Plumbing Permit in Kersey, Colorado

Required for installation, alteration, or repair of plumbing systems in Kersey. No local plumbing licensing or registration program is published by the Town; plumbing contractor licensing is assessed as deferring to the Colorado State Plumbing Board (DORA/DPO) by default, consistent with Colorado's framework for small municipalities without their own certified plumbing licensing program.

Reviewed 2026-07-06 · Source

When you need this permit

  • A permit is required anytime work involves the plumbing system, per the Town's general permitting FAQ
  • Underground plumbing inspection required prior to covering any piping and prior to placing concrete
  • No Kersey-specific local plumbing contractor licensing/registration document was found (unlike the Town's explicit Electrical License Contemporaneous Review Guidelines) — Colorado State Plumbing Board (DORA) licensure is assumed to govern by default. RE-CHASED 2026-07-23: confirmed DORA's live Plumbing Board page (dpo.colorado.gov/Plumbing) is the correct current statewide licensing authority; re-checked both live fee schedule PDFs directly — still no Kersey-specific plumbing licensing document or standalone plumbing fee line exists in either. The 'default to state licensure' framing remains an inference, not a Kersey-stated fact, because no Kersey document was found addressing plumbing licensing in as many words.

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plumbing Permit FeeThe Development Fee Schedule and 2026 Fee Schedule bundle plumbing/water/sewer inspection fees ($40 Water Inspection Fee, $40 Sewer Inspection Fee in the worked example) within the overall Building Permit Fee rather than publishing a standalone plumbing fee schedule
Not separately broken out in either published fee document

Review timeline

Plan review
Not published — contact the department

How long did your Plumbing Permit permit actually take in Kersey?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Underground Plumbing

    Before covering piping/wiring and before concrete placement

  2. 2

    Rough Plumbing

    Part of the combined Rough Trade inspection, before concealment

  3. 3

    Final Inspection

See the full Kersey inspection guide — scheduling & re-inspection fees →

Tips

  • Kersey does not publish a standalone plumbing licensing guideline the way it does for electrical — confirm with the Building Department/SAFEbuilt (970-686-7511) whether a specific plumbing license verification step applies to your project before assuming it mirrors the electrical contemporaneous-review process.

Frequently asked questions

Kersey requires a plumbing permit for: A permit is required anytime work involves the plumbing system, per the Town's general permitting FAQ; Underground plumbing inspection required prior to covering any piping and prior to placing concrete; No Kersey-specific local plumbing contractor licensing/registration document was found (unlike the Town's explicit Electrical License Contemporaneous Review Guidelines) — Colorado State Plumbing Board (DORA) licensure is assumed to govern by default. RE-CHASED 2026-07-23: confirmed DORA's live Plumbing Board page (dpo.colorado.gov/Plumbing) is the correct current statewide licensing authority; re-checked both live fee schedule PDFs directly — still no Kersey-specific plumbing licensing document or standalone plumbing fee line exists in either. The 'default to state licensure' framing remains an inference, not a Kersey-stated fact, because no Kersey document was found addressing plumbing licensing in as many words.. If your project isn't listed, confirm with Town of Kersey Building Inspection Department (building inspection services contracted to SAFEbuilt Colorado, Windsor Office) at 970-353-1681 before starting work.

In Kersey, the published Plumbing Permit Fee is: Not separately broken out in either published fee document. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Kersey does not publish a plan-review timeline for this permit. Contact Town of Kersey Building Inspection Department (building inspection services contracted to SAFEbuilt Colorado, Windsor Office) at 970-353-1681 for current turnaround.

You'll need: Plumbing Permit Application. See the required-documents checklist on this page for details on each.

Kersey requires 3 inspection(s) for a plumbing permit, in order: Underground Plumbing, Rough Plumbing, Final Inspection. Schedule each through Town of Kersey Building Inspection Department (building inspection services contracted to SAFEbuilt Colorado, Windsor Office) (970-353-1681).

Apply through Town of Kersey Building Inspection Department (building inspection services contracted to SAFEbuilt Colorado, Windsor Office) at 446 1st Street, P.O. Box 657, Kersey, CO 80644. Phone: 970-353-1681, email: kdamrell@kerseygov.com. Office hours: Not published on the Town of Kersey website (Building Inspection Department page, Administration Department page, or building permit how-to page were all checked directly). Town Hall main line 970-353-1681; SAFEbuilt Windsor office line 970-686-7511 (cited on the Town's Current Building Regulations page for building-code clarification); SAFEbuilt inspection requests may also be emailed to windsor@safebuilt.com per the Town's Re-Roofing guide.. Official information: https://www.kerseygov.com/departments/building_inspection_department/index.php.

