Solar PV Permit in Lovington, New Mexico

Required for installation of rooftop or ground-mounted solar photovoltaic systems in Lovington. As with Lovington's general Building Permit, the City's own Planning and Zoning Application has no dedicated Solar/Photovoltaic checkbox among its listed Type(s) — a PV installation would be filed as 'OTHER' (specified) or as an 'ADDITION,' with the City reviewing zoning/floodplain/site-plan compliance and signing a cover sheet BEFORE the applicant submits the actual electrical/structural permit application to the New Mexico Construction Industries Division (CID), which is the entity that actually issues the electrical permit governing the PV interconnection.

Verified 2026-07-20 · Source

When you need this permit

  • Filed on the same Lovington Planning and Zoning Application used for all other development permit types — the form's Type(s) checklist (Addition, Building Residential/Commercial, Carport, Curb Cut, Fence, Manufactured/Modular Home, New Home, Park, Porch, Roof/Re-Roof, Signage, Storage Unit, Sewer/Water Connection, Tower, Vacation, Variance, Zone Change, Other) has no dedicated Solar/Photovoltaic line; mark 'Other' and specify Solar/Photovoltaic, or file as an Addition if structurally tied to an existing building permit application
  • Submit a completed, legible, signed and dated Planning and Zoning Application plus proof of ownership or interest in the property
  • Submit a site plan showing property lines, building dimensions, lot area/dimensions, easements, building setbacks, road access points, and location of utilities/proposed array
  • Submit a Property Address for the Lea County Enhanced 9-1-1 System and a Floodplain Determination Letter, consistent with the general Building Permit checklist requirements
  • Submit a complete State building permit (CID) application cover sheet for the City Planner and Floodplain Manager signatures before submitting the electrical/structural permit application to the New Mexico Construction Industries Division — the actual PV electrical interconnection permit is a State CID permit, not a City-issued permit
  • The separately codified City electrical permit under Lovington Municode Chapter 15.08 (issued by the City's own 'electrical inspector') may also apply to the PV interconnection scope — as with the general electrical-permit entry in this file, no published city document resolves whether this legacy City ordinance is enforced independently alongside, or has been superseded by, the State CID-routed process
  • Pass the City's preliminary inspection (zoning/setback compliance) before the City Planner will sign the State CID permit cover sheet, and a final inspection after construction

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

City Permit Fee (processing, zoning/floodplain sign-off)Not published as a fixed schedule for any Lovington development permit type, including solar — consistent with the general building-permit entry in this file, the dollar amount is filled in by City Planning & Zoning staff at the time of application. Checked the City's Forms and Documents page and Municipal Code Title 3 (Revenue and Finance) — no fee schedule/resolution covering solar or general development permits was found.
Not published — contact the department
State Building Permit (CID) Fee — structural/racking scopeConfirmed 2026-07-20 directly from the New Mexico Administrative Code, 14.5.5.11 NMAC (General Construction Building Permit Fees), New Mexico State Records Center and Archives (srca.nm.gov/wp-content/uploads/attachments/14.005.0005.pdf) — currently in force (last amended within Part 5, effective 7-1-04, no repeal on record). This is CID's statewide fee rule and governs Lovington directly since the City's own Planning & Zoning application only handles the zoning/site-plan portion, not a separate structural building-permit fee.
$3.00 per $1,000 of valuation up to $15,000, plus $1.00 per $1,000 of valuation over $15,000, plus a 20% plan review fee on top of the building permit fee
State Electrical Permit (CID) Fee — PV interconnection scopeConfirmed 2026-07-20 from two consistent, currently-live sources: NM RLD Construction Industries Division's own fee page (rld.nm.gov/construction-industries/forms-and-applications/fees/), and the underlying base rates codified at 14.5.5.12 NMAC ($25/$40/$55/$125/$200 by the same tiers, "multiplied by 1.8 or $48.00/hr" per the rule text) — the live CID page's figures are exactly the NMAC base rate x 1.8, confirming both sources describe the same currently-effective schedule.
Residential, by service size: 100A or less $45.00; over 100-200A $72.00; over 200-320A $99.00; over 320-400A $225.00; over 400A $360.00 (live CID rate, includes the 1.8x multiplier applied to the base NMAC rate); plus $40.00/hr for plan review

