Furnace / Water Heater Replacement Permit in Hudson, Colorado

A distinct over-the-counter 'One Stop Permit' category in Hudson for like-for-like furnace/AC and hot water heater replacements, issued within 2 days at a flat fee, separate from the general mechanical/plumbing permit process for new installs.

Verified 2026-07-06 · Source

When you need this permit

  • Qualifies for the Town's One Stop (over-the-counter) Permit track, issued within 2 days
  • Emergency water heater failures (e.g., over a weekend) may be repaired/replaced first with a permit obtained the next business day at standard (non-doubled) fee, per the Town's Building FAQs
  • Non-emergency replacement work performed before permit issuance is subject to double the permit fee

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

One Stop Permit — Hot Water Heater ReplacementSec. 18-19(a); flat fee, over-the-counter, issued within 2 days
$125
One Stop Permit — Furnace/AC Replacement
$125
Working without a required permit (non-emergency)Per the Town's Building FAQs; emergency weekend failures generally exempted if a permit is obtained the next business day
Additional 100% of permit fee (double fee)

Review timeline

Plan reviewHudson’s published plan-review target
2–2 business days

How long did your Furnace / Water Heater Replacement Permit permit actually take in Hudson?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

    Equipment installed and operational per manufacturer instructions and applicable code

See the full Hudson inspection guide — scheduling & re-inspection fees →

Tips

  • If your water heater fails over a weekend, the Town generally allows replacement first with a permit obtained the next business day at the standard (non-doubled) fee — but confirm this with the Building Department at the time, since non-emergency after-the-fact permits are charged double.
  • This is one of the fastest permit categories in Hudson — a flat $125 fee with 2-day issuance for straightforward like-for-like replacements.

Frequently asked questions

Hudson requires a furnace / water heater replacement permit for: Qualifies for the Town's One Stop (over-the-counter) Permit track, issued within 2 days; Emergency water heater failures (e.g., over a weekend) may be repaired/replaced first with a permit obtained the next business day at standard (non-doubled) fee, per the Town's Building FAQs; Non-emergency replacement work performed before permit issuance is subject to double the permit fee. If your project isn't listed, confirm with Town of Hudson Building Department (contracted: ProCode Inc. / SAFEbuilt) at 970-305-3161 (Building Department, ProCode Inc.); 303-536-9311 (Town Hall main line) before starting work.

In Hudson, the published One Stop Permit — Hot Water Heater Replacement is: $125. Additional published fees: One Stop Permit — Furnace/AC Replacement — $125; Working without a required permit (non-emergency) — Additional 100% of permit fee (double fee). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Hudson's published plan-review target for a furnace / water heater replacement permit is 2–2 business days.

You'll need: One Stop Permit Application — Furnace/AC or Water Heater Replacement. See the required-documents checklist on this page for details on each.

Hudson requires 1 inspection(s) for a furnace / water heater replacement permit, in order: Final Inspection. Schedule each through Town of Hudson Building Department (contracted: ProCode Inc. / SAFEbuilt) (970-305-3161 (Building Department, ProCode Inc.); 303-536-9311 (Town Hall main line)).

Apply through Town of Hudson Building Department (contracted: ProCode Inc. / SAFEbuilt) at 50 Beech Street (also published as 50 S. Beech Street / P.O. Box 351), Hudson, CO 80642-0351. Phone: 970-305-3161 (Building Department, ProCode Inc.); 303-536-9311 (Town Hall main line), email: jgesick@procodeinc.net (Jonathan Gesick, Chief Building Official). Office hours: Not separately published for the Building Department on the Town's Building Permits & Inspections page; Town Hall main line 303-536-9311, fax 303-536-4753. Inspection requests: online at www.procodeinc.net/inspections-request or by phone 970-305-3161 ext. 1.. Official information: https://hudsonco.gov/166/Building-Permits-Inspections.