Kersey, Colorado has adopted: 2024 International Residential Code (IRC) — actively cited as the current adopted code on all nine of the Town's SAFEbuilt-published 'Building Guides for Homeowners' (Additions, Accessory Structures, Re-Roofing, Basement Finish, Decks, Patio Covers/Carports, Window Replacement, Pole Barns, Swimming Pools), each stamped 'Document published by SAFEbuilt, Inc. 1.1.2026' and headed '2024 IRC' — these are the Town's most recently updated, actively maintained permitting documents (site-wide document-center timestamps show a 2026-03-30 publish date).; 2020 National Electrical Code (NEC) — per the Town's Planning Department 'Current Building Regulations' page, which references a '2020 NEC - Significant Changes Residential Electrical' resource alongside the Municipal Code Chapter 18 structure.; RESOLVED 2026-07-23 (live primary source, Municode Library, library.municode.com/co/kersey, Kersey Municipal Code 'VERSION: OCT 23, 2025 (CURRENT)', codified through Ordinance No. 2025-0008 enacted 6/10/2025): the Municipal Code's own home page lists 'Adopted Ordinances Not Yet Codified,' including Ordinance No. 2025-0010, adopted 9/9/2025, titled verbatim 'AN ORDINANCE ADOPTING BY REFERENCE THE INTERNATIONAL BUILDING CODE, 2024 EDITION, THE INTERNATIONAL RESIDENTIAL CODE, 2024 EDITION, THE INTERNATIONAL FUEL GAS CODE, 2024 EDITION, THE INTERNATIONAL PLUMBING CODE, 2024 EDITION, THE INTERNATIONAL MECHANICAL CODE, 2024 EDITION, THE INTERNATIONAL EXISTING BUILDING CODE, 2024 EDITION, THE INTERNATIONAL PROPERTY MAINTENANCE CODE, 2024 EDITION, THE INTERNATIONAL SWIMMING POOL and SPA CODE, 2024 EDITION, AND THE INTERNATIONAL ENERGY CONSERVATION CODE, 2024 EDITION, PROMULGATED BY THE INTERNATIONAL CODE COUNCIL.' This is a real, dated, numbered ordinance (not a guess or inference) and directly confirms the SAFEbuilt-published '2024 IRC' guides were current and correct — the Town has adopted 2024 editions of IBC, IRC, IFGC, IPC, IMC, IEBC, IPMC, ISPSC, and IECC, superseding the 2018/2012 editions still shown in Chapter 18's currently-codified section text (Sec. 18-19 Building Code = 2018 IBC, Sec. 18-44 Residential Code = 2018 IRC, Sec. 18-64 Mechanical Code = 2018 IMC, Sec. 18-89 Fuel Gas Code = 2018 IFGC, Sec. 18-109 Plumbing Code = 2018 IPC, Sec. 18-134 Energy Conservation Code = 2012 IECC, Sec. 18-154 Property Maintenance Code = 2018 IPMC, Sec. 18-179 Existing Building Code = 2018 IEBC) — those codified sections simply have not yet been updated in Municode's online supplement to reflect the 9/9/2025 ordinance, exactly as the Municode banner itself discloses ('This Code of Ordinances... may not reflect the most current legislation adopted by the Municipality'). Notably, Ordinance No. 2025-0010's list does NOT include the International Fire Code — Article X (Sec. 18-199, adopted separately by Ordinance No. 2021-0001) remains the 2018 International Fire Code with no 2024-edition update found. Per this corpus's practice of treating the more current, actively-distributed and now ordinance-confirmed source as authoritative, this file treats IBC/IRC/IFGC/IPC/IMC/IEBC/IPMC/ISPSC as 2024 editions (per Ord. No. 2025-0010, 9/9/2025) and IFC as the 2018 edition (per Ord. No. 2021-0001, 1/12/2021, locally amended by Sec. 18-200) — the prior 'partial' flag on the non-residential code editions is resolved.; HB22-1362 (Colorado statewide energy code floor, 2021 IECC + electric/solar/EV-ready provisions, effective window July 2023-July 2026): RESOLVED IN PART 2026-07-23 — Municode confirms Chapter 18, Article VII (Sec. 18-134) currently codifies the 2012 IECC (not the ambiguous, undated 'Energy Conservation Code' the static Current Building Regulations page implied), and the same live Ordinance No. 2025-0010 (adopted 9/9/2025, not yet codified) adopts by reference the 2024 IECC, which post-dates and satisfies HB22-1362's 2021-IECC-floor requirement. The Home Additions guide's instruction to submit an 'Energy Code Compliance Report (www.energycodes.gov) or REScheck calculations' is consistent with 2024 IECC compliance documentation but still does not itself name an edition year — the 2024 IECC edition-year figure comes from the Ordinance 2025-0010 citation above, not from the SAFEbuilt guide.. Local amendments apply — see the Kersey overview page for the full list.

No local plumbing licensing or registration program was found published by the Town. Plumbing contractor licensing is expected to default to the Colorado State Plumbing Board (DORA/DPO), consistent with Colorado's default framework for municipalities without their own certified plumbing board, though this was not stated in as many words by the Town itself.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kersey building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.