Required for residential and commercial photovoltaic (solar) system installations in Dillon. A Town of Dillon Development Permit is required first (solar panels are explicitly listed among projects requiring a Development Permit). The Summit County Building Inspection Department then issues the PV permit; residential roof-mounted systems under 15kW may be issued over the counter if the submittal is complete, while larger, ground-mounted, and commercial systems require plan review.

Verified 2026-07-06 · Source

When you need this permit

  • Town of Dillon Development Permit required first — solar panels are explicitly named on the Town's list of projects requiring this permit
  • Residential roof-mounted PV systems under 15kW may be issued over the counter with a complete submittal
  • Plan review is required for all residential PV systems 15kW and over, all ground-mounted systems, and all commercial systems
  • Submit the PV Permit Application, PV Submittal Requirements, and PV Checklist materials in person at Summit County Building Inspection Department

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential Plan ReviewSummit County Building Permit Fee Schedule
$175.00
Residential Permit Fee
$325.00
Commercial Plan Review
$350.00
Commercial Permit Fee
$650.00

Review timeline

Plan review
Not published — contact the department

How long did your Photovoltaic (Solar) Permit permit actually take in Dillon?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Final

    Panel mounting, racking attachment, roof penetration sealing, and all electrical connections verified

See the full Dillon inspection guide — scheduling & re-inspection fees →

Tips

  • A residential roof-mounted system under 15kW with a fully complete submittal can potentially be issued over the counter — have every required document (application, submittal requirements, checklist) ready to maximize the chance of same-visit issuance.
  • Ground-mounted systems always require plan review regardless of system size.

Frequently asked questions

Dillon requires a photovoltaic (solar) permit for: Town of Dillon Development Permit required first — solar panels are explicitly named on the Town's list of projects requiring this permit; Residential roof-mounted PV systems under 15kW may be issued over the counter with a complete submittal; Plan review is required for all residential PV systems 15kW and over, all ground-mounted systems, and all commercial systems; Submit the PV Permit Application, PV Submittal Requirements, and PV Checklist materials in person at Summit County Building Inspection Department. If your project isn't listed, confirm with Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) at (970) 668-3170 before starting work.

Residential systems are $325.00 for the permit plus $175.00 for plan review; commercial systems are $650.00 for the permit plus $350.00 for plan review, per the Summit County Building Permit Fee Schedule.

Dillon does not publish a plan-review timeline for this permit. Contact Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) at (970) 668-3170 for current turnaround.

You'll need: Town of Dillon Development Permit Application; Photovoltaic Permit Application; PV Submittal Requirements / PV Checklist. See the required-documents checklist on this page for details on each.

Dillon requires 2 inspection(s) for a photovoltaic (solar) permit, in order: Rough Electrical, Final. Schedule each through Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) ((970) 668-3170).

Apply through Summit County Building Inspection Department (performing building-code review/inspection for the Town of Dillon under an intergovernmental services arrangement — not the Town's own department, and not the County's primary unincorporated-area jurisdiction) at County Commons, 0037 Peak One Drive, Frisco, CO 80443. Phone: (970) 668-3170, email: Contact via Email link at summitcountyco.gov/services/community_development/building_inspection/index.php. Office hours: Generally Monday-Friday 8:00 a.m.-5:00 p.m. (Wednesdays 10:00 a.m.-5:00 p.m. — the department is typically unavailable Wednesday mornings until 10:30 a.m. for a weekly staff meeting); Chief Building Official: Glen Morgan. Official information: https://www.summitcountyco.gov/services/community_development/building_inspection/index.php.

Dillon, Colorado has adopted: 2024 International Building Code (IBC) series with local amendments — Summit County Building Inspection Department completed adoption of the 2024 I-Code series; per the department's live announcement (checked 2026-07-06), all plans submitted on or after July 1, 2026 must comply with the 2024 I-Codes; 2024 International Residential Code (IRC) with local amendments — part of the same 2024 I-Code series adoption; 2024 International Energy Conservation Code (IECC) with amendments — replaces the former 'Summit County Sustainable Code' option for single-family homes; the Sustainable Code is no longer an energy-compliance pathway as of this adoption, per the department's own announcement; Appendix REMP (Renewable Energy Mitigation Program) — added with the 2024 code adoption, per Summit County Building Inspection Department announcement; Appendix BC (Accessory Dwelling Units for existing construction) — added with the 2024 code adoption, per Summit County Building Inspection Department announcement; Colorado Wildfire Resiliency Code — any permit applied for on or after May 4, 2026 is subject to the newly adopted fire codes, including the updated sprinkler square-footage threshold; the full code is published by the Colorado Division of Fire Prevention & Control (dfpc.colorado.gov/colorado-wildfire-resiliency-code); Sprinkler requirement: all new residential structures 4,500 sq ft or greater must have fire sprinkler systems installed, per the Colorado Wildfire Resiliency Code as adopted by Summit County; Town of Dillon Municipal Code, Chapter 18 — the Town has, 'in conjunction with Summit County... in general adopted the 2018 series of Building Codes with amendments' at the town-code level; however, the Summit County Building Inspection Department (which actually performs plan review/inspection for Dillon) has since moved forward to the 2024 I-Code series described above — this is a genuine, honestly-flagged discrepancy between the Dillon Municipal Code's own text (last referencing 2018) and the county department's current live practice (2024, effective July 1, 2026); applicants should confirm the currently-enforced edition directly with Summit County Building Inspection at time of submittal. Local amendments apply — see the Dillon overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Dillon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.