Plumbing Permit in Hudson, Colorado
Required for installation, alteration, or repair of plumbing systems in Hudson, billed under the Town's general valuation-based Building Permit Fee (no standalone locally-published plumbing fee schedule was found, unlike electrical which follows the state schedule). Governed by the 2018 International Plumbing Code (IPC) as locally amended. Plumbing contractors must hold a current Colorado state license, verified at permit acceptance.
Verified 2026-07-23 · Source
When you need this permit
- Governed by the 2018 IPC as adopted and amended by Hudson Municipal Code Chapter 18, Sec. 18-24 through 18-27
- Contractors must hold a current Colorado state plumbing contractor license, verified by the Town at permit acceptance per the Building FAQs Contractor
- Sewer depth per IPC Sec. 305.4.1 as amended: 12 inches minimum
- Roof extension per IPC Sec. 903.1.1 as amended: 12-inch minimum insertion dimension
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment; DWV systems tested by water or air with no evidence of leakage per IPC Sec. 2503.5.1 as amended
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
See the full Hudson inspection guide — scheduling & re-inspection fees →
Tips
- Unlike electrical permits, Hudson does not publish a standalone plumbing fee schedule — plumbing work is billed under the same general valuation-based Building Permit Fee used for building/mechanical work, confirmed against both the 2024 handout and the current 2026 Fee Schedule.
- Confirm your plumbing contractor's Colorado state license is current; the Town verifies licensing status at permit acceptance, consistent with statewide contemporaneous-review requirements.
- Sanitary sewer and water line repairs are treated as an Over-the-Counter/One-Stop item (2-day issuance) per the Town's live Building Permits page, distinct from new plumbing installs/alterations bundled into a larger construction permit, which follow the standard 1-2 week review track.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hudson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Hudson
Plumbing Permit in other cities
Compare plumbing permit fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Hudson project checklist
Describe your project once and get every permit, document, and fee it triggers in Hudson — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →