Commercial Building Permit in Kimberly, Idaho
New commercial construction in the City of Kimberly is NOT submitted on a separate freestanding commercial application. It is submitted on the same 'Residential-Commercial Application for Building Permit' used for houses (Ord. No. 671 effective 03-28-2022, amended 02-09-2026 per Ord. No. 689), checking the applicable Class of Work box (typically New Development, Addition, Alteration/Remodel, Accessory Structure, Repair, Demolish, or Re-Roof). The form itself distinguishes commercial submittals from residential ones in three confirmed ways: (1) commercial plan sets require 3 copies at 24"x36" versus 2 copies at 11"x17" for residential; (2) 'Commercial deposit fees shall be collected at issuance time' rather than at application as with the residential $150/$100 deposits; and (3) the form's own Development Impact Fee table prints distinct nonresidential (per-square-foot, by Retail/Office/Light-Industrial use) rates alongside the residential (per-dwelling-unit) rates. An older, standalone 'Commercial Building Permit Application' (Resolution #318, revised 03-15-14) also exists in the City's DocumentCenter but is no longer linked from the City's current Applications/Permits or Building-Planning-Zoning pages as of this research (2026-08-02) — it appears superseded by the combined form, though this could not be confirmed with certainty short of calling City Hall.
Reviewed 2026-08-02 · Source
When you need this permit
- Commercial construction is submitted on the City's combined Residential-Commercial Application for Building Permit (Ord. No. 671 eff. 03-28-2022, amended 02-09-2026 per Ord. No. 689) with the applicable Class of Work box checked — there is no separate freestanding commercial application currently linked from the City's website
- Commercial plans require 3 complete hard copy sets sized 24" x 36", versus 2 sets at minimum 11"x17" for residential — per the application form's own submittal checklist: '2 hard copy sets of plans to scale (minimum size 11" X 17") - Commercial plans (3-sets – 24" X 36")'
- Digital copy of the plan set must also be emailed to both ceckles@cityofkimberly.org and jtaylor@cityofkimberly.org, effective 02-09-2026, in addition to the hard copy sets delivered to City Hall — incomplete permits will not be processed
- Unlike residential work, where the $150/$100 non-refundable deposit is collected at application submittal, the current combined form states 'Commercial deposit fees shall be collected at issuance time' — no commercial deposit dollar figure is printed on the current form
- Site plan, floor plans, elevations, footings/foundation, typical construction details, and truss/floor-joist documentation are required as for residential work; an older (2014, Resolution #318) standalone Commercial Building Permit Application — no longer linked from the City's current site but still hosted in its DocumentCenter — additionally called for a completed 'COMM check' (vs. the current form's generic 'RES check' line), structural calculations where applicable, and plans stamped by an Idaho-licensed design professional. Whether these commercial-specific line items still apply under the current, amended-02-09-2026 combined form was not confirmed and should be verified with City Hall before submittal
- State Contractor Registration number (or Idaho Registration Exempt status) for the contractor Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Setback
Verify building location against required and stated setbacks before further work
- 2
Footing
Before concrete pour; UFER ground option noted on the fee worksheet
- 3
Foundation
Foundation inspection prior to backfill
- 4
Frame
After framing and rough-in trades are complete, before insulation or wall cover
- 5
Insulation
Insulation inspection before drywall
- 6
Drywall (shear/fire)
Shear wall and fire-rated assembly inspection at drywall stage
- 7
Final
Final inspection by the Kimberly Building Official; cannot be scheduled until the State of Idaho electrical, plumbing, and HVAC inspectors have signed off. A separate Public Works final inspection of sidewalks, water meter vaults, and meters follows before a Certificate of Occupancy is issued.
See the full Kimberly inspection guide — scheduling & re-inspection fees →
Tips
- There is no freestanding 'commercial' application to fill out — commercial projects use the same combined Residential-Commercial Application for Building Permit as houses, just under a different Class of Work checkbox and a 3-set/24"x36" plan requirement instead of 2-set/11"x17".
- Ask City Hall directly for the current commercial plan-review fee percentage and any COMM-check/design-professional-stamp requirement before submitting — the only written 30%-of-value plan-review figure and stamped-plans requirement found in this research come from an older (2014) standalone Commercial Building Permit Application that is no longer linked from the City's current website, so it may or may not still reflect current practice.
- Development Impact Fees for nonresidential development are charged per square foot (not per dwelling unit) and vary by land use classification — confirm with City staff whether your project will be classified Retail, Office, or Light Industrial, since the Admin and Street DIF rates differ by classification.
- Commercial deposit fees are collected at permit issuance, not at application submittal, per the current combined form — budget for this timing difference versus residential.
- As with residential permits, the City's own final building inspection cannot be scheduled until the State of Idaho electrical, plumbing, and HVAC inspectors have signed off, since Kimberly does not perform those trade inspections itself.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kimberly building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Kimberly.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Kimberly
Commercial Building Permit in other cities
Compare commercial building permit fees across Idaho →
Look up this fee in a different city →
Now live
Build your Kimberly project checklist
Describe your project once and get every permit, document, and fee it triggers in Kimberly — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →