Building Permit (Residential & Commercial Construction) — Lovington, New Mexico · Requirements sheet
Verified 2026-07-19 · Source: https://www.lovington.org/wp-content/uploads/2024/10/checklist_building.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Building Permit (Residential & Commercial Construction) in Lovington, New Mexico
Required for new construction, additions, and structural work on site-built or modular homes and commercial buildings in Lovington. The City of Lovington Planning and Zoning Department reviews zoning, setback, and floodplain compliance and signs a cover sheet BEFORE the applicant submits the actual building/electrical/plumbing/structural permit application to the New Mexico Construction Industries Division (CID), which administers the state-adopted New Mexico Building/Residential Code. The City performs its own preliminary (pre-construction, zoning-compliance) and final inspections separate from any CID code inspection.
Verified 2026-07-19 · Source
When you need this permit
- Submit a completed, legible, signed and dated Planning and Zoning Application (basic information for all City permitting applications)
- Provide proof of ownership or interest in the property — a deed with legal description or property lease; an Affidavit by Property Owner(s) if the applicant is not the owner
- Submit site plans for all structural work showing property lines, building dimensions (including height), lot area, lot dimensions, easements, building setbacks, road access points, and location of utilities
- Submit a Property Address for the Lea County Enhanced 9-1-1 System (obtained from Lea County Emergency Management, Elisa Millan, emillan@leacounty.net, (575) 391-2983, 1019 E Bender Blvd, Hobbs NM 88240)
- Submit a Floodplain Determination Letter, obtained by submitting the Lea County E-911 letter to the City Planning and Zoning Coordinator
- Submit a complete State building permit (CID) application cover sheet for the City Planner and Floodplain Manager signatures — these must be obtained BEFORE submitting the application to the State; the project must pass the City's preliminary inspection before the City Planner will sign the State permit
- Submit an Access permit from NM DOT if the site is on a State-owned highway or road
- Call 811 before digging, to locate buried utility lines
- Preliminary inspection required: outline the project area with flags/strings/markers and contact the City Planner to verify compliance with setbacks, zoning, and land development requirements
- Pay the City Permit Fee (amount determined by City staff at time of application; not a published fixed schedule)
- Final inspection required after construction to confirm work meets all City requirements
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Preliminary Inspection (City)
Verifies compliance with setbacks, zoning, and land development requirements before construction begins; project must pass before the City Planner will sign the State CID permit cover sheet
- 2
Final Inspection (City)
Confirms completed work meets City zoning/site requirements; separate from any State CID code-compliance inspection
See the full Lovington inspection guide — scheduling & re-inspection fees →
Tips
- Lovington does not issue its own valuation-based building permit the way City of Hobbs does — the City's role is zoning/floodplain/site-plan sign-off, and the actual construction permit is a State of New Mexico CID permit submitted directly to the Construction Industries Division after the City Planner and Floodplain Manager sign the cover sheet.
- Budget time for the Lea County Enhanced 9-1-1 addressing step and the City Floodplain Determination Letter — both must be obtained (in that order) before the City will sign off on the State CID permit cover sheet.
- Call 811 before digging is explicitly listed as a checklist item, not just general advice.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lovington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Lovington
Building Permit (Residential & Commercial Construction) in other cities
Compare building permit (residential & commercial construction) fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Lovington project checklist
Describe your project once and get every permit, document, and fee it triggers in Lovington — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.