Rooftop Solar Photovoltaic Permit — Kersey, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.kerseygov.com/departments/building_inspection_department/index.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Rooftop Solar Photovoltaic Permit in Kersey, Colorado
Required for rooftop or ground-mounted solar photovoltaic installations within the Town of Kersey. Building inspection services are contracted to SAFEbuilt Colorado (Windsor Office), which reviews plans and calculates permit fees using the Uniform Building Code (UBC) valuation-based fee schedule — the same worked-example mechanism documented in this file's Development Fee Schedule (Building Fee, 20% Town Surcharge, 30% Plan Review, Use Tax) applies to a solar installation's declared valuation. No separate flat solar-specific fee line was found published. Colorado's statewide solar-fee cap (C.R.S. § 24-48.5-113, $500 residential/$1,000 commercial via HB21-1284) applies as a ceiling regardless of the SAFEbuilt-calculated amount.
Verified 2026-07-20 · Source
When you need this permit
- Building permit required for the structural/mounting portion of a solar PV installation, processed through the Town's Community Core online portal (app.communitycore.com) after contractor/applicant registration, per SAFEbuilt's standard process
- Electrical contractor licensure is verified against the Colorado Department of Regulatory Agencies (DORA) License Lookup per the Town's Electrical License Contemporaneous Review Guidelines — Kersey defers electrical contractor licensing entirely to the Colorado State Electrical Board (DORA)
- Fee calculated using the UBC valuation-based schedule administered by SAFEbuilt, the same mechanism used for the Town's general Building Permit (Building Fee + 20% Town Surcharge + 30% Plan Review + Use Tax), applied to the solar project's declared valuation
- Colorado's statewide C.R.S. § 24-48.5-113 (HB21-1284) caps the aggregate of all fees a local government may charge to install an active solar energy system at $500 for a residential permit and $1,000 for a commercial permit, applying as a ceiling on the SAFEbuilt-calculated fee
- Use Tax of 3.0% of 50% of the value of construction materials (effectively 1.5% of total construction value) applies to the materials cost of the solar installation, per the Town's Development Fee Schedule and 2026 Fee Schedule
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing (ground-mount) or Framing (rooftop racking)
Structural attachment verified before panels are installed, per SAFEbuilt's standard inspection sequence
- 2
Final Electrical/Interconnection
Interconnection wiring verified; electrical contractor licensure re-checked against DORA's License Lookup per the Town's Electrical License Contemporaneous Review Guidelines
See the full Kersey inspection guide — scheduling & re-inspection fees →
Tips
- Kersey has no separate solar fee schedule — the same SAFEbuilt-administered UBC valuation formula (Building Fee + 20% Town Surcharge + 30% Plan Review + Use Tax) used for the Town's general Building Permit applies to a solar project's declared valuation.
- Colorado's statewide $500 residential / $1,000 commercial solar-fee cap (C.R.S. § 24-48.5-113) applies as a ceiling on whatever the SAFEbuilt UBC-based calculation produces.
- Verify your electrician's license is active on DORA's online License Lookup before starting work — Kersey's Building Inspectors may request to verify the identity/licensure of the electrician performing the interconnection at any inspection.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kersey building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Kersey
Rooftop Solar Photovoltaic Permit in other cities
Compare rooftop solar photovoltaic permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Kersey project checklist
Describe your project once and get every permit, document, and fee it triggers in Kersey — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →