Solar Panel (PV) Permit in Murray, Utah

Required for residential rooftop solar photovoltaic installations in Murray. Murray City Power (the municipal electric utility) requires a separate Net Metering Interconnection & Service Agreement in addition to the city building permit — this is a two-track process fully documented in Murray's own Residential Solar Panel Plan Submittal Requirements (rev. 09/24/2025) and Murray City Power Net Metering Checklist.

Verified 2026-07-19 · Source

When you need this permit

  • Murray Power approval required — contact netmetering@murray.utah.gov for the Net Metering Interconnection & Service Agreement
  • Building permit application via eProcess 360, including project valuation and contractor/subcontractor information
  • Site (plot) plan showing north arrow, home location, and all PV components grouped in an area not exceeding 6 feet (main meter, production meter, AC disconnect, module array(s), inverter(s))
  • One-line diagram showing PV system type, meters, disconnect and inverter ratings, module layout/wiring, maximum system output (system output capped at 10 kW per Murray's checklist), and grounding
  • Module/inverter/combiner box manufacturer specifications; engineer of record confirmation that the roof can support the added solar array load
  • Safety and warning labels: engraved, mechanically fastened (not taped) labels reading 'Solar Generation On Site' at meter bases and 'Solar Power Disconnect' at the safety disconnect switch

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Solar Roof & Ground Mounted Fee (residential)Murray City Building Permit Fees table, effective 07/01/2026: 'Solar Roof & Ground Mounted — Residential: $394.'
$394 flat
Solar Roof & Ground Mounted Fee (commercial)Murray City Building Permit Fees table, effective 07/01/2026: 'Solar Roof & Ground Mounted — Commercial: **BOV + 65% *PRF.'
Based on Valuation (BOV) + 65% Plan Review Fee
Net Meter Purchase Fee (Murray City Power)Murray City Power Net Metering Checklist: 'Purchase Net Meter — Residential Customer Net Meter - $250; Commercial Customer Net Meter - $350.' Paid to Murray City Power, 153 West 4800 South, Murray, UT 84107.
$250 (residential customer); $350 (commercial customer)
Energy Storage System (ESS) FeeMurray City Building Permit Fees table, effective 07/01/2026: 'Energy Storage System (ESS) — Residential: $300 + $20 ea addtl; Commercial: $300 + $20 ea addtl.'
$300 + $20 for each additional unit (residential and commercial)

Review timeline

Plan review
Not published — contact the department

How long did your Solar Panel (PV) Permit permit actually take in Murray?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

    Once solar system installation is complete, contact the Murray City Building Inspection Division at (801) 270-2431 to schedule an inspection, per the Murray City Power Net Metering Checklist.

  2. 2

    Net Meter Installation

    After final inspection passes, contact Murray City Power's Metering Supervisor (Victor Meza, 801-264-2724) to test the new system and install the net and production meters. Customer may not connect panels to Murray's system until the new net meter is installed — connecting early causes excess generation to register as consumption rather than credit, per the Net Metering Checklist.

See the full Murray inspection guide — scheduling & re-inspection fees →

Tips

  • Murray City Power requires a production/generation meter in addition to the net (bidirectional) meter; Murray City Power covers the cost of the production meter itself, but the customer pays the $250 (residential) or $350 (commercial) net meter fee.
  • A separate, manually-operated safety disconnect switch (with visibly open/closed contacts) must be installed between the inverter and the production meter, within several feet of the net meter — meter-base circuit breakers or inverter-integrated disconnects do NOT satisfy this requirement, per Murray City Power's diagram (rev. March 2017).
  • System output is capped at 10 kW maximum on Murray's residential solar checklist.
  • All PV system components (main meter, production meter, AC disconnect, module array, inverter) must be grouped within a 6-foot maximum span, per Murray's Site Plan checklist requirement.
  • Do not energize/connect panels before Murray City Power installs the new net meter — early connection causes generated kWh to register as consumption, resulting in extra cost rather than credit.

