EV Charger / EVSE Permit (Standard Electrical Permit) in Dillon, Colorado

Installation of an electric vehicle charging station in Dillon is not a distinct permit type — it is billed and processed as ordinary electrical work through the Summit County Building Inspection Department's standard Technical Permit Application, the same process and fee schedule documented on this file's electrical-permit entry. Summit County's published Building Permit Fee Schedule (directly fetched and reviewed this session) has NO distinct 'EV charger,' 'electric vehicle,' or 'EVSE' line item; a dedicated Level 2 charger circuit is billed under the same unit-area or valuation-based standalone electrical fee tiers used for any other electrical work. Summit County's Sustainability/Electric Vehicles page (which covers the County's own public charging infrastructure) likewise describes no dedicated EV-charger permitting process, fee, or land-use code, and does not reference Colorado's HB24-1173 (Electric Vehicle Charging System Permits, 2024) despite Summit County's population exceeding that law's 20,000-resident county threshold — no evidence of a HB24-1173-driven adoption of streamlined EV-charging land-use permitting was found published by the County as of this session.

Verified 2026-07-20 · Source

When you need this permit

  • Confirm with Dillon Town Planner Ned West, (970) 262-3421, whether the specific EV charger installation also requires a Town Development Permit (e.g., if bundled with a larger project) — the same check documented on this file's electrical-permit entry
  • Submit the Technical Permit Application in person at the Summit County Building Inspection Department Frisco office, the same form used for all standalone electrical work
  • Confirmed directly against the Summit County Building Permit Fee Schedule: no distinct EV-charger/EVSE fee line exists; a dedicated charger circuit is billed under the standard unit-area (if part of a larger area calculation) or valuation-based 'All other electrical work' tiers
  • Work must comply with the 2024 National Electrical Code series as adopted by Summit County (same code cited on this file's electrical-permit entry)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

All other electrical work — valuation not more than $2,000.00 (typical dedicated EV charger circuit)Summit County Building Permit Fee Schedule — same flat fee already documented on this file's electrical-permit entry; no distinct EV-charger/EVSE line item exists
$146.00
All other electrical work — valuation more than $2,000.00 (e.g., charger install bundled with a panel upgrade)Summit County Building Permit Fee Schedule
$15.00 per $1,000 or fraction thereof plus $146.00
Initial plan reviewSummit County Building Permit Fee Schedule
65% of the electrical permit fee

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit (Standard Electrical Permit) permit actually take in Dillon?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed (if applicable)

  2. 2

    Final

    Charger circuit/unit installed, breaker sized correctly, energized

See the full Dillon inspection guide — scheduling & re-inspection fees →

Tips

  • There is no distinct 'EV charger permit' in Dillon/Summit County — apply for a standard electrical permit via the Technical Permit Application; a dedicated charger circuit under $2,000 in valuation is billed at the flat $146.00 rate.
  • Summit County's population exceeds the 20,000-resident threshold that would trigger mandatory compliance action under Colorado's HB24-1173 (EV Charging System Permits law) by December 31, 2025, but no published County adoption of the state's streamlined EV Charging Model Land Use Code or an opt-out ordinance was found — confirm current status directly with the County before assuming a streamlined process exists.
  • Confirm with the Dillon Town Planner whether your specific project also needs a Town Development Permit before or alongside the Summit County electrical permit.

Frequently asked questions

Dillon requires an ev charger / evse permit (standard electrical permit) for: Confirm with Dillon Town Planner Ned West, (970) 262-3421, whether the specific EV charger installation also requires a Town Development Permit (e.g., if bundled with a larger project) — the same check documented on this file's electrical-permit entry; Submit the Technical Permit Application in person at the Summit County Building Inspection Department Frisco office, the same form used for all standalone electrical work; Confirmed directly against the Summit County Building Permit Fee Schedule: no distinct EV-charger/EVSE fee line exists; a dedicated charger circuit is billed under the standard unit-area (if part of a larger area calculation) or valuation-based 'All other electrical work' tiers; Work must comply with the 2024 National Electrical Code series as adopted by Summit County (same code cited on this file's electrical-permit entry). If your project isn't listed, confirm with Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) at (970) 668-3170 before starting work.

