Required for new commercial construction in Murray, regulated by the 2024 International Building Code (per Murray's own 'Notice of Building Code Adoption,' effective July 1, 2026; Utah Code § 15A-2-103(1)(a)). Murray's official Building Permit Fees table is titled 'Building Permit Fees, Commercial/Residential' — the same ICC-Building-Valuation-Data-based schedule used for the Residential Building Permit applies to commercial construction, using the February 2026 ICC Building Valuation Data Square Foot Construction Costs table for the applicable occupancy/construction type.

Verified 2026-07-19 · Source

When you need this permit

  • New commercial construction regulated by the 2024 IBC (per Murray's Notice of Building Code Adoption, effective July 1, 2026)
  • Project Approval from Murray City Planning & Zoning, or scheduling on the next available Planning Commission agenda, before the Building Department will accept the submittal for plan review — per Murray's official New Commercial Building Permit Requirements guide
  • Building Permit Application submitted electronically through eProcess 360 (murray.ut.eprocess360.com)
  • Restaurant plans require Salt Lake County Health Department approval prior to permit issuance
  • Structures in flood hazard areas require an elevation certificate

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation-based (Murray City table, effective 07/01/2026)Murray City 'Building Permit Fees, Commercial/Residential' table (dated 06.22.26, effective July 1, 2026), retrieved from murray.utah.gov/DocumentCenter/View/19435/Building-Fee-Sheet-eff-07012026 — this is the same table used for the Residential Building Permit; the table's own title confirms it applies to both. Valuation determined per the attached ICC Building Valuation Data, February 2026, Square Foot Construction Costs table.
$1.00–$500.00: $100.00 flat. $501.00–$2,000.00: $100.00 + $3.05 per additional $100 (or fraction). $2,001.00–$25,000.00: $150.00 + $14.00 per additional $1,000 (or fraction). $25,001.00–$50,000.00: $391.75 + $10.10 per additional $1,000. $50,001.00–$100,000.00: $643.75 + $7.00 per additional $1,000. $100,001.00–$500,000.00: $993.75 + $5.60 per additional $1,000. $500,001.00–$1,000,000.00: $3,233.75 + $4.75 per additional $1,000. $1,000,001.00 and up: $5,608.75 + $3.65 per additional $1,000.
No published generic plan-review-fee percentage for new commercial buildingMurray's Building Permit Fees packet publishes plan-review-fee (PRF) percentages only for specific narrow categories (e.g. ReRoof Commercial and Attached Signs at BOV + 10% PRF; Pole Signs, Cell Towers, Racking, Swimming Pool, Solar, and EV Chargers at BOV + 65% PRF) — no generic 'new commercial building' line with its own PRF percentage was found in the fee sheet. Omitted rather than assumed to match any single one of these category-specific rates.
Not found published
Re-inspection FeeMurray City Building Permit Fees packet, 'Other Inspections and Fees' item 2: 'Re-inspection fees assessed under provisions of Section 305.8 — $100.00 Per Hour.'
$100.00 per hour
Additional Plan Review (changes/additions/revisions)Murray City Building Permit Fees packet, 'Other Inspections and Fees' item 4.
$80.00 per hour (half-hour minimum)
Inspections Outside Normal Business HoursMurray City Building Permit Fees packet, 'Other Inspections and Fees' item 1.
$100.00 per hour (2-hour minimum)

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Murray?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footing

    Standard IBC inspection sequence before concrete pour; verified against the submitted structural drawings and geotechnical report.

  2. 2

    Structural / Framing

    Framing, floor and roof framing, and diaphragm connections verified against the submitted structural calculations.

  3. 3

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in verified against the submitted plans.

  4. 4

    Final

    Certificate of Occupancy issued once all sign-offs are complete, per Murray's 'Requirements For A Certificate Of Occupancy' form.

See the full Murray inspection guide — scheduling & re-inspection fees →

Tips

  • Murray requires Planning & Zoning project approval (or Planning Commission scheduling) before the Building Department will accept a new commercial building submittal for plan review.
  • Murray's Building Permit Fees table is explicitly titled 'Building Permit Fees, Commercial/Residential' — it is one shared valuation-based schedule, not separate residential and commercial tables.
  • Restaurant plans require Salt Lake County Health Department approval before the building permit can be issued.
  • Murray's own New Commercial Building Permit Requirements checklist (updated 9/16/24) still cites the 2021 IBC and 2021 IECC as design criteria — the city's own Notice of Building Code Adoption confirms the 2024 IBC and 2024 IECC are current as of July 1, 2026, so verify current code edition directly with the Building Division (801-270-2431).

