Change of Use / Certificate of Occupancy in Lovington, New Mexico
Lovington has no dedicated 'change of use' or 'certificate of occupancy' permit application, checklist, or fee schedule published on lovington.org (the City's full City Forms and Documents listing carries Planning & Zoning, Utilities, Parks & Recreation, Lodgers Tax, and general business forms but nothing for occupancy/change of use). As with Lovington's Building Permit, Solar PV Permit, and EV Charger entries, the substantive legal process is a New Mexico Construction Industries Division (CID) matter, since Lovington has not established its own certified Building Official / full-service building department (the statewide 'AHJ' definition at N.M. Admin. Code 14.5.1.7 requires 'a full-time certified building official' with 'permitting, inspection and enforcement authority,' which Lovington's own Planning and Zoning Department does not hold). 'Change of occupancy' is defined at N.M. Admin. Code 14.5.1.7 as 'a change in the use of the building or portion of a building including a change of the occupancy classification or any change in use within a classification group to another occupancy in the group,' and is governed substantively by the 2021 New Mexico Existing Building Code (NMEBC, N.M. Admin. Code 14.7.7, adopting the 2021 International Existing Building Code, Chapter 10 'Change of Occupancy'). Per N.M. Admin. Code 14.5.2.11(B), 'changes in the work, occupancy type, occupant load or kind of structure authorized by a permit must be reflected in an amended set of submittal documents, which must be resubmitted for approval by the AHJ' -- i.e., CID for Lovington. A Certificate of Occupancy (C/O) for the changed use is then issued per N.M. Admin. Code 14.5.3.13, which states 'no building...shall be occupied' under the new use until the C/O or an approved final inspection is issued, and 'no C/O shall be issued by the CBO or the inspector until all of the required inspections have been performed.' Separately from this State CID track, City of Lovington Municipal Code Section 17.08.160 ('Certificate of occupancy required') codifies the City's OWN, longstanding local certificate-of-occupancy requirement -- 'no change in the use or character of occupancy of land, nor any change of use or character of occupancy in an existing building, other than for single-family dwelling purposes, shall be made...until a certificate of occupancy has been issued by the building inspector' (Prior code Section 11-3-10(n-o)), with 17.08.050 assigning the 'city building inspector' role to 'the city manager or his designee.' No published city document reconciles this local Title 17 C/O ordinance with the CID-issued C/O process described above -- the same kind of dual-track tension documented in the electrical-permit entry (City Chapter 15.08 electrical permit vs. State CID electrical permit) is also present for change-of-use/occupancy. If the new use requires a different zoning classification (rather than only a different building-code occupancy classification within the same use), Lovington's own Zone Change (Municipal Code 17.08.170, 'Amendments to title') or Variance Request (17.08.030(B), heard as an appeal to the City's Board of Appeals per 17.08.040) processes would apply through the City's Planning and Zoning Department.
Verified 2026-07-23 · Source
When you need this permit
- No change in the use or occupancy classification of a building may occur, and the building may not be occupied under the new use, until a Certificate of Occupancy (or approved final inspection) has been issued (N.M. Admin. Code 14.5.3.13(A))
- Submit an amended set of submittal documents (plans/specifications reflecting the new occupancy type, occupant load, or kind of structure) to CID for review and approval -- the same AHJ that reviews Lovington's original building permits, per N.M. Admin. Code 14.5.2.11(B)
- Compliance with the 2021 New Mexico Existing Building Code (NMAC 14.7.7, adopting the 2021 IEBC), Chapter 10 Change of Occupancy, and any applicable requirements of the 2021 New Mexico Commercial Building Code (NMCBC)
- All required inspections applicable to the new occupancy/use must be performed and approved before a C/O will be issued (N.M. Admin. Code 14.5.3.13(B))
- SEPARATELY (found 2026-07-23): City of Lovington Municipal Code 17.08.160 also requires a City-issued certificate of occupancy from the 'building inspector' (the city manager or designee, per 17.08.050) before any change in the use or character of occupancy of land or of an existing building, other than for single-family dwelling purposes -- how this local requirement is coordinated in practice with the State CID C/O process above is not addressed in any published city document
- If the new use requires a different zoning classification (not just a different building-occupancy classification), separately pursue Lovington's own Zone Change (Municipal Code 17.08.170) or Variance Request (17.08.030(B)/17.08.040, an appeal to the City's Board of Appeals) process through the Planning and Zoning Department -- confirm with the Planning & Zoning Coordinator which track(s) apply to a specific project
- A temporary Certificate of Occupancy may be issued by the inspector for a 30-day period (or longer, if approved by the TBC/CBO) if the AHJ determines a temporary C/O is appropriate and life, safety, or health will not be adversely affected (N.M. Admin. Code 14.5.3.13(D))
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Read the complete current CID fee rule (N.M. Show full citationHide