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Permit permit actually take in Lovington?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Preliminary Inspection (City)

    Verifies compliance with setbacks, zoning, and land development requirements before the City Planner will sign the State CID permit cover sheet

  2. 2

    Final Inspection (City)

    Confirms completed work meets City zoning/site requirements, separate from any State CID electrical code-compliance inspection

See the full Lovington inspection guide — scheduling & re-inspection fees →

Tips

  • Lovington's Planning and Zoning Application has no dedicated Solar/Photovoltaic checkbox — mark 'Other' and specify, following the same pattern used for other project types without a dedicated line item.
  • As with the general Building Permit, the actual electrical permit for the PV interconnection is a New Mexico Construction Industries Division (CID) permit obtained directly from the State after the City signs off on zoning/floodplain/site-plan compliance — Lovington itself does not issue a valuation-based building/electrical permit.
  • Budget time for the Lea County Enhanced 9-1-1 addressing step and the City Floodplain Determination Letter, both required before City sign-off on the State CID cover sheet.

Frequently asked questions

Lovington requires a solar pv permit for: Filed on the same Lovington Planning and Zoning Application used for all other development permit types — the form's Type(s) checklist (Addition, Building Residential/Commercial, Carport, Curb Cut, Fence, Manufactured/Modular Home, New Home, Park, Porch, Roof/Re-Roof, Signage, Storage Unit, Sewer/Water Connection, Tower, Vacation, Variance, Zone Change, Other) has no dedicated Solar/Photovoltaic line; mark 'Other' and specify Solar/Photovoltaic, or file as an Addition if structurally tied to an existing building permit application; Submit a completed, legible, signed and dated Planning and Zoning Application plus proof of ownership or interest in the property; Submit a site plan showing property lines, building dimensions, lot area/dimensions, easements, building setbacks, road access points, and location of utilities/proposed array; Submit a Property Address for the Lea County Enhanced 9-1-1 System and a Floodplain Determination Letter, consistent with the general Building Permit checklist requirements; Submit a complete State building permit (CID) application cover sheet for the City Planner and Floodplain Manager signatures before submitting the electrical/structural permit application to the New Mexico Construction Industries Division — the actual PV electrical interconnection permit is a State CID permit, not a City-issued permit; The separately codified City electrical permit under Lovington Municode Chapter 15.08 (issued by the City's own 'electrical inspector') may also apply to the PV interconnection scope — as with the general electrical-permit entry in this file, no published city document resolves whether this legacy City ordinance is enforced independently alongside, or has been superseded by, the State CID-routed process; Pass the City's preliminary inspection (zoning/setback compliance) before the City Planner will sign the State CID permit cover sheet, and a final inspection after construction. If your project isn't listed, confirm with City of Lovington Planning and Zoning Department at (575) 396-9301 (Planning & Zoning Coordinator Crystal R. Ball, CFM, CZO); (575) 396-2884 (City Hall main line) before starting work.

Lovington does not publish a plan-review timeline for this permit. Contact City of Lovington Planning and Zoning Department at (575) 396-9301 (Planning & Zoning Coordinator Crystal R. Ball, CFM, CZO); (575) 396-2884 (City Hall main line) for current turnaround.

You'll need: Planning and Zoning Application; State Building Permit (CID) Application. Depending on your project, Lovington may also ask for: Affidavit by Property Owner(s). See the required-documents checklist on this page for details on each.

Lovington requires 2 inspection(s) for a solar pv permit, in order: Preliminary Inspection (City), Final Inspection (City). Schedule each through City of Lovington Planning and Zoning Department ((575) 396-9301 (Planning & Zoning Coordinator Crystal R. Ball, CFM, CZO); (575) 396-2884 (City Hall main line)).