Frequently asked questions

Murray requires a commercial building permit for: New commercial construction regulated by the 2024 IBC (per Murray's Notice of Building Code Adoption, effective July 1, 2026); Project Approval from Murray City Planning & Zoning, or scheduling on the next available Planning Commission agenda, before the Building Department will accept the submittal for plan review — per Murray's official New Commercial Building Permit Requirements guide; Building Permit Application submitted electronically through eProcess 360 (murray.ut.eprocess360.com); Restaurant plans require Salt Lake County Health Department approval prior to permit issuance; Structures in flood hazard areas require an elevation certificate. If your project isn't listed, confirm with Murray City Building Inspection Division (Community & Economic Development Department) at (801) 270-2431 before starting work.

Murray uses one shared 'Building Permit Fees, Commercial/Residential' valuation table for both residential and commercial construction: $100.00 flat for valuation up to $500, scaling to $5,608.75 plus $3.65 per additional $1,000 over $1,000,000, based on the February 2026 ICC Building Valuation Data. No generic commercial plan-review-fee percentage is separately published; a re-inspection fee of $100/hour and additional plan review at $80/hour (half-hour minimum) apply.

Murray does not publish a plan-review timeline for this permit. Contact Murray City Building Inspection Division (Community & Economic Development Department) at (801) 270-2431 for current turnaround.

You'll need: Building Permit Application (eProcess 360); New Commercial Building Permit Requirements Checklist; Structural Calculations. Depending on your project, Murray may also ask for: Special Inspection and Testing Agreement; Elevation Certificate. See the required-documents checklist on this page for details on each.

Murray requires 4 inspection(s) for a commercial building permit, in order: Foundation / Footing, Structural / Framing, MEP Rough-In, Final. Schedule each through Murray City Building Inspection Division (Community & Economic Development Department) ((801) 270-2431).

Apply through Murray City Building Inspection Division (Community & Economic Development Department) at 10 E 4800 S, Suite 260, Murray, UT 84107. Phone: (801) 270-2431, email: permits@murray.utah.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.murray.utah.gov/167/Building-Division.

Murray, Utah has adopted: 2024 International Building Code (IBC) — per Murray's own 'Notice of Building Code Adoption' (effective July 1, 2026) on the Building Division page; Utah Code § 15A-2-103(1)(a); superseded the 2021 IBC that had been in effect since July 1, 2023; 2021 International Residential Code (IRC) — Murray's Building Division page (Notice of Building Code Adoption, eff. 7/1/2026) states the IRC 'will remain 2021'; Utah Code § 15A-2-103(1)(b); unchanged by the 7/1/2026 code cycle; 2024 International Plumbing Code (IPC) — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(d); superseded the 2021 IPC that had been in effect since July 1, 2023; 2024 International Mechanical Code (IMC) — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(e); superseded the 2021 IMC that had been in effect since July 1, 2023; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective 2026-07-01, superseded the 2021 edition. NOTE: Murray's own city notice does not separately enumerate the IFGC (it lists IBC, IPC, IMC, IEBC, IECC, and NEC only) — this entry is sourced directly from the statute, which applies statewide regardless of whether a given city's own notice names it.; 2024 International Existing Building Code (IEBC) — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(i); superseded the 2021 IEBC that had been in effect since July 1, 2023; 2024 International Energy Conservation Code (IECC), as amended by the State of Utah — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(h); superseded the 2021 IECC that had been in effect since July 1, 2023; 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); effective 2026-07-01, superseded the 2021 edition. NOTE: Murray's own city notice does not separately enumerate the ISPSC — this entry is sourced directly from the statute, which applies statewide regardless of whether a given city's own notice names it.; 2023 National Electrical Code (NEC) — per Murray City Building Division page, adopted and unchanged by the July 1, 2026 update; Utah Code § 15A-2-103(1)(g); NOTE (verified 2026-07-16): Confirmed directly against Murray's own live 'Notice of Building Code Adoption' banner (murray.utah.gov/167/Building-Division, effective date July 1, 2026), which lists the 2024 IBC, IPC, IMC, IEBC, and IECC (Utah-amended), the 2023 NEC, and states the IRC 'will remain 2021.' Also confirmed directly against Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027) at le.utah.gov. CAUTION: the same Murray page also retains an older, unremoved 'Overview' paragraph further down stating 'As of July 1st 2023, the state of Utah has adopted the 2021 I Codes and the 2023 NEC' — that leftover sentence is stale and contradicts the page's own current banner; see tipsAndGotchas for this discrepancy.. Local amendments apply — see the Murray overview page for the full list.

Yes. Per Murray's official New Commercial Building Permit Requirements guide, the project must have Community Development acceptance — Project Approval from Murray City Planning & Zoning, or be scheduled for final approval on the next available Planning Commission agenda — before the Building Department will accept the submittal for plan review.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Murray building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Murray.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.