In Dillon, the published All other electrical work — valuation not more than $2,000.00 (typical dedicated EV charger circuit) is: $146.00. Additional published fees: All other electrical work — valuation more than $2,000.00 (e.g., charger install bundled with a panel upgrade) — $15.00 per $1,000 or fraction thereof plus $146.00; Initial plan review — 65% of the electrical permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Dillon does not publish a plan-review timeline for this permit. Contact Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) at (970) 668-3170 for current turnaround.

You'll need: Technical Permit Application (or Technical Permit Application Writeable). See the required-documents checklist on this page for details on each.

Dillon requires 2 inspection(s) for an ev charger / evse permit (standard electrical permit), in order: Rough-In, Final. Schedule each through Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) ((970) 668-3170).

Apply through Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) at County Commons, 0037 Peak One Drive, Frisco, CO 80443. Phone: (970) 668-3170, email: Contact via Email link at summitcountyco.gov/services/community_development/building_inspection/index.php. Office hours: Generally Monday-Friday 8:00 a.m.-5:00 p.m. (Wednesdays 10:00 a.m.-5:00 p.m. — the department is typically unavailable Wednesday mornings until 10:30 a.m. for a weekly staff meeting); Chief Building Official: Glen Morgan. Official information: https://www.summitcountyco.gov/services/community_development/building_inspection/index.php.

Dillon, Colorado has adopted: 2024 International Building Code (IBC) series with local amendments — Summit County Building Inspection Department completed adoption of the 2024 I-Code series; per the department's live announcement (checked 2026-07-06), all plans submitted on or after July 1, 2026 must comply with the 2024 I-Codes; 2024 International Residential Code (IRC) with local amendments — part of the same 2024 I-Code series adoption; 2024 International Energy Conservation Code (IECC) with amendments — replaces the former 'Summit County Sustainable Code' option for single-family homes; the Sustainable Code is no longer an energy-compliance pathway as of this adoption, per the department's own announcement; Appendix REMP (Renewable Energy Mitigation Program) — added with the 2024 code adoption, per Summit County Building Inspection Department announcement; Appendix BC (Accessory Dwelling Units for existing construction) — added with the 2024 code adoption, per Summit County Building Inspection Department announcement; Colorado Wildfire Resiliency Code — any permit applied for on or after May 4, 2026 is subject to the newly adopted fire codes, including the updated sprinkler square-footage threshold; the full code is published by the Colorado Division of Fire Prevention & Control (dfpc.colorado.gov/colorado-wildfire-resiliency-code); Sprinkler requirement: all new residential structures 4,500 sq ft or greater must have fire sprinkler systems installed, per the Colorado Wildfire Resiliency Code as adopted by Summit County; Town of Dillon Municipal Code, Chapter 18 — the Town has, 'in conjunction with Summit County... in general adopted the 2018 series of Building Codes with amendments' at the town-code level; however, the Summit County Building Inspection Department (which actually performs plan review/inspection for Dillon) has since moved forward to the 2024 I-Code series described above — this is a genuine, honestly-flagged discrepancy between the Dillon Municipal Code's own text (last referencing 2018) and the county department's current live practice (2024, effective July 1, 2026); applicants should confirm the currently-enforced edition directly with Summit County Building Inspection at time of submittal. Local amendments apply — see the Dillon overview page for the full list.

No. Summit County's Building Permit Fee Schedule has no distinct EV-charger or EVSE line item. An EV charging station circuit is billed as a standard electrical permit through the Summit County Building Inspection Department — typically the flat $146.00 fee for electrical work valued at $2,000 or less.