North Las Vegas building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in North Las Vegas, Nevada.

Verified 2026-07-17 · Source

How to schedule

Inspections are requested through the building department below.

Address
2250 Las Vegas Blvd. North, Suite 125, North Las Vegas, NV 89030
Phone
(702) 633-1536
Office hours
Mon–Thu 8:00 AM – 5:45 PM (closed Fri)

Published scheduling rules

  • North Las Vegas uses the Citizen Self-Service (CSS) portal for inspection scheduling: eg.cityofnorthlasvegas.com/EnerGov_Prod/SelfService (Residential Building Permit — New Construction (Single-Family))
  • Schedule inspections via the CSS portal at eg.cityofnorthlasvegas.com/EnerGov_Prod/SelfService or call (702) 633-1576. (Electrical Permit)
  • Schedule inspections via the CSS portal at eg.cityofnorthlasvegas.com/EnerGov_Prod/SelfService or call (702) 633-1576. (Electric Vehicle (EV) Charger / EVSE Permit)

Inspection sequence

Applies to: Residential Building Permit — New Construction (Single-Family)

  1. 1

    Foundation / Footings

    Before concrete pour — forms, rebar, anchor bolts, and frost depth compliance

  2. 2

    Underground Plumbing

    Underground plumbing before slab pour

  3. 3

    Framing

    After framing and sheathing complete, before insulation or wall cover — fire sprinkler rough-in also inspected

  4. 4

    Rough-In (MEP)

    Electrical, plumbing, and mechanical rough-in inspections before wall cover

  5. 5

    Insulation / Energy

    Insulation installed, energy compliance items verified before drywall

  6. 6

    Final

    All work complete per approved plans; permit becomes Certificate of Occupancy upon approved final for new SFD

Applies to: Fire Alarm System Permit

  1. 1

    Rough Electrical

    Rough electrical inspection by NLV Building Safety, before wiring is concealed

  2. 2

    Rough Fire Alarm

    Inspection of all device/box locations and wiring by NLV Fire Prevention, before concealment behind sheetrock

  3. 3

    Contractor Pretest

    Installing contractor pretests the entire system prior to scheduling the final inspection; a written pretest record must be provided

  4. 4

    24-Hour Battery Test

    Two-part test: AC power is disconnected, then at least 24 hours later all indicating devices are activated for at least 5 minutes (15 minutes for voice communications) while AC remains disconnected; the second portion may be performed at final

  5. 5

    Fire Alarm Final

    NLV Fire Prevention witnesses the fire alarm final at completion of installation; record of completion and maintenance agreement must be uploaded via the CSS Portal beforehand

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Footings and foundation before concrete pour

  2. 2

    Framing

    Structural framing, fire separation, egress

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical rough-ins before walls closed

  4. 4

    Final

    All work complete, smoke/CO detectors, address posted

Applies to: Swimming Pool / Spa Permit

  1. 1

    Pre-Gunite / Excavation

    Before pool shell is poured — steel placement, plumbing rough-in, depth verification

  2. 2

    Electrical Rough-In

    Pool bonding, equipment grounding, and conduit runs before cover

  3. 3

    Fence / Barrier

    Pool enclosure/barrier inspection before water fill

  4. 4

    Final

    All equipment installed and operational, safety features (alarms, fence/gates) verified per 2024 ISPSC

Applies to: Block Wall / Screen Wall / Retaining Wall Permit

  1. 1

    Footing

    Before concrete pour — footing depth, width, and rebar placement

  2. 2

    Masonry / Grout

    During construction — cell fill, grout placement, and rebar continuity

  3. 3

    Final

    Completed wall — verify height, alignment, drainage provisions

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Framing / Rough-In

    After framing and rough-in trades, before wall cover

  2. 2

    Fire / Life Safety

    Fire sprinkler, fire alarm, and exit signage inspections per 2024 IFC

  3. 3

    Final

    All work complete per approved plans; Certificate of Occupancy issued

Applies to: Residential Addition / Remodel Permit

  1. 1

    Framing / Structural

    After framing complete, before walls covered — structural connections, headers, blocking

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-ins before wall cover (sub-permits required)

  3. 3

    Final

    All work complete per approved plans

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final — Building

    Panel mounting, racking attachment, roof penetration sealing verified

  3. 3

    Final — Electrical

    Electrical connections, inverter installation, and interconnection point verified per 2023 NEC

Applies to: Electric Vehicle (EV) Charger / EVSE Permit

  1. 1

    Rough-In / Permanent Service

    After circuit wiring installed, before concealment — verify conductor sizing, box placement, and dedicated-circuit connection

  2. 2

    Final

    EVSE installed, GFCI protection and NEC Article 625 compliance verified

Applies to: Electrical Permit

  1. 1

    Rough-In / Permanent Service

    After wiring installed, before walls closed — verify conductor sizing, box placement, and service connections

  2. 2

    Final

    All devices installed, panel labeled, GFCI/AFCI protection verified per 2023 NEC

Applies to: Fire Sprinkler System Permit

  1. 1

    Rough & Hydrostatic Test

    Piping, hangers, and underground supply inspected and hydrostatically tested/flushed before concealment; North Las Vegas Fire Prevention must be notified at least 24 hours in advance. Piping concealed before signoff must be exposed for inspection per IFC §108.4.

  2. 2

    Final

    Completed system inspected and accepted by Fire Prevention, verified against approved plans and applicable NFPA standards

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Ductwork

    After ductwork installed, before walls covered — verify clearances, support, and connections

  2. 2

    Final

    Equipment operational, combustion air verified, venting correct, thermostat functional

Applies to: Plumbing Permit

  1. 1

    Underground / Rough-In

    After pipes installed, before walls or slab closed — pressure test and slope verification

  2. 2

    Final

    All fixtures connected, no leaks, proper venting verified per 2024 UPC

Re-inspection fees

Residential Building Permit — New Construction (Single-Family)Re-inspection fee · NLV MC 15.72.230B.4
$100
Residential Addition / Remodel PermitRe-inspection fee
$100
Electrical PermitRe-inspection fee
$100
Plumbing PermitRe-inspection fee
$100
Mechanical / HVAC PermitRe-inspection fee
$100
Residential Re-roof PermitRe-inspection fee
$100
Solar Photovoltaic (PV) PermitRe-inspection fee
$100
Commercial Tenant Improvement PermitRe-inspection fee
$100
Block Wall / Screen Wall / Retaining Wall PermitRe-inspection fee
$100
Sign PermitRe-inspection fee · NLV MC 15.72.230B.4
$100
Fire Sprinkler System PermitRe-inspection fee (fire-specific) · NLV MC 15.92.070.IV — distinct from the $100 general building re-inspection fee
$80.00 per inspection (3rd and subsequent reinspections; 1st/2nd are no charge)
Fire Alarm System PermitRe-inspection fee (fire-specific) · NLV MC 15.92.070.IV — distinct from the $100 general building re-inspection fee
$80.00 per inspection (3rd and subsequent reinspections; 1st/2nd are no charge)
Change of Occupancy / Certificate of Occupancy PermitRe-inspection fee · NLV MC 15.72.230B.4
$100

North Las Vegas building permits

Get alerts for North Las Vegas

We'll email you when North Las Vegas's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.