Read the complete current CID fee rule (N.M. Admin. Code 14.5.5, srca.nm.gov/wp-content/uploads/attachments/14.005.0005.pdf, in force since 7-1-04, no repeal on record) in full, section by section (14.5.5.11 General Building, 14.5.5.12 Electrical, 14.5.5.13 Mechanical/Plumbing, 14.5.5.14 Miscellaneous Fees) -- confirmed no line item anywhere in the rule references 'amended permit,' 'change of occupancy,' or 'certificate of occupancy' as a distinct fee category (the rule's only 'amended permit' language, at 14.5.5.4(A), just restates that no permit or amended permit is valid until fees otherwise due under the rule are paid -- it does not create a separate amendment fee). This is a genuine, exhaustively-checked verified-negative absence, not an extraction gap; valuation-based general construction fees remain quoted directly by a CID field office.City of Lovington Code of Ordinances, Section 17.08.040(F) (Prior code Section 11-3-8(c)): 'A fee of fifteen dollars shall be paid to the building inspector at the time the notice of appeal is filed,… Show full citationHide
City of Lovington Code of Ordinances, Section 17.08.040(F) (Prior code Section 11-3-8(c)): 'A fee of fifteen dollars shall be paid to the building inspector at the time the notice of appeal is filed, which the building inspector shall forthwith pay over to the city clerk to the credit of the general revenue fund of the city.' In Lovington's Municipal Code, a variance is obtained by appealing to the Board of Appeals under its hardship/variance power at 17.08.030(B); the $15.00 fee is filed with that notice of appeal. Confirmed via the site's render-section API (live 2026-07-23) and cross-checked against the complete Ordinance List and Disposition Table (Ords. 218-612, current through Ord. 612, 6-9-25) -- no ordinance has ever amended Section 17.08.040 or this fee since the 1992 codification (the only ordinance touching Chapter 17.08 at all, Ord. 262, amended prior code Section 11-3-14(a), zoning enforcement, which maps to 17.08.180 Enforcement, a different section).Read Section 17.08.170 in full (live via the site's render-section API) -- it describes the rezoning/amendment procedure (petition, planning and zoning commission referral, protest-percentage… Show full citationHide
Read Section 17.08.170 in full (live via the site's render-section API) -- it describes the rezoning/amendment procedure (petition, planning and zoning commission referral, protest-percentage supermajority-vote thresholds) but states no filing fee. No fee schedule/resolution for a Zone Change/text-amendment application was found in Municipal Code Title 3 (Revenue and Finance), Title 17 Chapter 17.08 (Administration, fully read section-by-section 2026-07-23), or elsewhere on lovington.org. Genuinely unpublished, distinct from the $15.00 Variance/Notice-of-Appeal fee documented separately above, which does have a codified figure.Review timeline
Inspection process
- 1
Required Inspections for New Occupancy/Use (CID)
All inspections applicable to the new occupancy classification must be performed and approved before a Certificate of Occupancy is issued; a C/O cannot be issued until all required inspections have been performed (N.M. Admin. Code 14.5.3.13(B))
See the full Lovington inspection guide — scheduling & re-inspection fees →
Tips
- There is no standalone 'change of use' or 'certificate of occupancy' checklist on lovington.org -- this is handled as an amendment to the CID building-permit submittal process described in the general Building Permit entry, not a separate City-issued permit application form.
- Lovington's own Municipal Code (17.08.160) separately requires a City-issued certificate of occupancy from the city's 'building inspector' for a change in use/occupancy other than single-family dwelling purposes -- a local requirement layered alongside the State CID C/O process, with no published document explaining how the two interact in practice.
- A change of occupancy is at minimum a two-track question in Lovington: a building-code occupancy-classification change goes through CID (2021 NMEBC/IEBC Chapter 10) and, per 17.08.160, may also require a City-issued C/O; a zoning-classification change goes through the City's own Zone Change (17.08.170) or Variance (17.08.030(B)/17.08.040) process -- confirm with the City Planning & Zoning Coordinator (cball@lovington.org, (575) 396-9301) which track(s) apply before assuming any one process alone is sufficient.
- If a variance is needed, budget the codified $15.00 Notice of Appeal fee (17.08.040(F)) filed with the Board of Appeals; a Zone Change/text amendment under 17.08.170 has no published filing fee.
- A temporary Certificate of Occupancy (minimum 30 days) is available under N.M. Admin. Code 14.5.3.13(D) if the AHJ determines it will not adversely affect life, safety, or health -- useful if final inspections are pending but occupancy is otherwise ready.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fee schedules
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lovington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Lovington's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Lovington yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Lovington lands. Privacy.
Other permits in Lovington
Change of Use / Certificate of Occupancy in other cities
Compare change of use / certificate of occupancy fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Lovington project checklist
Describe your project once and get every permit, document, and fee it triggers in Lovington — in one checklist. Free, for any city and any number of projects.
Get started →