Photovoltaic (Solar) Permit — Dillon, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://www.summitcountyco.gov/services/community_development/building_inspection/building_permit_fee_schedule.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Photovoltaic (Solar) Permit in Dillon, Colorado
Required for residential and commercial photovoltaic (solar) system installations in Dillon. A Town of Dillon Development Permit is required first (solar panels are explicitly listed among projects requiring a Development Permit). The Summit County Building Inspection Department then issues the PV permit; residential roof-mounted systems under 15kW may be issued over the counter if the submittal is complete, while larger, ground-mounted, and commercial systems require plan review.
Verified 2026-07-06 · Source
When you need this permit
- Town of Dillon Development Permit required first — solar panels are explicitly named on the Town's list of projects requiring this permit
- Residential roof-mounted PV systems under 15kW may be issued over the counter with a complete submittal
- Plan review is required for all residential PV systems 15kW and over, all ground-mounted systems, and all commercial systems
- Submit the PV Permit Application, PV Submittal Requirements, and PV Checklist materials in person at Summit County Building Inspection Department
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Summit County Building Permit Fee Schedule, Photovoltaic Permit Fees table — RESIDENTIAL PERMIT FEE at $325.00. Show full citationHide
Summit County Building Permit Fee Schedule, Photovoltaic Permit Fees table — RESIDENTIAL PERMIT FEE at $325.00. Summit County publishes two incompatible bases for photovoltaic fees: this flat-fee table, and its Exhibit A/B code-amendment PDF, which instead says to see the electrical valuation table “not to exceed $400.00” residential and “$1,000.00” commercial. Both are current County publications. The flat figures are recorded here because they are the more specific and the ones the fee-schedule page states outright.Summit County Building Permit Fee Schedule, Photovoltaic Permit Fees table — COMMERCIAL PLAN REVIEW at $350.00. Show full citationHide
Summit County Building Permit Fee Schedule, Photovoltaic Permit Fees table — COMMERCIAL PLAN REVIEW at $350.00. Summit County publishes two incompatible bases for photovoltaic fees: this flat-fee table, and its Exhibit A/B code-amendment PDF, which instead says to see the electrical valuation table “not to exceed $400.00” residential and “$1,000.00” commercial. Both are current County publications. The flat figures are recorded here because they are the more specific and the ones the fee-schedule page states outright.Summit County Building Permit Fee Schedule, Photovoltaic Permit Fees table — COMMERCIAL PERMIT FEE at $650.00. Show full citationHide
Summit County Building Permit Fee Schedule, Photovoltaic Permit Fees table — COMMERCIAL PERMIT FEE at $650.00. Summit County publishes two incompatible bases for photovoltaic fees: this flat-fee table, and its Exhibit A/B code-amendment PDF, which instead says to see the electrical valuation table “not to exceed $400.00” residential and “$1,000.00” commercial. Both are current County publications. The flat figures are recorded here because they are the more specific and the ones the fee-schedule page states outright.Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before cover
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, and all electrical connections verified
See the full Dillon inspection guide — scheduling & re-inspection fees →
Tips
- A residential roof-mounted system under 15kW with a fully complete submittal can potentially be issued over the counter — have every required document (application, submittal requirements, checklist) ready to maximize the chance of same-visit issuance.
- Ground-mounted systems always require plan review regardless of system size.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fee schedules
Online permit portal
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Dillon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Dillon's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Dillon yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Dillon lands. Privacy.
Other permits in Dillon
Photovoltaic (Solar) Permit in other cities
Compare photovoltaic (solar) permit fees across Colorado →
Look up this fee in a different city →