Skip to main content
PermitBase

Electrical Permit (City Electrical Inspector) in Lovington, New Mexico

Lovington Municode Chapter 15.08 (Electrical Code) separately requires a permit from the City's own 'electrical inspector' before any wiring, devices, or equipment for transmission, distribution, or utilization of electrical energy are installed. This is a distinct, still-codified City ordinance; the City's newer Building Permit Application checklist separately directs electrical work through the State building permit (CID) process, and no published document reconciles the two. RE-CHASED 2026-07-23, gap still open: N.M. Admin. Code 14.5.1.7(B) grandfathers in 'a municipality, county or other political subdivision established as an AHJ prior to July 1, 2009, with authority over specified trades' to 'continue in that capacity without a full-service building department until relinquishing its authority as a building trades department' -- since Chapter 15.08's electrical-permit ordinance is pre-1992-codification text, it would qualify for this grandfather clause if validly established as such an AHJ before 2009, but no published document confirms whether the City has ever formally relinquished that authority. Separately, the City's own live Departments listing (lovington.org/departments/, checked 2026-07-23) publishes no Building Department, Building Official, or Electrical Inspector department among its 14 listed departments -- though Municipal Code 17.08.050 (a different title, governing zoning-permit enforcement) assigns a comparable 'city building inspector' function to 'the city manager or his designee,' so the absence of a standalone department listing does not by itself prove Chapter 15.08's electrical-inspector function has lapsed. The underlying enforcement-in-practice question remains genuinely unresolved by any published source.

Reviewed 2026-07-19 · Source

When you need this permit

  • A permit from the electrical inspector is required before installing, altering, or adding to wiring, devices, or equipment for transmission, distribution, or utilization of electrical energy for light, power, or heat, or before disconnecting/reconnecting any motor, within or on any building or structure (Municode 15.08.030); in an emergency when the building department is closed, the permit must be secured as soon as possible thereafter
  • Application must state information required under Municode 15.08.050
  • Work must comply with the National Electrical Code, 1956 Edition, as amended (Municode 15.08.020) — in practice, the current governing electrical code is the CID-administered 2020 New Mexico Electrical Code / 2020 NEC (NMAC 14.10.4)
  • Concealed installations require inspection before being covered (Municode 15.08.180)
  • Noncompliant work is red-tagged and may not be covered or concealed (Municode 15.08.130); a white-tag certificate of approval is required before connection to electrical service (Municode 15.08.140)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

New work or addition to old work — first ten outletsCity of Lovington Code of Ordinances Section 15.08.060 (Fee schedule), Prior code Section 16-1-8 — a per-item schedule carried forward from the pre-1992 codification, not updated since; likely a vestigial figure not reflective of current administrative practice, since no matching current fee table is published elsewhere. CONFIRMED CURRENT PER THE CODE (re-chased 2026-07-19): read the City's complete Ordinance List and Disposition Table (codelibrary.amlegal.com, all ordinances 218 through 612, current supplement 2026 S-21 through Ord. 612, passed 6-9-25) end to end — no ordinance has ever amended, repealed, or superseded Chapter 15.08 or Section 15.08.060 since the 1992 codification; the only Title 15 ordinance on record (Ord. 546, 2016) amended Section 15.04.010 (Uniform Building Code adoption) instead. Also confirmed no standalone City fee resolution/schedule exists anywhere (searched lovington.org, Municipal Code Title 3 Revenue and Finance, and NM Sunshine Portal/NM DFA LGBMS — none found) that could have superseded this schedule administratively. So this cents-and-low-dollar schedule is not an extraction error or an overlooked update — it is genuinely still the only electrical-fee text on the books, administratively unusual as that is, and the tension with current CID-routed electrical permitting (see description/tips) remains unresolved by any published document.
$0.20 each
Motors over 1/3 horsepowerLovington Code of Ordinances Section 15.08.060, Prior code Section 16-1-8 — see the supersession-check note on the first fee line item above (re-chased 2026-07-19): confirmed never amended through the current Ord. 612 (6-9-25) supplement.
$1.00 per horsepower or fraction thereof, per motor, maximum $3.00 per motor
Inspection of apparatus with no prescribed feeLovington Code of Ordinances Section 15.08.060, Prior code Section 16-1-8 — see the supersession-check note on the first fee line item above (re-chased 2026-07-19): confirmed never amended through the current Ord. 612 (6-9-25) supplement.
$1.00 for the first hour or fraction thereof, plus $1.00 for each additional hour or fraction thereof

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit (City Electrical Inspector) permit actually take in Lovington?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Concealed Installation Inspection

    Required before concealed electrical work is covered (Municode 15.08.180)

  2. 2

    Final / Certificate of Approval

    White-tag certificate of approval required before connection to electrical service (Municode 15.08.140)

See the full Lovington inspection guide — scheduling & re-inspection fees →

Tips

  • This chapter's fee schedule (cents-per-outlet, dollar-per-horsepower) and its underlying 'National Electrical Code, 1956 Edition' citation are both legacy, pre-1992-codification text (Prior code Section 16-1-2 / 16-1-8) — a full re-check of the City's Ordinance List and Disposition Table (2026-07-19) confirms it has never been amended through the current Ord. 612 (6-9-25) supplement, so this is confirmed still the current codified figure, not an overlooked update; treat it with caution as administratively vestigial and confirm actual counter practice directly with the City rather than assuming it is charged at face value.
  • The City's own newer Building Permit Application checklist states that plumbing, electrical, and structural work are covered by 'State building permits,' i.e. the CID permit — it is not clear from any published city document whether the separately codified Chapter 15.08 City electrical inspector/permit is still independently enforced alongside the CID permit, or has been superseded by it in practice. This tension is documented here rather than resolved by assumption.
  • RE-CHASED 2026-07-23: N.M. Admin. Code 14.5.1.7(B)'s pre-2009 AHJ grandfather clause could legally explain why Chapter 15.08 remains on the books, but does not by itself confirm it is still actively enforced; the City's current lovington.org Departments page lists no separate Building Department/Electrical Inspector department, though a comparable 'city building inspector' role is assigned by Municipal Code 17.08.050 (Title 17 Zoning) to the city manager or a designee. Confirm directly with the Planning & Zoning Coordinator (cball@lovington.org, (575) 396-9301) whether Chapter 15.08's electrical permit is still collected in practice before assuming either the legacy fee schedule or the CID-only process controls.

Frequently asked questions

Lovington requires an electrical permit (city electrical inspector) for: A permit from the electrical inspector is required before installing, altering, or adding to wiring, devices, or equipment for transmission, distribution, or utilization of electrical energy for light, power, or heat, or before disconnecting/reconnecting any motor, within or on any building or structure (Municode 15.08.030); in an emergency when the building department is closed, the permit must be secured as soon as possible thereafter; Application must state information required under Municode 15.08.050; Work must comply with the National Electrical Code, 1956 Edition, as amended (Municode 15.08.020) — in practice, the current governing electrical code is the CID-administered 2020 New Mexico Electrical Code / 2020 NEC (NMAC 14.10.4); Concealed installations require inspection before being covered (Municode 15.08.180); Noncompliant work is red-tagged and may not be covered or concealed (Municode 15.08.130); a white-tag certificate of approval is required before connection to electrical service (Municode 15.08.140). If your project isn't listed, confirm with City of Lovington Planning and Zoning Department at (575) 396-9301 (Planning & Zoning Coordinator Crystal R. Ball, CFM, CZO); (575) 396-2884 (City Hall main line) before starting work.

In Lovington, the published New work or addition to old work — first ten outlets is: $0.20 each. Additional published fees: Motors over 1/3 horsepower — $1.00 per horsepower or fraction thereof, per motor, maximum $3.00 per motor; Inspection of apparatus with no prescribed fee — $1.00 for the first hour or fraction thereof, plus $1.00 for each additional hour or fraction thereof. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Lovington does not publish a plan-review timeline for this permit. Contact City of Lovington Planning and Zoning Department at (575) 396-9301 (Planning & Zoning Coordinator Crystal R. Ball, CFM, CZO); (575) 396-2884 (City Hall main line) for current turnaround.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

Lovington requires 2 inspection(s) for an electrical permit (city electrical inspector), in order: Concealed Installation Inspection, Final / Certificate of Approval. Schedule each through City of Lovington Planning and Zoning Department ((575) 396-9301 (Planning & Zoning Coordinator Crystal R. Ball, CFM, CZO); (575) 396-2884 (City Hall main line)).

