Residential Addition / Remodel Permit (incl. Basement Finish) — Murray, Utah · Requirements sheet
Verified 2026-07-04 · Source: https://www.murray.utah.gov/DocumentCenter/View/19435/Building-Fee-Sheet-eff-07012026
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Addition / Remodel Permit (incl. Basement Finish) in Murray, Utah
Required for residential additions, remodels, and basement finishes in Murray. The official fee sheet lists a distinct discounted rate for Basement Finish: valuation-based fee plus a 50% plan review surcharge (lower than the 65% commercial/general residential plan-review rate).
Verified 2026-07-04 · Source
When you need this permit
- Additions to existing one- and two-family residential structures
- Basement finish work (framing, MEP) in an existing home
- Structural remodel work regulated by the adopted 2021 IRC
- Site plan required per Murray City Code § 17.04.100
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Framing
Wall framing and fire blocking inspection, part of the combined Building/Electrical/Mechanical/Plumbing inspection line (801-270-2431) per the Certificate of Occupancy Requirements form.
- 2
Final / Certificate of Occupancy
Certificate of Occupancy or Temporary CO issued 5 to 10 working days after the General Contractor of record submits the completed sign-off form, per Murray's official CO Requirements form.
See the full Murray inspection guide — scheduling & re-inspection fees →
Tips
- Murray's Basement Finish fee gets a reduced 50% plan-review surcharge versus the 65% rate used for swimming pools and other residential BOV items on the same fee sheet.
- Use the ICC Building Valuation Data (Feb 2026) 'Additions to this Table' section for basement and addition per-square-foot rates — these differ substantially by finished vs. unfinished basement status.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Murray building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Murray
Residential Addition / Remodel Permit (incl. Basement Finish) in other cities
Compare residential addition / remodel permit (incl. basement finish) fees across Utah →
Look up this fee in a different city →