Residential Building Permit — Murray, Utah · Requirements sheet
Verified 2026-07-04 · Source: https://www.murray.utah.gov/DocumentCenter/View/19435/Building-Fee-Sheet-eff-07012026
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit in Murray, Utah
Required for new single-family and two-family residential construction and any work regulated by the adopted 2021 IRC / 2024 IBC. Murray's fee schedule uses its own valuation-based table (distinct from Provo's 1997 UBC chart) with a February 2026 ICC Building Valuation Data square-foot construction cost table.
Verified 2026-07-04 · Source
When you need this permit
- New single-family or two-family residential construction
- Any work regulated by the adopted 2021 IRC
- Structural modifications regulated by the adopted 2024 IBC / 2021 IRC
- Site plan drawn to scale showing actual lot dimensions, size and location of existing buildings, required per Murray City Code § 17.04.100
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Building, Electrical, Mechanical & Plumbing
Combined trade inspection line administered by the Building Inspection Division, per the official Certificate of Occupancy Requirements form (Doc 15706). Scheduled via eProcess 360 (permits starting with 'E') or the legacy Munis phone line (801-270-2431, option 1) per Murray's Inspection Scheduling Changes notice.
- 2
Engineering & SWPP
Required sign-off for any work performed in the public way (driveways, curb and gutter, drainage systems, public sidewalks) per the Certificate of Occupancy Requirements form. Contact: (801) 270-2454.
- 3
Fire
Fire Department sign-off required before Certificate of Occupancy issuance. Contact: (801) 264-2776.
- 4
Planning/Zoning
Planning/Zoning sign-off required before Certificate of Occupancy issuance. Contact: (801) 270-2426.
- 5
Final / Certificate of Occupancy
Certificate of Occupancy or Temporary Certificate of Occupancy issued 5 to 10 working days after the General Contractor of record submits the completed Requirements form. Per the form: 'A Certificate of Occupancy or Temporary Certificate of Occupancy will be issued 5 to 10 working days.'
See the full Murray inspection guide — scheduling & re-inspection fees →
Tips
- Murray's Building Division office is open Mon–Fri 8:00 AM–5:00 PM (no Friday closure, unlike Provo).
- Murray transitioned from the legacy Munis system to eProcess 360 — permit numbers starting with 'E' must have inspections requested online at murray.ut.eprocess360.com; older (non-'E') permits still use the phone line at (801) 270-2431, option 1.
- The Certificate of Occupancy Requirements form must be submitted only by the General Contractor of record — no one else is authorized to submit it, per the official form.
- Murray uses its own valuation-based building permit fee table (not the 1997 UBC chart used by Provo) — see the ICC Building Valuation Data, February 2026, for per-square-foot construction costs by occupancy group.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Murray building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Murray
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Murray project checklist
Describe your project once and get every permit, document, and fee it triggers in Murray — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →