Commercial Building Permit in Murray, Utah
Required for new commercial construction in Murray, regulated by the 2024 International Building Code (per Murray's own 'Notice of Building Code Adoption,' effective July 1, 2026; Utah Code § 15A-2-103(1)(a)). Murray's official Building Permit Fees table is titled 'Building Permit Fees, Commercial/Residential' — the same ICC-Building-Valuation-Data-based schedule used for the Residential Building Permit applies to commercial construction, using the February 2026 ICC Building Valuation Data Square Foot Construction Costs table for the applicable occupancy/construction type.
Verified 2026-07-19 · Source
When you need this permit
- New commercial construction regulated by the 2024 IBC (per Murray's Notice of Building Code Adoption, effective July 1, 2026)
- Project Approval from Murray City Planning & Zoning, or scheduling on the next available Planning Commission agenda, before the Building Department will accept the submittal for plan review — per Murray's official New Commercial Building Permit Requirements guide
- Building Permit Application submitted electronically through eProcess 360 (murray.ut.eprocess360.com)
- Restaurant plans require Salt Lake County Health Department approval prior to permit issuance
- Structures in flood hazard areas require an elevation certificate
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footing
Standard IBC inspection sequence before concrete pour; verified against the submitted structural drawings and geotechnical report.
- 2
Structural / Framing
Framing, floor and roof framing, and diaphragm connections verified against the submitted structural calculations.
- 3
MEP Rough-In
Electrical, mechanical, and plumbing rough-in verified against the submitted plans.
- 4
Final
Certificate of Occupancy issued once all sign-offs are complete, per Murray's 'Requirements For A Certificate Of Occupancy' form.
See the full Murray inspection guide — scheduling & re-inspection fees →
Tips
- Murray requires Planning & Zoning project approval (or Planning Commission scheduling) before the Building Department will accept a new commercial building submittal for plan review.
- Murray's Building Permit Fees table is explicitly titled 'Building Permit Fees, Commercial/Residential' — it is one shared valuation-based schedule, not separate residential and commercial tables.
- Restaurant plans require Salt Lake County Health Department approval before the building permit can be issued.
- Murray's own New Commercial Building Permit Requirements checklist (updated 9/16/24) still cites the 2021 IBC and 2021 IECC as design criteria — the city's own Notice of Building Code Adoption confirms the 2024 IBC and 2024 IECC are current as of July 1, 2026, so verify current code edition directly with the Building Division (801-270-2431).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Murray building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Murray.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Murray
Commercial Building Permit in other cities
Compare commercial building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Murray project checklist
Describe your project once and get every permit, document, and fee it triggers in Murray — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →