Murray building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Murray, Utah.
Verified 2026-07-04 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 10 E 4800 S, Suite 260, Murray, UT 84107
- Phone
- (801) 270-2431
- Office hours
- Mon–Fri 8:00 AM – 5:00 PM
- Website
- Official site
Published scheduling rules
- This is a separate Fire Marshals Office permit and fee track from the Building Division's 'Building Permit Fees' sheet — the $150 plan review plus $50 per inspection line items are not part of the Building Division's valuation-based fee table. (Fire Sprinkler System Permit)
- This is a separate Fire Marshals Office permit and fee track from the Building Division's 'Building Permit Fees' sheet — the $150 plan review plus $50 per inspection line items are not part of the Building Division's valuation-based fee table. (Fire Alarm and Detection System Permit)
- Murray is transitioning from a legacy Munis permitting system to eProcess 360 — permits starting with 'E' require online inspection requests at murray.ut.eprocess360.com; older permits still use the phone line (801-270-2431, option 1). (General)
Inspection sequence
Applies to: Residential Building Permit
- 1
Building, Electrical, Mechanical & Plumbing
Combined trade inspection line administered by the Building Inspection Division, per the official Certificate of Occupancy Requirements form (Doc 15706). Scheduled via eProcess 360 (permits starting with 'E') or the legacy Munis phone line (801-270-2431, option 1) per Murray's Inspection Scheduling Changes notice.
- 2
Engineering & SWPP
Required sign-off for any work performed in the public way (driveways, curb and gutter, drainage systems, public sidewalks) per the Certificate of Occupancy Requirements form. Contact: (801) 270-2454.
- 3
Fire
Fire Department sign-off required before Certificate of Occupancy issuance. Contact: (801) 264-2776.
- 4
Planning/Zoning
Planning/Zoning sign-off required before Certificate of Occupancy issuance. Contact: (801) 270-2426.
- 5
Final / Certificate of Occupancy
Certificate of Occupancy or Temporary Certificate of Occupancy issued 5 to 10 working days after the General Contractor of record submits the completed Requirements form. Per the form: 'A Certificate of Occupancy or Temporary Certificate of Occupancy will be issued 5 to 10 working days.'
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Standard IBC inspection sequence before concrete pour; verified against the submitted structural drawings and geotechnical report.
- 2
Structural / Framing
Framing, floor and roof framing, and diaphragm connections verified against the submitted structural calculations.
- 3
MEP Rough-In
Electrical, mechanical, and plumbing rough-in verified against the submitted plans.
- 4
Final
Certificate of Occupancy issued once all sign-offs are complete, per Murray's 'Requirements For A Certificate Of Occupancy' form.
Applies to: Fire Sprinkler System Permit
- 1
Fire Sprinkler Flow Test / Riser Inspection
Per the Fire and Life Safety Fee Schedule, administered by the Murray City Fire Marshals Office (801-264-2780).
- 2
Fire Sprinkler 200lbs Test
Per the Fire and Life Safety Fee Schedule.
- 3
Fire Sprinkler Above the Grid and Bracing Inspection
Per the Fire and Life Safety Fee Schedule.
- 4
Fire Sprinkler Final Inspection
Per the Fire and Life Safety Fee Schedule; required before off-site monitoring and building final sign-off.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Fire-Rated Assembly
Wall construction and any fire-rated/occupancy separation assemblies verified before close-in, per the Commercial Tenant Improvement checklist.
- 2
MEP Rough-In
Electrical (lighting, fire alarm/smoke detectors), mechanical (exhaust fans, fire/smoke dampers), and plumbing (fixture locations) rough-in verified against the submitted plans.
- 3
Final
Exit signage, emergency lighting, and all finishes verified complete before occupancy.
Applies to: Change of Occupancy / Change of Use Permit
- 1
Building Inspection Division Review
The Building Inspection Division reviews and comments on the architect's hazard analysis and upgrade plan before permits are issued for the identified work; additional issues may need to be addressed after review, per Murray's official 'Change of Occupancy' policy.
- 2
Final / Certificate of Occupancy
A Certificate of Occupancy or Temporary Certificate of Occupancy is issued once all sign-offs (Building/Electrical/Mechanical/Plumbing, Engineering & SWPP, Fire, Planning/Zoning) are complete, per Murray's Requirements For A Certificate Of Occupancy form — required before the new use may occupy the space, per IBC 2021 Section 111.
Applies to: Fire Alarm and Detection System Permit
- 1
Fire Alarm Test/Inspection
Per the Fire and Life Safety Fee Schedule, administered by the Murray City Fire Marshals Office (801-264-2780).
- 2
Fire Alarm 24hr Battery Test
Per the Fire and Life Safety Fee Schedule.
Applies to: Residential Addition / Remodel Permit (incl. Basement Finish)
- 1
Framing
Wall framing and fire blocking inspection, part of the combined Building/Electrical/Mechanical/Plumbing inspection line (801-270-2431) per the Certificate of Occupancy Requirements form.
- 2
Final / Certificate of Occupancy
Certificate of Occupancy or Temporary CO issued 5 to 10 working days after the General Contractor of record submits the completed sign-off form, per Murray's official CO Requirements form.
Applies to: Solar Panel (PV) Permit
- 1
Final Inspection
Once solar system installation is complete, contact the Murray City Building Inspection Division at (801) 270-2431 to schedule an inspection, per the Murray City Power Net Metering Checklist.
- 2
Net Meter Installation
After final inspection passes, contact Murray City Power's Metering Supervisor (Victor Meza, 801-264-2724) to test the new system and install the net and production meters. Customer may not connect panels to Murray's system until the new net meter is installed — connecting early causes excess generation to register as consumption rather than credit, per the Net Metering Checklist.
Final inspection only: Electrical Permit, Plumbing Permit, EV Charger / EVSE Permit, Mechanical / HVAC Permit, Roofing / Re-Roof Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Murray building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Murray building permits
Get alerts for Murray
We'll email you when Murray's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.