Solar (Rooftop PV) Permit in Hudson, Colorado

Required for photovoltaic solar installations in Hudson, billed under a dedicated PV Solar fee tier distinct from the general electrical fee schedule. The Town's live Building page notes the pending 2024 code adoption will include 'Solar and EV-ready provisions' via the Colorado Model Electric and Solar Ready Code, 2023 Edition (still in draft/proposal status as of this review).

Verified 2026-07-20 · Source

When you need this permit

  • Listed under the Town's Permits and Licenses residential application categories ('Solar installations and energy compliance certificates')
  • Billed under a dedicated PV Solar fee tier (Residential/Commercial) distinct from the general 'All Other' electrical fee schedule
  • Electrical contractors performing PV interconnection work must hold a current Colorado state electrical license
  • The Colorado Model Electric and Solar Ready Code, 2023 Edition (HB22-1362 implementing framework) is drafted for local adoption as new Sec. 18-43/18-44 but not yet confirmed adopted in the live-codified Municode chapter as of this review

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

PV Solar — ResidentialBuilding Permit Fees handout (updated 3/27/2025). Re-confirmed 2026-07-20 by re-downloading the live document directly and extracting its text, which still reads verbatim 'PV Solar Residential - $500, PV Solar Commercial < 2MW - $1,000' — this figure exactly matches Colorado's statewide solar-permit fee ceiling (C.R.S. 24-48.5-113, extended through 12-31-2029 by HB21-1284: aggregate solar permit fees capped at $500 residential / $1,000 nonresidential under 2MW), confirming Hudson has adopted the statutory maximum as its flat rate rather than a lower locally-set figure.
$500
PV Solar — Commercial, under 2MW
$1,000
PV Solar — Commercial, over 2MW
$2,000 plus $10 per each additional $2,000 of valuation over $2,000, plus 60% Plan Review Fee

Review timeline

Plan review
Not published — contact the department

How long did your Solar (Rooftop PV) Permit permit actually take in Hudson?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical interconnection verified

See the full Hudson inspection guide — scheduling & re-inspection fees →

Tips

  • Hudson prices residential solar PV as a flat $500 fee, separate from both the general valuation-based Building Permit Fee and the square-footage-based residential electrical fee tiers.
  • Watch for the Town's pending 2024 code cycle, which is expected to formally incorporate the Colorado Model Electric and Solar Ready Code, 2023 Edition (the state's HB22-1362 implementing code) — this may add EV-charging-readiness requirements to future solar/electrical-adjacent permits once finalized.

Frequently asked questions

Hudson requires a solar (rooftop pv) permit for: Listed under the Town's Permits and Licenses residential application categories ('Solar installations and energy compliance certificates'); Billed under a dedicated PV Solar fee tier (Residential/Commercial) distinct from the general 'All Other' electrical fee schedule; Electrical contractors performing PV interconnection work must hold a current Colorado state electrical license; The Colorado Model Electric and Solar Ready Code, 2023 Edition (HB22-1362 implementing framework) is drafted for local adoption as new Sec. 18-43/18-44 but not yet confirmed adopted in the live-codified Municode chapter as of this review. If your project isn't listed, confirm with Town of Hudson Building Department (contracted: ProCode Inc. / SAFEbuilt) at 970-305-3161 (Building Department, ProCode Inc.); 303-536-9311 (Town Hall main line) before starting work.

A flat $500 fee for residential PV Solar installations, per the Town's current Building Permit Fees handout — separate from the standard electrical fee schedule.

Hudson does not publish a plan-review timeline for this permit. Contact Town of Hudson Building Department (contracted: ProCode Inc. / SAFEbuilt) at 970-305-3161 (Building Department, ProCode Inc.); 303-536-9311 (Town Hall main line) for current turnaround.

You'll need: Electrical/Building Permit Application — Solar PV scope. See the required-documents checklist on this page for details on each.

Hudson requires 2 inspection(s) for a solar (rooftop pv) permit, in order: Rough Electrical, Final Inspection. Schedule each through Town of Hudson Building Department (contracted: ProCode Inc. / SAFEbuilt) (970-305-3161 (Building Department, ProCode Inc.); 303-536-9311 (Town Hall main line)).

