Roofing / Re-Roof Permit in Murray, Utah

Required for roof replacement and re-roofing in Murray. Murray publishes a distinct flat residential re-roof fee (separate from its general valuation-based building permit fee), with an added charge if new sheathing is installed.

Verified 2026-07-04 · Source

When you need this permit

  • Complete roof replacement (tear-off and re-roof)
  • Re-roof involving new sheathing (additional fee applies)
  • Murray City Re-Roof Questionnaire required for plan submittal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

ReRoof Fee (residential)Murray City Building Permit Fees table, effective 07/01/2026: 'ReRoof — Residential: $200' with a listed addition 'W/ Sheathing Add: $100' (residential column).
$200 flat; add $100 if sheathing is being replaced
ReRoof Fee (commercial)Murray City Building Permit Fees table, effective 07/01/2026: 'ReRoof — Commercial: **BOV + 10% *PRF.'
Based on Valuation (BOV) + 10% Plan Review Fee

Review timeline

Plan review
Not published — contact the department

How long did your Roofing / Re-Roof Permit permit actually take in Murray?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Building, Electrical, Mechanical & Plumbing

    Combined trade inspection administered by the Building Inspection Division (801-270-2431). A Roof Warranty (TPO) is a listed line item on Murray's official Certificate of Occupancy Requirements form for applicable roofing systems.

See the full Murray inspection guide — scheduling & re-inspection fees →

Tips

  • Murray charges a distinct flat $200 residential re-roof fee (not the general BOV building-permit table) — add $100 if sheathing is being replaced as part of the re-roof.
  • Commercial re-roofing is charged Based on Valuation plus a 10% plan review fee, a lower plan-review percentage than the 65% rate used for pole signs, racking, and solar on the same fee sheet.

Frequently asked questions

Murray requires a roofing / re-roof permit for: Complete roof replacement (tear-off and re-roof); Re-roof involving new sheathing (additional fee applies); Murray City Re-Roof Questionnaire required for plan submittal. If your project isn't listed, confirm with Murray City Building Inspection Division (Community & Economic Development Department) at (801) 270-2431 before starting work.

Per Murray's official Building Permit Fees table (effective July 1, 2026), a residential re-roof is a flat $200, plus an additional $100 if new sheathing is installed.

Murray does not publish a plan-review timeline for this permit. Contact Murray City Building Inspection Division (Community & Economic Development Department) at (801) 270-2431 for current turnaround.

You'll need: Re-Roof Questionnaire; Building Permit Application (eProcess 360). See the required-documents checklist on this page for details on each.

Murray requires 1 inspection(s) for a roofing / re-roof permit, in order: Building, Electrical, Mechanical & Plumbing. Schedule each through Murray City Building Inspection Division (Community & Economic Development Department) ((801) 270-2431).

Apply through Murray City Building Inspection Division (Community & Economic Development Department) at 10 E 4800 S, Suite 260, Murray, UT 84107. Phone: (801) 270-2431, email: permits@murray.utah.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.murray.utah.gov/167/Building-Division.

Murray, Utah has adopted: 2024 International Building Code (IBC) — per Murray's own 'Notice of Building Code Adoption' (effective July 1, 2026) on the Building Division page; Utah Code § 15A-2-103(1)(a); superseded the 2021 IBC that had been in effect since July 1, 2023; 2021 International Residential Code (IRC) — Murray's Building Division page (Notice of Building Code Adoption, eff. 7/1/2026) states the IRC 'will remain 2021'; Utah Code § 15A-2-103(1)(b); unchanged by the 7/1/2026 code cycle; 2024 International Plumbing Code (IPC) — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(d); superseded the 2021 IPC that had been in effect since July 1, 2023; 2024 International Mechanical Code (IMC) — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(e); superseded the 2021 IMC that had been in effect since July 1, 2023; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective 2026-07-01, superseded the 2021 edition. NOTE: Murray's own city notice does not separately enumerate the IFGC (it lists IBC, IPC, IMC, IEBC, IECC, and NEC only) — this entry is sourced directly from the statute, which applies statewide regardless of whether a given city's own notice names it.; 2024 International Existing Building Code (IEBC) — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(i); superseded the 2021 IEBC that had been in effect since July 1, 2023; 2024 International Energy Conservation Code (IECC), as amended by the State of Utah — per Murray's Notice of Building Code Adoption (effective July 1, 2026); Utah Code § 15A-2-103(1)(h); superseded the 2021 IECC that had been in effect since July 1, 2023; 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); effective 2026-07-01, superseded the 2021 edition. NOTE: Murray's own city notice does not separately enumerate the ISPSC — this entry is sourced directly from the statute, which applies statewide regardless of whether a given city's own notice names it.; 2023 National Electrical Code (NEC) — per Murray City Building Division page, adopted and unchanged by the July 1, 2026 update; Utah Code § 15A-2-103(1)(g); NOTE (verified 2026-07-16): Confirmed directly against Murray's own live 'Notice of Building Code Adoption' banner (murray.utah.gov/167/Building-Division, effective date July 1, 2026), which lists the 2024 IBC, IPC, IMC, IEBC, and IECC (Utah-amended), the 2023 NEC, and states the IRC 'will remain 2021.' Also confirmed directly against Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027) at le.utah.gov. CAUTION: the same Murray page also retains an older, unremoved 'Overview' paragraph further down stating 'As of July 1st 2023, the state of Utah has adopted the 2021 I Codes and the 2023 NEC' — that leftover sentence is stale and contradicts the page's own current banner; see tipsAndGotchas for this discrepancy.. Local amendments apply — see the Murray overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Murray building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.