Building Permit (New Construction / Foundation, Framing, Finish) in Dillon, Colorado
Required for construction of new single-family homes, foundations, framing, carpentry, and exterior/interior finish work in Dillon. A Town of Dillon Development Permit must be obtained FIRST from the Dillon Planning & Zoning Department; the building permit itself is then issued and inspected by the Summit County Building Inspection Department under the 2024 I-Code series (effective for submittals on or after July 1, 2026).
Verified 2026-07-06 · Source
When you need this permit
- STEP 1 (prerequisite): Obtain a Town of Dillon Development Permit from the Planning & Zoning Department (Ned West, Sr. Town Planner, (970) 262-3421, nwest@townofdillon.com) before applying for the building permit
- STEP 2: Submit the building permit application, plans, and all hard-copy materials IN PERSON to Summit County Building Inspection Department, County Commons, 0037 Peak One Drive, Frisco, CO 80443 — electronic, mailed, or couriered submittals are not accepted; cutoff 4:30 p.m. daily
- Plans submitted on or after July 1, 2026 must comply with the 2024 I-Code series with Summit County amendments (2024 IBC/IRC/IECC, Appendix REMP, Appendix BC)
- Any permit applied for on or after May 4, 2026 must comply with the Colorado Wildfire Resiliency Code, including the updated sprinkler square-footage threshold; new residential structures of 4,500 sq ft or greater require fire sprinkler systems
- Plan review fee (65% of the building permit fee) is due at time of submittal
- Affordable Housing Development Impact Fee applies based on square footage (see localAmendments)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footings
Before concrete pour
- 2
Framing
After framing complete, before insulation or wall cover
- 3
MEP Rough-In
Mechanical, electrical, and plumbing rough-in before walls closed
- 4
Final
All work complete, ready for Certificate of Occupancy
See the full Dillon inspection guide — scheduling & re-inspection fees →
Tips
- Do not apply for a Summit County building permit before securing your Town of Dillon Development Permit — the county will not accept a building-related permit application without it.
- Building permit and technical permit applications must be submitted IN PERSON at the Frisco office; the department does not accept electronic, mailed, or couriered submittals.
- Building inspections can be scheduled online via eTRAKiT once your permit is issued.
- The Building Inspection Department is typically unavailable Wednesday mornings until 10:30 a.m. for a weekly staff meeting — plan in-person submittal visits accordingly.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Dillon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Dillon
Building Permit (New Construction / Foundation, Framing, Finish) in other cities
Compare building permit (new construction / foundation, framing, finish) fees across Colorado →
Look up this fee in a different city →