement permit actually take in Dillon?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Framing

    After framing complete, before wall cover

  2. 2

    MEP Rough-In

    If mechanical, electrical, or plumbing work is part of the scope

  3. 3

    Final

    All work complete per approved plans

See the full Dillon inspection guide — scheduling & re-inspection fees →

Tips

  • Window and sliding glass door replacement associated with an existing building permit does not need a separate Window Permit — but replacement NOT tied to an existing building permit does (see the standalone Window Permit on Summit County's site, not modeled separately here as it is a narrow trade-permit variant of this same process).

Frequently asked questions

Dillon requires a building permit — addition, remodel, deck, guard replacement for: Town of Dillon Development Permit required first — the Town's own guidance explicitly lists 'building additions,' 'remodels,' 'tenant finish,' and 'large sheds' among projects requiring this permit; Decks and guard replacements require a Summit County building permit per the department's own Building Permits page; Submit in person at the Summit County Building Inspection Department, Frisco office, before 4:30 p.m.; Plan review fee of 65% of the building permit fee due at submittal when plans are required; Affordable Housing Development Impact Fee applies to additions to existing detached single-family structures at the same tiered rates as new construction. If your project isn't listed, confirm with Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) at (970) 668-3170 before starting work.

In Dillon, the published Building Permit Fee (same valuation tiers as new construction) is: $50.00 minimum (valuation $1-$500) up to $6,332.22 for the first $1,000,000 plus $3.90 per additional $1,000. Additional published fees: Plan Review Fee — 65% of the Building Permit Fee; Affordable Housing Development Impact Fee — $0/sq ft up to 1,499 sq ft, scaling to $2.00/sq ft at 5,000+ sq ft. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Dillon does not publish a plan-review timeline for this permit. Contact Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) at (970) 668-3170 for current turnaround.

You'll need: Town of Dillon Development Permit Application; Building Permit Application (Summit County). See the required-documents checklist on this page for details on each.

Dillon requires 3 inspection(s) for a building permit — addition, remodel, deck, guard replacement, in order: Framing, MEP Rough-In, Final. Schedule each through Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) ((970) 668-3170).

Apply through Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) at County Commons, 0037 Peak One Drive, Frisco, CO 80443. Phone: (970) 668-3170, email: Contact via Email link at summitcountyco.gov/services/community_development/building_inspection/index.php. Office hours: Generally Monday-Friday 8:00 a.m.-5:00 p.m. (Wednesdays 10:00 a.m.-5:00 p.m. — the department is typically unavailable Wednesday mornings until 10:30 a.m. for a weekly staff meeting); Chief Building Official: Glen Morgan. Official information: https://www.summitcountyco.gov/services/community_development/building_inspection/index.php.

Dillon, Colorado has adopted: 2024 International Building Code (IBC) series with local amendments — Summit County Building Inspection Department completed adoption of the 2024 I-Code series; per the department's live announcement (checked 2026-07-06), all plans submitted on or after July 1, 2026 must comply with the 2024 I-Codes; 2024 International Residential Code (IRC) with local amendments — part of the same 2024 I-Code series adoption; 2024 International Energy Conservation Code (IECC) with amendments — replaces the former 'Summit County Sustainable Code' option for single-family homes; the Sustainable Code is no longer an energy-compliance pathway as of this adoption, per the department's own announcement; Appendix REMP (Renewable Energy Mitigation Program) — added with the 2024 code adoption, per Summit County Building Inspection Department announcement; Appendix BC (Accessory Dwelling Units for existing construction) — added with the 2024 code adoption, per Summit County Building Inspection Department announcement; Colorado Wildfire Resiliency Code — any permit applied for on or after May 4, 2026 is subject to the newly adopted fire codes, including the updated sprinkler square-footage threshold; the full code is published by the Colorado Division of Fire Prevention & Control (dfpc.colorado.gov/colorado-wildfire-resiliency-code); Sprinkler requirement: all new residential structures 4,500 sq ft or greater must have fire sprinkler systems installed, per the Colorado Wildfire Resiliency Code as adopted by Summit County; Town of Dillon Municipal Code, Chapter 18 — the Town has, 'in conjunction with Summit County... in general adopted the 2018 series of Building Codes with amendments' at the town-code level; however, the Summit County Building Inspection Department (which actually performs plan review/inspection for Dillon) has since moved forward to the 2024 I-Code series described above — this is a genuine, honestly-flagged discrepancy between the Dillon Municipal Code's own text (last referencing 2018) and the county department's current live practice (2024, effective July 1, 2026); applicants should confirm the currently-enforced edition directly with Summit County Building Inspection at time of submittal. Local amendments apply — see the Dillon overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Dillon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.