Building Permit (New Construction, Additions, Remodels, Repairs, Demolition, Re-Roof) — Kimberly, Idaho · Requirements sheet
Verified 2026-07-07 · Source: https://cityofkimberly.org/478/Building---Planning-and-Zoning
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Building Permit (New Construction, Additions, Remodels, Repairs, Demolition, Re-Roof) in Kimberly, Idaho
The City of Kimberly uses a single 'Residential-Commercial Application for Building Permit' covering new development, accessory structures, alteration/remodel, additions, repairs, demolition, re-roof, sign, fence, and tenant improvement work (selected via a 'Class of Work' checkbox on the application). Required for erecting, constructing, enlarging, altering, repairing, moving, or demolishing any structure within the City.
Verified 2026-07-07 · Source
When you need this permit
- New development, accessory structures, alterations/remodels, additions, repairs, demolition, re-roofing, signs, fences, and tenant improvements are all submitted on the same Building Permit Application, with the applicable 'Class of Work' checked
- Two (2) complete hard copy sets of building plans (minimum size 11" x 17"; commercial plans require 3 sets at 24" x 36") delivered to City Hall
- Effective 02-09-2026: a digital copy of the building permit plans must also be e-mailed to both ceckles@cityofkimberly.org and jtaylor@cityofkimberly.org — incomplete building permits will not be processed
- Complete hard copy sets include: Application, Warranty Deed (with legal description), Architectural Design Approval (where subject to a subdivision's CC&Rs), and New Construction Water Application form
- Site plan must be to scale and depict setbacks, easements, and public rights-of-way, showing all buildings, property boundaries, adjacent street names, curb/sidewalk, and entry-exit access points
- Floor plans with dimensions, elevations, footings and foundation details, typical construction details (cross-section, stair detail, etc.), and a completed RES check or compliance with prescriptive energy requirements
- State Contractor Registration number (or Idaho Registration Exempt status) for the contractor/installer Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Setback
Verify building location against required and stated setbacks before further work
- 2
Footing
Before concrete pour; UFER ground option noted on the fee worksheet
- 3
Foundation
Foundation inspection prior to backfill
- 4
Frame
After framing and rough-in trades are complete, before insulation or wall cover
- 5
Insulation
Insulation inspection before drywall
- 6
Drywall (shear/fire)
Shear wall and fire-rated assembly inspection at drywall stage
- 7
Final
Final inspection by the Kimberly Building Official; cannot be scheduled until the State of Idaho electrical, plumbing, and HVAC inspectors have signed off. A separate Public Works final inspection of sidewalks, water meter vaults, and meters follows before a Certificate of Occupancy is issued.
See the full Kimberly inspection guide — scheduling & re-inspection fees →
Tips
- All calls for inspections require 24-hour notice, Monday through Thursday; inspections requested on Friday will normally be performed the following Monday.
- Final building inspections cannot be scheduled until the State of Idaho electrical, plumbing, and HVAC inspectors have signed off — the City does not perform trade inspections itself.
- Effective 02-09-2026, applicants must email a digital copy of the full plan set to BOTH the Planning & Zoning Administrator (ceckles@cityofkimberly.org) and the Planner I (jtaylor@cityofkimberly.org), in addition to delivering two hard copy sets to City Hall — incomplete submittals will not be processed.
- Certain subdivisions in Kimberly require Architectural Design Review/CC&R compliance approval from the subdivision's Homeowners' Association before a building permit can issue without delay.
- Only the City may turn water service on or off at the meter; unauthorized connection by a contractor or plumber can trigger a $300.00 fine to the property owner.
- The $150/$100 application deposits are non-refundable and applied toward the total permit fee, which is separately calculated from the per-square-foot valuation table (R-3 $45.75/sf, U-1 $36.00/sf, covered porch/carport $31.00/sf) plus Development Impact Fees and utility connection charges.
- Idaho Code 39-4117 (effective 2025) gives Kimberly 10 business days (residential) / 20 business days (commercial) to determine an application complete — this is not a guarantee of full plan approval within that window.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kimberly building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Kimberly
Building Permit (New Construction, Additions, Remodels, Repairs, Demolition, Re-Roof) in other cities