Commercial Tenant Improvement / Tenant Finish Permit in Nephi, Utah

Required for tenant improvement and tenant finish work in existing commercial buildings in Nephi. Nephi does not publish a distinct tenant-improvement application, checklist, or fee tier separate from its general Commercial Building Permit process — tenant improvement projects are processed as commercial construction using the same Building Permit Application, Commercial Permit Plan Check Fee, and valuation-based Building Permit Fee.

Reviewed 2026-07-23 · Source

When you need this permit

  • Tenant improvement or tenant finish work in an existing commercial building within Nephi
  • Completed Nephi City Building Permit Application, signed by owner and contractor
  • Compliance with Nephi's Commercial-Industrial zoning chart for the applicable zone
  • Construction documents showing the scope of tenant-space work (new vs. existing construction, MEP changes)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeNephi City Fee Schedule Report, 'Building Permit' > 'Miscellaneous Permit' > 'Building Permit' line — same valuation-driven methodology used for new commercial and residential permits; no separate tenant-improvement valuation bracket is published.
Based off valuation (no flat citywide table published)
Commercial Permit Plan Check FeeSame Commercial Permit Plan Check Fee documented on this file's Commercial Building Permit entry — Nephi's fee schedule does not carve out a lower tenant-improvement-specific plan check rate. Content-verified 2026-07-23 against the live Fee Schedule Report, effective 6/16/2026 (figure unchanged from the prior 6/3/2025 edition).
$600.00 minimum per plan; $150.00 per hour for review time exceeding 4 hours
Building Permit Application DepositSame deposit structure documented on this file's Residential and Commercial Building Permit entries.
$1,000.00 per permit (non-refundable; credited toward the Building Permit Fee at issuance)
Building Permit State SurchargeStatewide surcharge under Utah Code § 15A-1-403.
1% of building permit fee

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Tenant Improvement / Tenant Finish Permit permit actually take in Nephi?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Framing / Fire-Rated Assembly (if applicable)

    Wall construction and any fire-rated/occupancy separation assemblies verified before close-in, where the tenant improvement scope includes framing changes.

  2. 2

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in verified against submitted plans, scheduled through the respective Nephi City utility departments where applicable.

  3. 3

    Final

    All work complete; occupancy of the tenant space is prohibited until after final inspection and Certificate of Occupancy issuance.

See the full Nephi inspection guide — scheduling & re-inspection fees →

Tips

  • Nephi treats tenant improvement/tenant finish work as ordinary commercial construction for permitting and fee purposes — there is no separate TI application or discounted plan-check fee tier published as of 2026-07-19. Confirm scope-specific requirements directly with the Building Department (435-250-8086, building.permit@nephi.utah.gov) before applying.
  • The same $600 minimum Commercial Permit Plan Check Fee that applies to new commercial construction also applies to tenant improvement projects — there is no reduced rate for remodel-scope work in Nephi's published fee schedule.

Frequently asked questions

Nephi requires a commercial tenant improvement / tenant finish permit for: Tenant improvement or tenant finish work in an existing commercial building within Nephi; Completed Nephi City Building Permit Application, signed by owner and contractor; Compliance with Nephi's Commercial-Industrial zoning chart for the applicable zone; Construction documents showing the scope of tenant-space work (new vs. existing construction, MEP changes). If your project isn't listed, confirm with Nephi City Building Department (Planning and Zoning, Buildings, and Development) at (435) 250-8086 before starting work.

No. Nephi's published Building Permit Application and Fee Schedule Report do not distinguish tenant improvement/tenant finish work from new commercial construction — the same $600 minimum Commercial Permit Plan Check Fee, the same valuation-based Building Permit Fee, and the same $1,000 non-refundable Building Permit Application Deposit apply. Contact the Building Department at 435-250-8086 to confirm the fee for a specific tenant-improvement scope.

Nephi does not publish a plan-review timeline for this permit. Contact Nephi City Building Department (Planning and Zoning, Buildings, and Development) at (435) 250-8086 for current turnaround.

You'll need: Nephi City Building Permit Application; Construction Documents (Tenant Space Scope). See the required-documents checklist on this page for details on each.

Nephi requires 3 inspection(s) for a commercial tenant improvement / tenant finish permit, in order: Framing / Fire-Rated Assembly (if applicable), MEP Rough-In, Final. Schedule each through Nephi City Building Department (Planning and Zoning, Buildings, and Development) ((435) 250-8086).

Apply through Nephi City Building Department (Planning and Zoning, Buildings, and Development) at 21 E 100 N, Nephi, UT 84648. Phone: (435) 250-8086, email: building.permit@nephi.utah.gov. Office hours: Mon–Thu 7:30 AM – 5:30 PM, Fri 8:00 AM – 12:00 PM. Official information: https://www.nephi.utah.gov/283/Building-Permit.

Nephi, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide-mandatory edition per Utah Code § 15A-2-103(1)(a), effective July 1, 2026, binding on Nephi per § 15A-1-204; Nephi City's own Building Permit page links directly to the ICC code library (codes.iccsafe.org/codes/i-codes) rather than publishing a distinct local edition page, indicating adoption of whatever the current statewide-standard edition is without a documented local vintage override.; 2021 International Residential Code (IRC) — current statewide edition per Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update, same statutory basis as above.; 2024 International Plumbing Code (IPC) — current statewide edition per Utah Code § 15A-2-103(1)(d), effective July 1, 2026.; 2024 International Mechanical Code (IMC) — current statewide edition per Utah Code § 15A-2-103(1)(e), effective July 1, 2026.; 2024 International Fuel Gas Code (IFGC) — current statewide edition per Utah Code § 15A-2-103(1)(f), effective July 1, 2026; not separately itemized on Nephi's own Building Permit page, but applies statewide.; 2024 International Energy Conservation Code (IECC) with Utah amendments — current statewide edition per Utah Code § 15A-2-103(1)(h), effective July 1, 2026.; 2024 International Existing Building Code (IEBC) and the residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — adopted statewide per Utah Code § 15A-2-103(1)(i) and (1)(n) respectively; not separately itemized on Nephi's own Building Permit page, but apply statewide.; National Electrical Code (NEC) — Nephi's own Electrical Policy documents (Overhead/Underground Residential Electric Service requirements) require installation 'in accordance with the latest edition of the NATIONAL ELECTRIC CODE' — a self-updating reference with no specific year stated on the city's own documents. The current statewide edition is the 2023 NEC per Utah Code § 15A-2-103(1)(g), unchanged by the July 1, 2026 statewide update (a prior version of this entry incorrectly stated '2020 NEC' as if that were a specific city-documented edition; Nephi's own document does not name a year at all). Nephi Power Department administers electrical service inspections separately from the Building Department (435-623-0276).. Local amendments apply — see the Nephi overview page for the full list.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nephi building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Nephi.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.