EV Charger / EVSE Permit — Kimberly, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://dopl.idaho.gov/ele/ele-permits-and-inspections/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Kimberly, Idaho
Electric vehicle charging equipment (EVSE) installation in the City of Kimberly is an electrical installation, and the City of Kimberly does not itself inspect electrical trade work — per the City's own Building Permit Application, electrical, plumbing, and HVAC/mechanical trades are inspected and signed off directly by State of Idaho inspectors (Division of Occupational and Professional Licenses, DOPL) before the City's own final building inspection can be scheduled. DOPL's own published Electrical Permit Worksheet (Fee Schedule) has no distinct EVSE/EV-charger line item; a Level 2 EVSE circuit at an existing residence is billed under the worksheet's 'Existing Residence' branch-circuit tier, and one added as part of new construction is folded into the 'New Single Family Dwelling' square-footage tier.
Verified 2026-07-20 · Source
When you need this permit
- EVSE/EV charger circuit installation requires a State of Idaho DOPL electrical permit, purchased online via DOPL's ArcGIS location-based portal (dbs.idaho.gov) — the City of Kimberly does not itself issue or inspect electrical permits
- Homeowners performing EVSE wiring on their own primary or secondary residence may obtain a DOPL Homeowner Electrical Permit directly; otherwise an Idaho-licensed electrical contractor must pull the permit
- No distinct EV-charger/EVSE fee line exists on the DOPL Electrical Permit Worksheet (Fee Schedule, rev. 8/17/2022) — a charger circuit added to an existing residence is billed under the worksheet's 'Existing Residence' tier ($65 base + $10 per additional branch circuit); a charger installed with new-home construction is folded into the 'New Single Family Dwelling' square-footage tier
- If the EVSE circuit is part of a City-permitted building project (e.g., new construction or an addition), the City's own building permit process still applies to the structural/general-building scope, but the electrical trade inspection itself remains with DOPL, not the City
- Inspections are scheduled through DOPL's own system and performed by a DOPL-assigned inspector
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final (DOPL-inspected)
EVSE circuit, breaker/disconnect, and NEC Article 625 (Electric Vehicle Power Transfer System) compliance verified by a DOPL-assigned inspector; must be signed off before the City of Kimberly's own final building inspection (if applicable) can be scheduled
See the full Kimberly inspection guide — scheduling & re-inspection fees →
Tips
- The City of Kimberly does not accept or inspect electrical permits — apply directly through DOPL's ArcGIS location-based portal (dbs.idaho.gov) or call DOPL at 1-800-955-3044.
- If the EVSE installation is bundled with a City building permit (e.g., new construction), the City's final inspection cannot be scheduled until the State electrical inspector has signed off, consistent with the City's general trade-inspection policy documented on the Residential Building Permit entry.
- Idaho state law bars local governments from mandating EV charging infrastructure or dedicated EV parking in new construction — the City of Kimberly has no such local mandate.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kimberly building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Kimberly
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Idaho →
Look up this fee in a different city →