Apply through City of Lovington Planning and Zoning Department at 214 S. Love Street, Lovington, NM 88260 (address on the Planning & Zoning Coordinator's own permit-checklist forms and P&Z Application cover sheet; the City's own Departments webpage separately lists the same office at 201 S Main Street, Lovington, NM 88260 — both addresses are published on official city.lovington.org pages as of 2026-07-18, discrepancy not resolved by any further published source). Phone: (575) 396-9301 (Planning & Zoning Coordinator Crystal R. Ball, CFM, CZO); (575) 396-2884 (City Hall main line), email: cball@lovington.org. Office hours: Monday-Thursday 7:30 AM - 5:00 PM, Friday 8:00 AM - 12:00 PM (noon), walk-in basis. Official information: https://www.lovington.org/departments/planning-and-zoning/.

Lovington, New Mexico has adopted: New Mexico is a statewide-code state administered by the Construction Industries Division (CID) of the Regulation and Licensing Department (RLD) under the Construction Industries Licensing Act (CILA), NMSA 1978 Sections 60-13-3 and 60-13-45. City of Lovington Municode Section 15.04.010 adopts by reference 'the state building code also known as the International Conference of Building Officials Uniform Building Code, 2009 or any adopted edition adopted by the State of New Mexico hence forth,' with all conditions, provisions, limitations and terms of the current New Mexico State building code adopted as the City's own building rules and regulations (Ord. 546, 2016; amended during 1992 codification: prior code Section 14-1-1). Unlike the City of Hobbs, Lovington has NOT established its own certified Building Inspection Department to administer the CID-adopted code as a delegated Authority Having Jurisdiction: the City's own Planning and Zoning Department and Building Permit Application checklist explicitly state that 'State building permits are required for the construction, repair or demolition of site-built or modular homes,' covering plumbing, electrical, and structural work — the actual building/electrical/plumbing/mechanical permit is a New Mexico Construction Industries Division (CID) permit, applied for directly with the State after the City Planning & Zoning Coordinator and Floodplain Manager sign a cover sheet confirming zoning, setback, and floodplain compliance.; 2021 New Mexico Commercial Building Code (NMCBC, NMAC 14.7.2) and 2021 New Mexico Residential Building Code (NMRBC, NMAC 14.7.3) — the current statewide editions administered by CID, which supersede the 2009 UBC edition-year text still printed in Lovington Municode 15.04.010 by operation of that same section's 'or any adopted edition adopted by the State of New Mexico hence forth' clause; 2020 New Mexico Electrical Code / 2020 National Electrical Code (NMAC 14.10.4) — the current CID-administered statewide electrical code; Lovington's own Municode Section 15.08.020 separately adopts 'the National Electrical Code, 1956 Edition, as the same are now or may be amended' (Prior code Section 16-1-2) as the basis for the City's own, separately-codified electrical permit and electrical inspector chapter (15.08) — a legacy municipal ordinance whose relationship to the newer City practice of routing electrical work through the State CID permit is not clarified in any published city document; 2021 New Mexico Plumbing and Mechanical Code (NMAC 14.8.2, 14.9.2) — CID-administered statewide; New Mexico Regulation and Licensing Department, Construction Industries Division rules, laws, and building codes (statewide adoption authority). Local amendments apply — see the Lovington overview page for the full list.

No. Solar installations are filed on the same general Planning and Zoning Application used for all other development permit types — there is no dedicated Solar/Photovoltaic checkbox. Mark 'Other' and specify, or file as an Addition. The actual electrical/structural permit for the PV system is a State of New Mexico Construction Industries Division (CID) permit, obtained after the City signs off on zoning/floodplain compliance.

No dollar-figure fee schedule is published for any Lovington development permit, including solar. The City Permit Fee is filled in by staff at the time of application; the separate State CID permit fee is based on construction type, square footage, materials, and cost — contact a CID field office for a project-specific quote.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lovington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.