Skip to main content
PermitBase

Hudson building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Hudson, Colorado.

Verified 2026-07-23 · Source

How to schedule

Inspections are requested through the building department below.

Address
50 Beech Street (also published as 50 S. Beech Street / P.O. Box 351), Hudson, CO 80642-0351
Phone
970-305-3161 (Building Department, ProCode Inc.); 303-536-9311 (Town Hall main line)
Office hours
Not separately published for the Building Department on the Town's Building Permits & Inspections page; Town Hall main line 303-536-9311, fax 303-536-4753. Inspection requests: online at www.procodeinc.net/inspections-request or by phone 970-305-3161 ext. 1.

Published scheduling rules

  • If your water heater fails over a weekend, the Town generally allows replacement first with a permit obtained the next business day at the standard (non-doubled) fee — but confirm this with the Building Department at the time, since non-emergency after-the-fact permits are charged double. (Furnace / Water Heater Replacement Permit)
  • Emergency water heater failures (e.g., over a weekend) may be repaired/replaced first with a permit obtained the next business day at standard (non-doubled) fee, per the Town's Building FAQs (Furnace / Water Heater Replacement Permit)
  • Working without a required permit costs double the standard permit fee if discovered after the fact (100% additional per Sec. 18-4(a)(8)/18-4(b)(5)) — though genuine emergencies (e.g., a weekend water heater failure) are generally allowed to proceed first if a permit is obtained the next business day. (General)

Inspection sequence

Applies to: Residential Addition / Basement Finish / Interior Remodel Permit

  1. 1

    Foundation (additions with new footings only)

    Before concrete pour

  2. 2

    Rough Frame

    Framing complete, connection to existing structure verified

  3. 3

    Insulation

    Following wall/ceiling/floor insulation and window installation, before wall coverings

  4. 4

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  5. 5

    Final Inspection

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Before concrete pour, per 30-inch minimum frost line depth

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Insulation

    Following installation of wall, ceiling, and floor insulation and exterior windows, before wall coverings are installed (IRC Sec. R110.3.9.1 as amended)

  4. 4

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  5. 5

    Final Inspection

    All work complete per approved plans and applicable codes; final drainage certificate submitted before certificate of occupancy

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Before concrete pour, if the ADU is a new structure

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Rough Frame / Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  2. 2

    Fire/Life Safety

    Fire Department review of kitchen/life-safety systems where a Fire Department Fact Sheet was required

  3. 3

    Final Inspection

    All work complete per approved plans, Certificate of Occupancy issued if applicable

Applies to: Deck / Patio Permit

  1. 1

    Footing/Foundation

    Before concrete pour, per 30-inch minimum frost line depth

  2. 2

    Framing

    Ledger attachment, joists, posts, and guardrail framing before decking installed

  3. 3

    Final Inspection

    Decking, guardrails, and stairs complete per approved plans

Applies to: Demolition Permit

  1. 1

    Pre-Demolition (utility disconnect verification)

    Confirms utilities disconnected before demolition

  2. 2

    Final Inspection

    Site cleared/graded per approved scope

Applies to: Electric Vehicle (EV) Charger / EVSE Permit

  1. 1

    Rough Electrical

    Circuit/conduit and disconnect placement before concealment, if applicable

  2. 2

    Final Inspection

    Charger mounted, circuit labeled, GFCI/breaker protection and disconnect verified per NEC Article 625 (EV charging equipment)

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment (for new-install scopes)

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment; DWV systems tested by water or air with no evidence of leakage per IPC Sec. 2503.5.1 as amended

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: Solar (Rooftop PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical interconnection verified

Re-inspection fees

Electrical PermitElectrical Re-Inspection Fee
$150

Hudson building permits

Get alerts for Hudson

We'll email you when Hudson's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.