Commercial Building Permit in Richfield, Utah

Required for new commercial building construction in Richfield, filed as part of the city's 'Large Building Permit Application' (house, garage, commercial, etc.) online via the utah.cityinspect.com portal, per the city's official Forms & Applications page. Richfield's own 2021 Request for Proposal for Plan Review and Building Inspection Services — a city procurement document still published on richfieldut.gov — commits its contracted plan reviewer to complete commercial plan reviews within 10 business days, and separately documents that Richfield issues very few commercial permits (1 in 2019, 1 in 2020, versus 69 and 125 residential permits those same years). The RFP lists this 10-business-day commercial figure as a standalone line item, distinct from the 5-business-day single-family and 10-business-day multifamily residential commitments in the same document — a genuine city-specific commercial SLA, not a misapplied borrowing of the statewide residential statutory floor (Utah Code § 10-20-909 scopes only to residential dwellings/townhomes/other-residential per its own text). Separately, and materially: richfieldut.gov's Forms & Applications page no longer lists the 'Large Building Permit Application' (CityInspect) or 'Small Building Permit Application' (DocHub) links in its Building Department table — a genuine, recent site change (a 2025-10-29 archived capture still shows both links present). The underlying utah.cityinspect.com registration URL and the DocHub PDF page both still resolve directly, so neither system has been shut down, but current on-page navigation to them from Forms & Applications has changed; see tips for full detail.

Reviewed 2026-08-02 · Source

When you need this permit

  • New commercial construction, filed under the 'Large Building Permit Application' track
  • Any structural, electrical, plumbing, or mechanical work, per Richfield's official FAQ general permit-trigger language
  • Utah law requires commercial building plans to be designed, drawn, and stamped by a Utah Licensed Architect or Engineer (Utah Code §§ 58-22-305 and 58-3a-304 — the exemption from stamped plans applies only to one- and two-family dwellings, not commercial structures)
  • Site Plan Review Application Packet, for new commercial development requiring site-plan approval, per the city's Forms & Applications page

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Filing fee
Not published — contact the department

Review timeline

Plan reviewRichfield’s published plan-review target
10–10 business days

How long did your Commercial Building Permit permit actually take in Richfield?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Building, Electrical, Mechanical & Plumbing

    Inspections administered by the Richfield City Building and Zoning Department; contact the Building Inspector at (435) 896-6439 to schedule. A Building Permit Number must be provided when scheduling any inspection.

See the full Richfield inspection guide — scheduling & re-inspection fees →

Tips

  • Richfield's own 2021 procurement RFP for its contracted plan reviewer states commercial construction is rare: only 1 commercial permit was issued in 2019 and 1 in 2020, compared to 69 and 125 residential permits those same years.
  • The city's Plan Review and Building Inspection Services RFP commits its contracted plan reviewer to a 10-business-day commercial plan-review turnaround. That is a procurement commitment to the city rather than a statutory deadline, so treat it as a planning figure and confirm current timing with the Building and Zoning Department.
  • No dedicated commercial building-permit fee amount is published. Richfield's fee-bearing PDFs ('Small Building Permit' and 'Impact Fees', both linked from richfieldut.gov/forms-applications) are hosted on DocHub, whose client-rendered viewer does not expose the documents' text, and no fee schedule or budget document appears anywhere else on richfieldut.gov — the same gap documented for the residential-building-permit entry. The 'Small Building Permit' document is a single page, last updated 2021-04-20, consistent with a short application form rather than an itemized fee schedule — so it is unlikely that document ever contained a commercial fee figure. The Utah Public Notice Website (utah.gov/pmn) carries no Richfield-specific Consolidated Fee Schedule notice (only other municipalities' schedules appear there). Confidence stays partial.
  • richfieldut.gov's Forms & Applications page 'Building Department' table now lists only 'Encroachment Permit', a 'Permitted Use Application' (hosted on xpressformsbuilder.com) and 'Impact Fees'. It no longer lists the 'Large Building Permit Application' (CityInspect) or 'Small Building Permit Application' (DocHub), both of which were present as recently as late 2025. The utah.cityinspect.com registration URL and the DocHub 'Small Building Permit' PDF page both remain live, so neither underlying system has shut down — they have simply been delinked from that page. Whether the new 'Permitted Use Application' is a successor intake system for building permits or an unrelated zoning form is undetermined. This does not change the fee-gap conclusion, since neither delinked application published a fee figure even when linked, but it does mean the Forms & Applications page no longer corroborates the CityInspect intake route. Confirm current commercial-permit intake procedure directly with the Building and Zoning Department (435-896-6439).

