North Las Vegas building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in North Las Vegas, Nevada.
Verified 2026-07-17 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 2250 Las Vegas Blvd. North, Suite 125, North Las Vegas, NV 89030
- Phone
- (702) 633-1536
- Office hours
- Mon–Thu 8:00 AM – 5:45 PM (closed Fri)
- Website
- Official site
Published scheduling rules
- North Las Vegas uses the Citizen Self-Service (CSS) portal for inspection scheduling: eg.cityofnorthlasvegas.com/EnerGov_Prod/SelfService (Residential Building Permit — New Construction (Single-Family))
- Schedule inspections via the CSS portal at eg.cityofnorthlasvegas.com/EnerGov_Prod/SelfService or call (702) 633-1576. (Electrical Permit)
- Schedule inspections via the CSS portal at eg.cityofnorthlasvegas.com/EnerGov_Prod/SelfService or call (702) 633-1576. (Electric Vehicle (EV) Charger / EVSE Permit)
Inspection sequence
Applies to: Residential Building Permit — New Construction (Single-Family)
- 1
Foundation / Footings
Before concrete pour — forms, rebar, anchor bolts, and frost depth compliance
- 2
Underground Plumbing
Underground plumbing before slab pour
- 3
Framing
After framing and sheathing complete, before insulation or wall cover — fire sprinkler rough-in also inspected
- 4
Rough-In (MEP)
Electrical, plumbing, and mechanical rough-in inspections before wall cover
- 5
Insulation / Energy
Insulation installed, energy compliance items verified before drywall
- 6
Final
All work complete per approved plans; permit becomes Certificate of Occupancy upon approved final for new SFD
Applies to: Fire Alarm System Permit
- 1
Rough Electrical
Rough electrical inspection by NLV Building Safety, before wiring is concealed
- 2
Rough Fire Alarm
Inspection of all device/box locations and wiring by NLV Fire Prevention, before concealment behind sheetrock
- 3
Contractor Pretest
Installing contractor pretests the entire system prior to scheduling the final inspection; a written pretest record must be provided
- 4
24-Hour Battery Test
Two-part test: AC power is disconnected, then at least 24 hours later all indicating devices are activated for at least 5 minutes (15 minutes for voice communications) while AC remains disconnected; the second portion may be performed at final
- 5
Fire Alarm Final
NLV Fire Prevention witnesses the fire alarm final at completion of installation; record of completion and maintenance agreement must be uploaded via the CSS Portal beforehand
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation
Footings and foundation before concrete pour
- 2
Framing
Structural framing, fire separation, egress
- 3
MEP Rough-In
Electrical, plumbing, mechanical rough-ins before walls closed
- 4
Final
All work complete, smoke/CO detectors, address posted
Applies to: Swimming Pool / Spa Permit
- 1
Pre-Gunite / Excavation
Before pool shell is poured — steel placement, plumbing rough-in, depth verification
- 2
Electrical Rough-In
Pool bonding, equipment grounding, and conduit runs before cover
- 3
Fence / Barrier
Pool enclosure/barrier inspection before water fill
- 4
Final
All equipment installed and operational, safety features (alarms, fence/gates) verified per 2024 ISPSC
Applies to: Block Wall / Screen Wall / Retaining Wall Permit
- 1
Footing
Before concrete pour — footing depth, width, and rebar placement
- 2
Masonry / Grout
During construction — cell fill, grout placement, and rebar continuity
- 3
Final
Completed wall — verify height, alignment, drainage provisions
Applies to: Commercial Tenant Improvement Permit
- 1
Framing / Rough-In
After framing and rough-in trades, before wall cover
- 2
Fire / Life Safety
Fire sprinkler, fire alarm, and exit signage inspections per 2024 IFC
- 3
Final
All work complete per approved plans; Certificate of Occupancy issued
Applies to: Residential Addition / Remodel Permit
- 1
Framing / Structural
After framing complete, before walls covered — structural connections, headers, blocking
- 2
MEP Rough-In
Electrical, plumbing, and mechanical rough-ins before wall cover (sub-permits required)
- 3
Final
All work complete per approved plans
Applies to: Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final — Building
Panel mounting, racking attachment, roof penetration sealing verified
- 3
Final — Electrical
Electrical connections, inverter installation, and interconnection point verified per 2023 NEC
Applies to: Electric Vehicle (EV) Charger / EVSE Permit
- 1
Rough-In / Permanent Service
After circuit wiring installed, before concealment — verify conductor sizing, box placement, and dedicated-circuit connection
- 2
Final
EVSE installed, GFCI protection and NEC Article 625 compliance verified
Applies to: Electrical Permit
- 1
Rough-In / Permanent Service
After wiring installed, before walls closed — verify conductor sizing, box placement, and service connections
- 2
Final
All devices installed, panel labeled, GFCI/AFCI protection verified per 2023 NEC
Applies to: Fire Sprinkler System Permit
- 1
Rough & Hydrostatic Test
Piping, hangers, and underground supply inspected and hydrostatically tested/flushed before concealment; North Las Vegas Fire Prevention must be notified at least 24 hours in advance. Piping concealed before signoff must be exposed for inspection per IFC §108.4.
- 2
Final
Completed system inspected and accepted by Fire Prevention, verified against approved plans and applicable NFPA standards
Applies to: Mechanical / HVAC Permit
- 1
Rough-In / Ductwork
After ductwork installed, before walls covered — verify clearances, support, and connections
- 2
Final
Equipment operational, combustion air verified, venting correct, thermostat functional
Applies to: Plumbing Permit
- 1
Underground / Rough-In
After pipes installed, before walls or slab closed — pressure test and slope verification
- 2
Final
All fixtures connected, no leaks, proper venting verified per 2024 UPC
Final inspection only: Change of Occupancy / Certificate of Occupancy Permit, Demolition Permit, Residential Re-roof Permit, Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-17.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the North Las Vegas building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
North Las Vegas building permits
Get alerts for North Las Vegas
We'll email you when North Las Vegas's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.