Hudson, Colorado has adopted: 2018 International Building Code (IBC), as codified and amended per Hudson Municipal Code Chapter 18, Article I, Sec. 18-2 (Ord. No. 19-13, 7-3-19) — currently in force per the live Municode-codified chapter; 2018 International Residential Code (IRC), Sec. 18-6 (Ord. No. 19-13, 7-3-19) — currently in force; 2018 International Mechanical Code (IMC), Sec. 18-10 (Ord. No. 19-13, 7-3-19) — currently in force; 2018 International Fuel Gas Code (IFGC), Sec. 18-20 (Ord. No. 19-13, 7-3-19) — currently in force; 2018 International Plumbing Code (IPC), Sec. 18-24 (Ord. No. 19-13, 7-3-19) — currently in force; 2012 International Energy Conservation Code (IECC), Sec. 18-28 (Ord. No. 19-13, 7-3-19) — currently in force per the live-codified chapter, though the Town's own DRAFT 2024 amendments propose replacing this with the 2024 IECC (status: not yet adopted as of this review); 2018 International Property Maintenance Code (IPMC), Sec. 18-32 (Ord. No. 19-13, 7-3-19) — currently in force; 2018 International Existing Building Code (IEBC), Sec. 18-36 (Ord. No. 19-13, 7-3-19) — currently in force; 2018 International Swimming Pool and Spa Code (ISPSC), Sec. 18-40 (Ord. No. 19-13, 7-3-19) — currently in force; National Electrical Code: no locally adopted NEC edition found in Chapter 18; IPMC Section 604.2 as amended defers to 'the Electrical Code adopted by the State of Colorado' rather than naming a specific NEC edition — electrical work in Hudson is administered under the Colorado State Electrical Board framework (see localAmendments); IMPORTANT STATUS NOTE — code edition transition in progress but NOT yet finalized: the Town's live Building Permits & Inspections page (hudsonco.gov/166/Building-Permits-Inspections) states the Town 'will adopt the 2024 ICC codes beginning June 2026, including Solar and EV-ready provisions,' and the Town has posted a document titled 'DRAFT 2024 Building Code Amendments' (DocumentCenter View/6523) proposing 2024 editions of IBC/IRC/IMC/IFGC/IPC/IECC(2024)/IPMC/IEBC/ISPSC plus a new Colorado Model Electric and Solar Ready Code, 2023 Edition (Title 31, Article 16, Part 2, C.R.S.) as Sec. 18-43. However, that document is watermarked 'DRAFT' throughout (dated 4/02/2026) and the live, currently-codified Municode text of Chapter 18 (confirmed via search-engine cache of library.municode.com/co/hudson, page directly 403'd to automated fetch) still shows the 2018/2012 editions listed above as being in force via Ord. No. 19-13. Per this project's zero-tolerance policy, the 2024 suite is NOT recorded as adopted until a signed ordinance/Municode update is confirmed; codesAdopted above reflects the current in-force 2018/2012 baseline, with this note flagging the pending transition for the next verification pass.; Separately, the Hudson Fire Protection District (HFPD) — an independent special district, not a Town department — has its own fire-code adoption process. The Town's live Building page states 'The Hudson Fire Protection District Board has adopted the 2024 IFC amendments, with draft documents available for review,' and a scanned board resolution (DocumentCenter View/6549, '2024-IFC-Adoption-Board-Resolution', a Konica Minolta scan dated April 2026) is posted. The underlying scanned PDF could not be OCR'd/text-extracted directly during this research pass (image-only scan, no embedded text layer) and the HFPD's own website (hfpdco.org) does not independently confirm a specific in-force IFC edition on the pages checked. Treated as partial confidence: an HFPD board resolution exists and the Town references it as adopted, but the specific currently-effective IFC edition enforced Town-wide could not be independently corroborated beyond the Town's own page summary.. Local amendments apply — see the Hudson overview page for the full list.

Generally yes for genuine emergencies, per the Town's Building FAQs. Non-emergency work performed before permit issuance is charged double the standard permit fee.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hudson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.