Commercial Building Permit (New Commercial Construction) in Kersey, Colorado
Kersey DOES have a genuine, published commercial permitting track distinct from its residential process — confirmed 2026-08-02 by locating and fully reading the Town's 'Kersey Commercial Submittal Checklist 2021' PDF (linked from the Building Inspection Department page as 'new Commercial Plan Submittal Procedures for the Town of Kersey'), a 3-page SAFEbuilt Colorado document with three sections: 'New Commercial Plan Submittal Procedure' (page 1, this entry), 'Commercial Tenant Finish/Remodel Plan Submittal Procedure' (page 2, see the separate commercial-tenant-improvement-permit entry), and 'Restaurants & Commercial Kitchens' (page 3, folded into this entry's requirements). Plan review and inspection are performed by SAFEbuilt Colorado (Windsor Office) under the same contract as residential work; applications go through the Town's Community Core online portal. Governing code: the 2024 International Building Code per Ordinance No. 2025-0010 (adopted 9/9/2025, adopting 2024 IBC/IPC/IMC/IFGC/IEBC/IECC etc. by reference) — note the submittal checklist itself is a 2021-dated document that predates this code update, so its procedural content stands but the code editions in force are the 2024 ICC suite (except the Fire Code, which remains the 2018 IFC per Ordinance No. 2021-0001).
Verified 2026-08-02 · Source
When you need this permit
- Building permit application must state description of project and square footage, total project valuation and electrical valuation, type of construction, and occupancy group
- Submit ONE ELECTRONIC SET of: Town of Kersey Approved Site Plan (all pages — title page, site plan, utility drawings, drainage plans, elevations, landscape plans, etc.); Architectural Plans; Project Specifications; Structural Plans; Soils Report; Structural Calculations; List of special inspections required by the Building Code (on plan cover sheet OK); Electrical Plans; Mechanical/Plumbing Plans; Fire Protection Plans (if a system is part of the design); Energy Code Compliance Documents
- Architectural plans must include floor plan, wall section details, building section, fire-resistive construction details, and code summary, plus detailed drawings for fire-rated floor/ceiling, roof/ceiling, and wall assemblies — stamped by a Colorado licensed architect or engineer
- Structural plans stamped by a Colorado licensed engineer; soils report stamped by a Colorado licensed soils engineer; structural calculations stamped by a Colorado licensed structural engineer
- Electrical plans stamped by a Colorado licensed engineer and must include load calculations, one-line diagrams, and fault current analysis
- All plan sheets must bear the original seal of a Colorado-licensed architect or engineer unless exempted (the checklist cites 'section 12-4-112 C.R.S.' verbatim for the exemption)
- Cover sheet must include the building code summary and assumptions regarding occupancy, construction type, total allowable building area, exiting and occupant load, wind speed design, snow load, frost depth, and other pertinent information
- The approved job-site plan set must remain on the job site through final inspection and must be identical to the Town of Kersey approved site plan; changes to the approved site plan require Town of Kersey approval PRIOR to implementation
- Restaurants/commercial kitchens (checklist page 3): grease interceptor required where grease output could damage the sewer treatment plant (sized per the adopted Plumbing Code or engineer-designed and jurisdiction-approved); restaurants over 5,000 sq ft or with 50+ occupants must have an approved fire sprinkler system; Type I hoods with approved suppression for grease/smoke-producing appliances and Type II hoods for heat/steam-only appliances; 50+ occupant load requires two exits with panic hardware (exits may not pass through kitchen/storage spaces); Weld County health department approval is required as a condition of the Certificate of Occupancy (written approval must be on the jobsite before final inspection); a seating plan is required for inside or outside dining areas
- Restaurants serving liquor are responsible for obtaining all necessary liquor licenses, inspections, and other approvals from the Town of Kersey
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 7 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Special Inspections (per Building Code)
A list of special inspections required by the Building Code must be declared with the submittal (on the plan cover sheet is acceptable); the special-inspection regime of the adopted 2024 IBC (Chapter 17) governs which apply
- 2
Final Inspection / Certificate of Occupancy
Approved plan set must be on the job site through final inspection; for restaurants/food service, written Weld County health department approval must be on the jobsite before the final inspection will be approved and is a condition of the Certificate of Occupancy
See the full Kersey inspection guide — scheduling & re-inspection fees →
Tips
- Although not required, the Town's checklist explicitly advises a pre-submittal meeting with SAFEbuilt and the Kersey Fire Protection District before applying, submitting a building code summary and a list of project questions to SAFEbuilt beforehand — the checklist's own stated purpose for this is 'to speed up the review process'.
- Site plan approval through the Town of Kersey is a prerequisite embedded in the submittal itself — the electronic building-permit submittal must include ALL pages of the already-approved Town site plan, and any change to it after approval requires Town sign-off before implementation.
- The commercial submittal checklist is a 2021-dated SAFEbuilt document and cites '12-4-112 C.R.S.' for the architect/engineer seal exemption; Colorado's Title 12 was recodified in 2019 (the architects practice act now lives at C.R.S. 12-120-403 et seq.), and the Town has since adopted the 2024 ICC codes (Ordinance No. 2025-0010, 9/9/2025) — treat the checklist as authoritative for WHAT to submit, but verify current code editions and statutory cites with SAFEbuilt Windsor (970-686-7511).
- One internal oddity in the checklist, noted rather than resolved: its restaurant sprinkler threshold line cites '(WFPD)' — an acronym matching no Kersey-named entity (the advisory-meeting paragraphs in the same document name the 'Kersey Fire Protection District') — suggesting template text carried over from another SAFEbuilt jurisdiction; confirm the actual sprinkler threshold with the fire district serving your parcel before relying on the 5,000 sq ft / 50-occupant figure.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kersey building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Kersey.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Kersey
Commercial Building Permit (New Commercial Construction) in other cities
Compare commercial building permit (new commercial construction) fees across Colorado →
Look up this fee in a different city →
Now live
Build your Kersey project checklist
Describe your project once and get every permit, document, and fee it triggers in Kersey — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →