Residential Building Permit in Nephi, Utah
Required for new single-family and duplex residential construction and any work regulated by the statewide-adopted 2021 IRC / 2024 IBC. Nephi's Building Department (staffed separately from the Juab County-contracted Planning and Zoning function) issues the permit; plan review and building inspection services are themselves delivered under a competitively-bid professional-services contract (RFP No. 22-01) rather than by county staff. The core Building Permit fee is valuation-based (no flat citywide table is published); a $1,000 non-refundable Building Permit Application Deposit is credited toward the final fee at issuance.
Verified 2026-07-19 · Source
When you need this permit
- New single-family or duplex residential construction, or any work regulated by the statewide-adopted 2021 IRC
- Completed Nephi City Building Permit Application (Rev. 12-6-23), signed by owner and contractor
- Signed Receipt of Nephi City Policy Documents (Electrical, Natural Gas, Sewer Lateral, and Curb/Gutter/Sidewalk policy packets)
- Two sets of plans and a plat map/site plan submitted to the Building Department after Planning and Zoning approval of the underlying land use application
- Toilet on site before work commences (per the official Building Permit Application, Page 2 conditions)
- Compliance with subdivision soils report recommendations where applicable (collapsible soils notice, per the official application form)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Plan Review
Performed by the contracted Plans Examiner per RFP No. 22-01 Section IV.B; generally completed within 10 business days of plan receipt, with correction-comment letters referencing specific code sections delivered to the city and applicant.
- 2
Building Inspection (Combination Building Inspector)
Field inspections performed by the contracted Combination Building Inspector per RFP No. 22-01 Section IV.C; inspections generally performed within 2 business days of the inspection request. Contact: Lane Allred, Building Inspector, nephi.inspector@nephi.utah.gov, (435) 610-0547.
- 3
Electrical Service Inspection
Inspection of electrical service construction/installation performed by the Nephi City Power Department (435-623-0276); 24 hours' prior notice required, per the Building Permit Policy Document Packet.
- 4
Natural Gas Service Inspection
Inspection of natural gas service construction/installation performed by the Nephi City Gas Department (435-623-4914); 24 hours' prior notice required.
- 5
Sewer Lateral Inspection
Inspection of sewer service construction/installation performed by the Nephi City Sewer Department (435-623-2349); 24 hours' prior notice required.
- 6
Curb, Gutter, Sidewalk, and Drive Approach Inspection
Required before and after construction of all concrete work in the public way, performed by the Nephi City Streets Department (435-623-0712); 24 hours' prior notice required. Sidewalk must pass ADA-compliance inspection for the $4,000 deposit to be refunded.
- 7
Final Inspection / Certificate of Occupancy
Occupancy of the structure is prohibited until after final inspections and Certificate of Occupancy issuance, per the official Building Permit Application (Page 2 conditions).
See the full Nephi inspection guide — scheduling & re-inspection fees →
Tips
- Nephi contracts Planning and Zoning functions to Juab County (per Nephi's own budget documentation: 'Nephi contracts with Juab County for planning services'), but the Building Department — permit issuance, plan review, and inspection — remains a distinct Nephi City function with its own staff (Building Permit Tech, Building Inspector) and its own budget line, separate from the county-contracted planning role. Plan review and inspection labor is itself delivered via a competitively-bid contractor relationship (RFP No. 22-01) shared across Nephi City, Levan Town, and Juab County, but Nephi City is the permit-issuing authority of record.
- The permit application must be signed on Page 2 to be complete — a page 1-only submission is explicitly rejected per the form's own instruction ('MUST SIGN ON PAGE 2 TO COMPLETE APPLICATION').
- A permit becomes null and void if construction is not commenced within 180 days, or if work is suspended/abandoned for 180 days at any point after commencement.
- The $1,000 Building Permit Application Deposit is non-refundable but is credited toward the final Building Permit Fee when the permit is issued; if the application is canceled, the deposit is retained to cover the cost of plan review already performed.
- Nephi's utility inspections (electrical, gas, sewer, curb/gutter/sidewalk) are scheduled separately through each respective city utility department, not through the Building Department's inspector — each requires 24 hours' advance notice.
- Nephi has no distinct EV charger / EVSE permit type or fee: a full-text check of Nephi's Fee Schedule Report (nephi.utah.gov/DocumentCenter/View/4127, PDF fetched and searched directly 2026-07-20) found zero mentions of 'EV,' 'electric vehicle,' 'charging station,' or 'EVSE.' A residential EV charger install is expected to route through the general Building Permit process as standard electrical work, with the electrical service inspection itself scheduled through Nephi City Power (435-623-0276, 24 hours' advance notice) alongside the building permit; confirm current fee treatment directly with the Nephi City Building Department.
- RFP No. 22-01 explicitly states: 'Nephi City, and Levan Town are independent political subdivisions of the state of Utah operating within Juab County. Juab County is an independent political subdivision of the state of Utah' — confirming Nephi's separate legal and administrative status even though it shares contracted plan-review/inspection personnel with the county.
- Nephi has no distinct solar-PV permit type or fee: the city's Fee Schedule Report (effective 6/16/2026) itemizes dozens of specific trade/miscellaneous permits (fence, shed, re-roof, soffit/fascia, brick/siding, electrical meter base upgrade, electrical re-wire) but contains no 'solar' line anywhere, so rooftop or ground-mounted solar installations are permitted and fee-assessed through this same valuation-based Building Permit (re-checked directly against the full fee schedule PDF, 2026-07-19).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nephi building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Nephi
Residential Building Permit in other cities
Compare residential building permit fees across Utah →