EV Charger / EVSE Permit in Nephi, Utah

Nephi does not publish a distinct EV-charger fee line item. Per the Nephi City Fee Schedule (effective 6/16/2026), installing an EV charger (EVSE) is electrical work billed under one of the city's standalone electrical permit categories: the Electrical Meter Base Upgrade Permit ($75.00 per inspection, if a service/meter upgrade is required) or the Electrical Re-wire Permit (valuation-based, determined by the building inspector, for new circuit work).

Verified 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
  • New dedicated circuit and/or panel/meter-base capacity to serve the charger
  • Building Permit Application submitted to Nephi City (contracted plan review/building inspector services)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Meter Base Upgrade PermitNephi City Fee Schedule (effective 6/16/2026), 'Building Permit > Miscellaneous Permit > Electrical Meter Base Upgrade Permit.' Applies if the EV charger installation requires a meter base or service upgrade.
$75.00 per inspection
Electrical Re-wire PermitNephi City Fee Schedule (effective 6/16/2026), 'Building Permit > Miscellaneous Permit > Electrical Re-wire Permit.' Applies to new circuit/wiring work for an EV charger not requiring a meter base upgrade.
Building inspector determines fee by valuation
Building Permit State SurchargeNephi City Fee Schedule (effective 6/16/2026) — statewide surcharge under Utah Code § 15A-1-403.
1% of building permit fee

Review timeline

Plan reviewTypical estimate — confirm current times with the Nephi building department
~10–10 business days

How long did your EV Charger / EVSE Permit permit actually take in Nephi?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Inspection

    Inspection of the installed circuit, meter base/panel work, and EVSE equipment.

See the full Nephi inspection guide — scheduling & re-inspection fees →

Tips

  • Nephi has no distinct EV charger permit category — file it as an Electrical Meter Base Upgrade Permit ($75 per inspection) if a service upgrade is needed, or an Electrical Re-wire Permit (valuation-based) for new circuit work only.
  • The 'Subdivision Connection - Electric' ($500, up to 200 amps) and 'Non-subdivision Connection - Electric' (cost-estimate based) fees are utility meter-connection charges for new lots/service, not the applicable fee for adding an EV charger circuit to an already-served property.

Frequently asked questions

Nephi requires an ev charger / evse permit for: Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property; New dedicated circuit and/or panel/meter-base capacity to serve the charger; Building Permit Application submitted to Nephi City (contracted plan review/building inspector services). If your project isn't listed, confirm with Nephi City Building Department (Planning and Zoning, Buildings, and Development) at (435) 250-8086 before starting work.

No EV-specific fee is published. Per the Nephi City Fee Schedule (effective 6/16/2026), an EV charger install is billed under the standalone Electrical Meter Base Upgrade Permit ($75.00 per inspection) if a service upgrade is needed, or the Electrical Re-wire Permit (valuation-based, determined by the building inspector) for new circuit work.

Plan review for an ev charger / evse permit in Nephi typically runs 10–10 business days. This is an estimate, not a published figure — confirm current review times with Nephi City Building Department (Planning and Zoning, Buildings, and Development) at (435) 250-8086.

You'll need: Nephi City Building Permit Application. See the required-documents checklist on this page for details on each.

Nephi requires 1 inspection(s) for an ev charger / evse permit, in order: Electrical Inspection. Schedule each through Nephi City Building Department (Planning and Zoning, Buildings, and Development) ((435) 250-8086).

Apply through Nephi City Building Department (Planning and Zoning, Buildings, and Development) at 21 E 100 N, Nephi, UT 84648. Phone: (435) 250-8086, email: building.permit@nephi.utah.gov. Office hours: Mon–Thu 7:30 AM – 5:30 PM, Fri 8:00 AM – 12:00 PM. Official information: https://www.nephi.utah.gov/283/Building-Permit.

Nephi, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide-mandatory edition per Utah Code § 15A-2-103(1)(a), effective July 1, 2026, binding on Nephi per § 15A-1-204; Nephi City's own Building Permit page links directly to the ICC code library (codes.iccsafe.org/codes/i-codes) rather than publishing a distinct local edition page, indicating adoption of whatever the current statewide-standard edition is without a documented local vintage override.; 2021 International Residential Code (IRC) — current statewide edition per Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update, same statutory basis as above.; 2024 International Plumbing Code (IPC) — current statewide edition per Utah Code § 15A-2-103(1)(d), effective July 1, 2026.; 2024 International Mechanical Code (IMC) — current statewide edition per Utah Code § 15A-2-103(1)(e), effective July 1, 2026.; 2024 International Fuel Gas Code (IFGC) — current statewide edition per Utah Code § 15A-2-103(1)(f), effective July 1, 2026; not separately itemized on Nephi's own Building Permit page, but applies statewide.; 2024 International Energy Conservation Code (IECC) with Utah amendments — current statewide edition per Utah Code § 15A-2-103(1)(h), effective July 1, 2026.; 2024 International Existing Building Code (IEBC) and the residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — adopted statewide per Utah Code § 15A-2-103(1)(i) and (1)(n) respectively; not separately itemized on Nephi's own Building Permit page, but apply statewide.; National Electrical Code (NEC) — Nephi's own Electrical Policy documents (Overhead/Underground Residential Electric Service requirements) require installation 'in accordance with the latest edition of the NATIONAL ELECTRIC CODE' — a self-updating reference with no specific year stated on the city's own documents. The current statewide edition is the 2023 NEC per Utah Code § 15A-2-103(1)(g), unchanged by the July 1, 2026 statewide update (a prior version of this entry incorrectly stated '2020 NEC' as if that were a specific city-documented edition; Nephi's own document does not name a year at all). Nephi Power Department administers electrical service inspections separately from the Building Department (435-623-0276).. Local amendments apply — see the Nephi overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nephi building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.