Apply through Town of Hudson Building Department (contracted: ProCode Inc. / SAFEbuilt) at 50 Beech Street (also published as 50 S. Beech Street / P.O. Box 351), Hudson, CO 80642-0351. Phone: 970-305-3161 (Building Department, ProCode Inc.); 303-536-9311 (Town Hall main line), email: jgesick@procodeinc.net (Jonathan Gesick, Chief Building Official). Office hours: Not separately published for the Building Department on the Town's Building Permits & Inspections page; Town Hall main line 303-536-9311, fax 303-536-4753. Inspection requests: online at www.procodeinc.net/inspections-request or by phone 970-305-3161 ext. 1.. Official information: https://hudsonco.gov/166/Building-Permits-Inspections.

Hudson, Colorado has adopted: 2018 International Building Code (IBC), as codified and amended per Hudson Municipal Code Chapter 18, Article I, Sec. 18-2 (Ord. No. 19-13, 7-3-19) — currently in force per the live Municode-codified chapter; 2018 International Residential Code (IRC), Sec. 18-6 (Ord. No. 19-13, 7-3-19) — currently in force; 2018 International Mechanical Code (IMC), Sec. 18-10 (Ord. No. 19-13, 7-3-19) — currently in force; 2018 International Fuel Gas Code (IFGC), Sec. 18-20 (Ord. No. 19-13, 7-3-19) — currently in force; 2018 International Plumbing Code (IPC), Sec. 18-24 (Ord. No. 19-13, 7-3-19) — currently in force; 2012 International Energy Conservation Code (IECC), Sec. 18-28 (Ord. No. 19-13, 7-3-19) — currently in force per the live-codified chapter, though the Town's own DRAFT 2024 amendments propose replacing this with the 2024 IECC (status: not yet adopted as of this review); 2018 International Property Maintenance Code (IPMC), Sec. 18-32 (Ord. No. 19-13, 7-3-19) — currently in force; 2018 International Existing Building Code (IEBC), Sec. 18-36 (Ord. No. 19-13, 7-3-19) — currently in force; 2018 International Swimming Pool and Spa Code (ISPSC), Sec. 18-40 (Ord. No. 19-13, 7-3-19) — currently in force; National Electrical Code: no locally adopted NEC edition found in Chapter 18; IPMC Section 604.2 as amended defers to 'the Electrical Code adopted by the State of Colorado' rather than naming a specific NEC edition — electrical work in Hudson is administered under the Colorado State Electrical Board framework (see localAmendments); IMPORTANT STATUS NOTE — code edition transition in progress but NOT yet finalized: the Town's live Building Permits & Inspections page (hudsonco.gov/166/Building-Permits-Inspections) states the Town 'will adopt the 2024 ICC codes beginning June 2026, including Solar and EV-ready provisions,' and the Town has posted a document titled 'DRAFT 2024 Building Code Amendments' (DocumentCenter View/6523) proposing 2024 editions of IBC/IRC/IMC/IFGC/IPC/IECC(2024)/IPMC/IEBC/ISPSC plus a new Colorado Model Electric and Solar Ready Code, 2023 Edition (Title 31, Article 16, Part 2, C.R.S.) as Sec. 18-43. However, that document is watermarked 'DRAFT' throughout (dated 4/02/2026) and the live, currently-codified Municode text of Chapter 18 (confirmed via search-engine cache of library.municode.com/co/hudson, page directly 403'd to automated fetch) still shows the 2018/2012 editions listed above as being in force via Ord. No. 19-13. Per this project's zero-tolerance policy, the 2024 suite is NOT recorded as adopted until a signed ordinance/Municode update is confirmed; codesAdopted above reflects the current in-force 2018/2012 baseline, with this note flagging the pending transition for the next verification pass.; Separately, the Hudson Fire Protection District (HFPD) — an independent special district, not a Town department — has its own fire-code adoption process. The Town's live Building page states 'The Hudson Fire Protection District Board has adopted the 2024 IFC amendments, with draft documents available for review,' and a scanned board resolution (DocumentCenter View/6549, '2024-IFC-Adoption-Board-Resolution', a Konica Minolta scan dated April 2026) is posted. The underlying scanned PDF could not be OCR'd/text-extracted directly during this research pass (image-only scan, no embedded text layer) and the HFPD's own website (hfpdco.org) does not independently confirm a specific in-force IFC edition on the pages checked. Treated as partial confidence: an HFPD board resolution exists and the Town references it as adopted, but the specific currently-effective IFC edition enforced Town-wide could not be independently corroborated beyond the Town's own page summary.. Local amendments apply — see the Hudson overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hudson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.