Apply through City of Lovington Planning and Zoning Department at 214 S. Love Street, Lovington, NM 88260 (address on the Planning & Zoning Coordinator's own permit-checklist forms and P&Z Application cover sheet; the City's own Departments webpage separately lists the same office at 201 S Main Street, Lovington, NM 88260 — both addresses are published on official city.lovington.org pages as of 2026-07-18, discrepancy not resolved by any further published source). Phone: (575) 396-9301 (Planning & Zoning Coordinator Crystal R. Ball, CFM, CZO); (575) 396-2884 (City Hall main line), email: cball@lovington.org. Office hours: Monday-Thursday 7:30 AM - 5:00 PM, Friday 8:00 AM - 12:00 PM (noon), walk-in basis. Official information: https://www.lovington.org/departments/planning-and-zoning/.

Lovington, New Mexico has adopted: New Mexico is a statewide-code state administered by the Construction Industries Division (CID) of the Regulation and Licensing Department (RLD) under the Construction Industries Licensing Act (CILA), NMSA 1978 Sections 60-13-3 and 60-13-45. City of Lovington Municode Section 15.04.010 adopts by reference 'the state building code also known as the International Conference of Building Officials Uniform Building Code, 2009 or any adopted edition adopted by the State of New Mexico hence forth,' with all conditions, provisions, limitations and terms of the current New Mexico State building code adopted as the City's own building rules and regulations (Ord. 546, 2016; amended during 1992 codification: prior code Section 14-1-1). Unlike the City of Hobbs, Lovington has NOT established its own certified Building Inspection Department to administer the CID-adopted code as a delegated Authority Having Jurisdiction: the City's own Planning and Zoning Department and Building Permit Application checklist explicitly state that 'State building permits are required for the construction, repair or demolition of site-built or modular homes,' covering plumbing, electrical, and structural work — the actual building/electrical/plumbing/mechanical permit is a New Mexico Construction Industries Division (CID) permit, applied for directly with the State after the City Planning & Zoning Coordinator and Floodplain Manager sign a cover sheet confirming zoning, setback, and floodplain compliance.; 2021 New Mexico Commercial Building Code (NMCBC, NMAC 14.7.2) and 2021 New Mexico Residential Building Code (NMRBC, NMAC 14.7.3) — the current statewide editions administered by CID, which supersede the 2009 UBC edition-year text still printed in Lovington Municode 15.04.010 by operation of that same section's 'or any adopted edition adopted by the State of New Mexico hence forth' clause; 2020 New Mexico Electrical Code / 2020 National Electrical Code (NMAC 14.10.4) — the current CID-administered statewide electrical code; Lovington's own Municode Section 15.08.020 separately adopts 'the National Electrical Code, 1956 Edition, as the same are now or may be amended' (Prior code Section 16-1-2) as the basis for the City's own, separately-codified electrical permit and electrical inspector chapter (15.08) — a legacy municipal ordinance whose relationship to the newer City practice of routing electrical work through the State CID permit is not clarified in any published city document; 2021 New Mexico Plumbing and Mechanical Code (NMAC 14.8.2, 14.9.2) — CID-administered statewide; New Mexico Regulation and Licensing Department, Construction Industries Division rules, laws, and building codes (statewide adoption authority). Local amendments apply — see the Lovington overview page for the full list.

Lovington's Municipal Code (Chapter 15.08) still codifies a City electrical permit issued by a City 'electrical inspector,' with its own legacy fee schedule. However, the City's own current Building Permit checklist describes electrical work as covered by the State CID building permit process. No published city source clarifies how these two requirements interact today.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lovington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.