Swimming Pool / Spa Permit in North Las Vegas, Nevada

Required for construction of residential and commercial swimming pools, spas, and hot tubs in the City of North Las Vegas. Governed by the 2024 International Swimming Pool and Spa Code (ISPSC) with Southern Nevada and NLV amendments (effective January 5, 2026, amended by Ord. 3259 3/4/26 to protect pet door openings with direct pool/spa access). A Drowning Prevention Fee applies to each pool/spa permit.

Verified 2026-06-30 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Building Permit Fee — valuation-based per Table 3-AVaries — valuation-based ($36.00/sq ft × 0.89 NV modifier for standard pool), then per Table 3-AValuation per NLV MC Table 3-F (15.72.280): 'Standard swim pool $36.00; Above ground (over 5K gals) $16.00; Pool deck $6.00.' Nevada Regional Modifier 0.89 applied. Standard swimming pool $36.00 × 0.89 = $32.04/sq ft effective valuation rate; above-ground pool (over 5,000 gal) $16/sq ft effective; pool deck $6/sq ft.
Administrative fee$75 per permit
Drowning Prevention Fee$25 per pool or spa permitNLV MC 15.72.230B.6 — charged on each pool or spa permit in addition to the standard permit fee
Plumbing Permit Fee (pool plumbing)$29.00 for private/wading pool including spa; $15.00 for preformed spa (private)Per NLV MC Table 3-D (15.72.260) — separate plumbing permit required
Electrical Permit Fee (pool electrical)$29.00 for residential pool (electrical)Per NLV MC Table 3-B (15.72.240) — separate electrical permit required
Plan check fee65% of permit fee
Recording fee3% of permit fee (minimum $2)

Review timeline

~521 business days

Typical estimate — confirm current times with the North Las Vegas building department

Inspection process

  1. 1

    Pre-Gunite / Excavation

    Before pool shell is poured — steel placement, plumbing rough-in, depth verification

  2. 2

    Electrical Rough-In

    Pool bonding, equipment grounding, and conduit runs before cover

  3. 3

    Fence / Barrier

    Pool enclosure/barrier inspection before water fill

  4. 4

    Final

    All equipment installed and operational, safety features (alarms, fence/gates) verified per 2024 ISPSC

Tips

Frequently asked questions

What is the Drowning Prevention Fee in North Las Vegas?
NLV charges a $25 Drowning Prevention Fee on each pool or spa permit, in addition to the standard permit fee. This is established in NLV Municipal Code Section 15.72.230B.6.
How many permits do I need to build a swimming pool in North Las Vegas?
Typically three: (1) a Building Permit for the pool structure (Swimming Pool Application), (2) a Plumbing Permit for pool plumbing ($29 for private pool), and (3) an Electrical Permit for bonding and equipment ($29 for residential pool). All three are available at the Permit Application Center.

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the North Las Vegas building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in North Las Vegas

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.