Frequently asked questions

Murray requires a solar panel (pv) permit for: Murray Power approval required — contact netmetering@murray.utah.gov for the Net Metering Interconnection & Service Agreement; Building permit application via eProcess 360, including project valuation and contractor/subcontractor information; Site (plot) plan showing north arrow, home location, and all PV components grouped in an area not exceeding 6 feet (main meter, production meter, AC disconnect, module array(s), inverter(s)); One-line diagram showing PV system type, meters, disconnect and inverter ratings, module layout/wiring, maximum system output (system output capped at 10 kW per Murray's checklist), and grounding; Module/inverter/combiner box manufacturer specifications; engineer of record confirmation that the roof can support the added solar array load; Safety and warning labels: engraved, mechanically fastened (not taped) labels reading 'Solar Generation On Site' at meter bases and 'Solar Power Disconnect' at the safety disconnect switch. If your project isn't listed, confirm with Murray City Building Inspection Division (Community & Economic Development Department) at (801) 270-2431 before starting work.

Per Murray's official Building Permit Fees table (effective July 1, 2026), a residential Solar Roof & Ground Mounted permit is a flat $394, plus a separate $250 Net Meter purchase fee paid to Murray City Power per its Net Metering Checklist.

Murray does not publish a plan-review timeline for this permit. Contact Murray City Building Inspection Division (Community & Economic Development Department) at (801) 270-2431 for current turnaround.

You'll need: Residential Solar Panel Plan Submittal Requirements Checklist; Murray City Power Interconnection Agreement; Murray City Power Net Metering Checklist. See the required-documents checklist on this page for details on each.

Murray requires 2 inspection(s) for a solar panel (pv) permit, in order: Final Inspection, Net Meter Installation. Schedule each through Murray City Building Inspection Division (Community & Economic Development Department) ((801) 270-2431).

Apply through Murray City Building Inspection Division (Community & Economic Development Department) at 10 E 4800 S, Suite 260, Murray, UT 84107. Phone: (801) 270-2431, email: permits@murray.utah.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.murray.utah.gov/167/Building-Division.

Murray, Utah has adopted: 2024 International Building Code (IBC) — per Murray's own 'Notice of Building Code Adoption' (effective July 1, 2026) on the Building Division page; Utah Code § 15A-2-103(1)(a); superseded the 2021 IBC that had been in effect since July 1, 2023; 2021 International Residential Code (IRC) — Murray's Building Division page (Notice of Building Code Adoption, eff. 7/1/2026) states the IRC 'will remain 2021'; Utah Code § 15A-2-103(1)(b); unchanged by the 7/1/2026 code cycle; 2024 International Plumbing Code (IPC) — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(d); superseded the 2021 IPC that had been in effect since July 1, 2023; 2024 International Mechanical Code (IMC) — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(e); superseded the 2021 IMC that had been in effect since July 1, 2023; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective 2026-07-01, superseded the 2021 edition. NOTE: Murray's own city notice does not separately enumerate the IFGC (it lists IBC, IPC, IMC, IEBC, IECC, and NEC only) — this entry is sourced directly from the statute, which applies statewide regardless of whether a given city's own notice names it.; 2024 International Existing Building Code (IEBC) — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(i); superseded the 2021 IEBC that had been in effect since July 1, 2023; 2024 International Energy Conservation Code (IECC), as amended by the State of Utah — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(h); superseded the 2021 IECC that had been in effect since July 1, 2023; 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); effective 2026-07-01, superseded the 2021 edition. NOTE: Murray's own city notice does not separately enumerate the ISPSC — this entry is sourced directly from the statute, which applies statewide regardless of whether a given city's own notice names it.; 2023 National Electrical Code (NEC) — per Murray City Building Division page, adopted and unchanged by the July 1, 2026 update; Utah Code § 15A-2-103(1)(g); NOTE (verified 2026-07-16): Confirmed directly against Murray's own live 'Notice of Building Code Adoption' banner (murray.utah.gov/167/Building-Division, effective date July 1, 2026), which lists the 2024 IBC, IPC, IMC, IEBC, and IECC (Utah-amended), the 2023 NEC, and states the IRC 'will remain 2021.' Also confirmed directly against Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027) at le.utah.gov. CAUTION: the same Murray page also retains an older, unremoved 'Overview' paragraph further down stating 'As of July 1st 2023, the state of Utah has adopted the 2021 I Codes and the 2023 NEC' — that leftover sentence is stale and contradicts the page's own current banner; see tipsAndGotchas for this discrepancy.. Local amendments apply — see the Murray overview page for the full list.

Yes. Murray City Power requires a Net Metering Interconnection & Service Agreement, emailed to netmetering@murray.utah.gov, in addition to the standard city building permit. The Murray City Power Net Metering Checklist sequences both processes: Interconnection Agreement, Building Permit, Purchase Net Meter, Installation, Final Inspection, then Net Meter Installation.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Murray building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.