Commercial Building Permit (including Tenant Improvement / Tenant Finish) — Dillon, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.summitcountyco.gov/services/community_development/building_inspection/building_permit_fee_schedule.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (including Tenant Improvement / Tenant Finish) in Dillon, Colorado
Required for new commercial construction, commercial remodels, and tenant finish/tenant improvement work in Dillon. Same two-agency process as all Dillon building work: a Town of Dillon Development Permit must be issued FIRST by the Dillon Planning & Zoning Department, then the building permit itself is issued and inspected by the Summit County Building Inspection Department (the Town has no building department of its own). Summit County publishes NO separate commercial building permit type — its Building Permits page lists a single 'Building Permit' and its fee schedule applies one valuation-based fee table to all occupancies. Tenant improvement is likewise NOT a distinct county permit type or fee line; 'tenant finish' appears only at the Town level, as one of the named project types requiring a Dillon Development Permit. What IS commercially distinct in Dillon: all commercial and multi-family developments (new or remodel) must be designed in conformance with the Town's adopted Architectural Design Guidelines (2017), which adds a paid design-review step at the Town stage (see fees).
Verified 2026-08-02 · Source
When you need this permit
- STEP 1 (prerequisite): Obtain a Town of Dillon Development Permit via the Town's online Development Application Form — 'tenant finish,' 'remodels,' 'new structures,' and 'buildings' are all explicitly named on the Town's list of projects requiring a Development Permit; Town Staff reviews the application and responds by email with the required Development Permit fee and next steps (contact Ned West, Sr. Town Planner, (970) 262-3421, nwest@townofdillon.com)
- Architectural Design Guidelines conformance (commercial-specific): all commercial and multi-family residential developments, new OR remodel, must be designed in conformance with the Town of Dillon Design Guidelines (2017); the applicant must submit the guideline checklists with a site plan, building elevations, roof plan, and floor plans, and must enter into a cost reimbursement agreement with the Town covering a minimum of one meeting with the Town's architectural consultant
- STEP 2: Submit the building permit application, plans, and all hard-copy materials IN PERSON to Summit County Building Inspection Department, County Commons, 0037 Peak One Drive, Frisco, CO 80443 — electronic, mailed, or couriered submittals are not accepted; submittals not accepted after 4:30 p.m.
- Plans submitted on or after July 1, 2026 must comply with the 2024 I-Code series with Summit County amendments (2024 IBC/IECC et al.); any permit applied for on or after May 4, 2026 is also subject to the Colorado Wildfire Resiliency Code as adopted by Summit County
- Plan review fee (65% of the building permit fee) is due at time of submittal; county plan review is routed through Planning, Engineering, Building Inspection, Environmental Health, and Housing departments
- Affordable Housing Development Impact Fee applies to commercial/industrial structures at a flat $2.00 per square foot (Copper Mountain and Keystone PUD are exempt; Dillon is not listed as exempt)
- Associated plumbing and mechanical permit fees for new commercial projects use a valuation based on 10% of the project's total valuation (x 0.0075, $65.00 minimum each), per the county fee schedule
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footings
Before concrete pour (new construction)
- 2
Framing
After framing complete, before insulation or wall cover
- 3
MEP Rough-In
Mechanical, electrical, and plumbing rough-in before walls closed
- 4
Final
All work complete per approved plans, ready for Certificate of Occupancy
See the full Dillon inspection guide — scheduling & re-inspection fees →
Tips
- Tenant improvement is NOT a separate permit type here — 'tenant finish' is simply one of the named triggers for the Town of Dillon Development Permit, and at the county stage a TI runs through the exact same valuation-based Building Permit as any other commercial work. No TI-specific fee line or process is published at either level, so no separate tenant-improvement entry is modeled for this jurisdiction.
- The commercially distinct step in Dillon is the Town's Architectural Design Guidelines review: every commercial or multi-family project, new or remodel, must submit guideline checklists with site plan, elevations, roof plan, and floor plans, and pay for at least one $500-$800 meeting with the Town's architectural consultant under a cost reimbursement agreement — budget for this before the county permit stage.
- Do not apply to Summit County before your Dillon Development Permit is issued: 'A valid Town of Dillon development permit must be issued before applying for the building related permits' (Town's own page, verified live 2026-08-02).
- Summit County requires in-person submittal at the Frisco office (0037 Peak One Drive) by a representative who can answer submittal questions — no electronic, mailed, or couriered submittals; cutoff 4:30 p.m. The department is typically unavailable Wednesday mornings.
- The commercial Affordable Housing Impact Fee ($2.00/sq ft flat) is steeper at small square footages than the residential tiers, which start at $0/sq ft — factor it into project budgets early.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Dillon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Dillon.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Dillon
Commercial Building Permit (including Tenant Improvement / Tenant Finish) in other cities
Look up this fee in a different city →
Now live
Build your Dillon project checklist
Describe your project once and get every permit, document, and fee it triggers in Dillon — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →