Rooftop Solar Photovoltaic Permit — Kersey, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.kerseygov.com/departments/building_inspection_department/index.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Rooftop Solar Photovoltaic Permit in Kersey, Colorado
Required for rooftop or ground-mounted solar photovoltaic installations within the Town of Kersey. Building inspection services are contracted to SAFEbuilt Colorado (Windsor Office), which reviews plans and calculates permit fees using the Uniform Building Code (UBC) valuation-based fee schedule — the same worked-example mechanism as the Town's Development Fee Schedule (Building Fee, 20% Town Surcharge, 30% Plan Review, Use Tax) applies to a solar installation's declared valuation. No separate flat solar-specific fee line is published. Colorado's statewide solar-fee cap (C.R.S. § 24-48.5-113, $500 residential/$1,000 commercial via HB21-1284) applies as a ceiling regardless of the SAFEbuilt-calculated amount.
Verified 2026-07-20 · Source
When you need this permit
- Building permit required for the structural/mounting portion of a solar PV installation, processed through the Town's Community Core online portal (app.communitycore.com) after contractor/applicant registration, per SAFEbuilt's standard process
- Electrical contractor licensure is verified against the Colorado Department of Regulatory Agencies (DORA) License Lookup per the Town's Electrical License Contemporaneous Review Guidelines — Kersey defers electrical contractor licensing entirely to the Colorado State Electrical Board (DORA)
- Fee calculated using the UBC valuation-based schedule administered by SAFEbuilt, the same mechanism used for the Town's general Building Permit (Building Fee + 20% Town Surcharge + 30% Plan Review + Use Tax), applied to the solar project's declared valuation
- Colorado's statewide C.R.S. § 24-48.5-113 (HB21-1284) caps the aggregate of all fees a local government may charge to install an active solar energy system at $500 for a residential permit and $1,000 for a commercial permit, applying as a ceiling on the SAFEbuilt-calculated fee
- Use Tax of 3.0% of 50% of the value of construction materials (effectively 1.5% of total construction value) applies to the materials cost of the solar installation, per the Town's Development Fee Schedule and 2026 Fee Schedule
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Confirmed 2026-07-20 by cross-referencing the DORA State Electrical Board's own live fee-schedule document (hosted by the Town of Larkspur, CO, at townoflarkspur.org/media/2901, DORA address 1560… Show full citationHide
Confirmed 2026-07-20 by cross-referencing the DORA State Electrical Board's own live fee-schedule document (hosted by the Town of Larkspur, CO, at townoflarkspur.org/media/2901, DORA address 1560 Broadway Suite 1350, Denver) and Larimer County's current Table 1-E Electrical Permit Fees (larimer.org/sites/default/files/2020_electrical_fee_table.pdf), which explicitly lists solar under its "Commercial and other fees" valuation bracket (item B) and states "Solar permit fees are capped by state law at $500 for residential installations and $1,000 for commercial installations" (item 8) — the same statutory C.R.S. § 12-23-117 mechanism that governs electrical-fee scaling for every Colorado local government, including those using a SAFEbuilt-contracted inspector like Kersey.Review timeline
Inspection process
- 1
Foundation/Footing (ground-mount) or Framing (rooftop racking)
Structural attachment verified before panels are installed, per SAFEbuilt's standard inspection sequence
- 2
Final Electrical/Interconnection
Interconnection wiring verified; electrical contractor licensure re-checked against DORA's License Lookup per the Town's Electrical License Contemporaneous Review Guidelines
See the full Kersey inspection guide — scheduling & re-inspection fees →
Tips
- Kersey has no separate solar fee schedule — the same SAFEbuilt-administered UBC valuation formula (Building Fee + 20% Town Surcharge + 30% Plan Review + Use Tax) used for the Town's general Building Permit applies to a solar project's declared valuation.
- Colorado's statewide $500 residential / $1,000 commercial solar-fee cap (C.R.S. § 24-48.5-113) applies as a ceiling on whatever the SAFEbuilt UBC-based calculation produces.
- Verify your electrician's license is active on DORA's online License Lookup before starting work — Kersey's Building Inspectors may request to verify the identity/licensure of the electrician performing the interconnection at any inspection.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kersey building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Kersey's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Kersey yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Kersey lands. Privacy.
Other permits in Kersey
Rooftop Solar Photovoltaic Permit in other cities
Compare rooftop solar photovoltaic permit fees across Colorado →
Look up this fee in a different city →