Frequently asked questions

Richfield requires a commercial building permit for: New commercial construction, filed under the 'Large Building Permit Application' track; Any structural, electrical, plumbing, or mechanical work, per Richfield's official FAQ general permit-trigger language; Utah law requires commercial building plans to be designed, drawn, and stamped by a Utah Licensed Architect or Engineer (Utah Code §§ 58-22-305 and 58-3a-304 — the exemption from stamped plans applies only to one- and two-family dwellings, not commercial structures); Site Plan Review Application Packet, for new commercial development requiring site-plan approval, per the city's Forms & Applications page. If your project isn't listed, confirm with Richfield City Building and Zoning Department at (435) 896-6439 before starting work.

Richfield's 2021 Request for Proposal for Plan Review and Building Inspection Services commits the city's contracted plan reviewer to completing commercial plan reviews within 10 business days — faster than the 5-business-day single-family standard is not the case; single-family is actually faster at 5 business days, with multifamily and commercial both at 10 business days.

You'll need: Large Building Permit Application (CityInspect online portal). Depending on your project, Richfield may also ask for: Site Plan Review Application Packet; Building Permit Application (paper form, alternate). See the required-documents checklist on this page for details on each.

Richfield requires 1 inspection(s) for a commercial building permit, in order: Building, Electrical, Mechanical & Plumbing. Schedule each through Richfield City Building and Zoning Department ((435) 896-6439).

Apply through Richfield City Building and Zoning Department at 75 East Center Street (basement level), Richfield, UT 84701. Phone: (435) 896-6439. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://richfieldut.gov/forms-applications/.

Richfield, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide code as of 7/1/2026 under the Utah Uniform Building Standard Act (Utah Code Title 15A); Utah Code § 15A-2-103(1)(a). Richfield, as a Utah municipality, is bound to the statewide State Construction Code per Utah Code § 15A-2-103 and does not separately codify its own edition (its own FAQ/Forms pages, live-checked 2026-07-16, do not state any code edition at all); 2021 International Residential Code (IRC) — REMAINS CURRENT statewide code; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 amendment (consistent with the same statewide code confirmed on Murray City's official Building Division page, though Murray's own page has separately been found to contradict itself elsewhere — not relied on here beyond the general statewide-cycle confirmation); Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); Richfield does not separately itemize this, added here per statute; 2024 International Plumbing Code (IPC) — CURRENT statewide code as of 7/1/2026; Utah Code § 15A-2-103(1)(d); 2024 International Mechanical Code (IMC) — CURRENT statewide code as of 7/1/2026; Utah Code § 15A-2-103(1)(e); 2024 International Fuel Gas Code (IFGC) — CURRENT statewide code as of 7/1/2026; Utah Code § 15A-2-103(1)(f); not itemized in Richfield's own materials (which cite only the statewide statute generally), added here per statute since this record had previously omitted it entirely; 2024 International Existing Building Code (IEBC) — CURRENT statewide code as of 7/1/2026; Utah Code § 15A-2-103(1)(i); 2024 International Energy Conservation Code (IECC) with Utah amendments, single unsplit statewide edition — CURRENT statewide code as of 7/1/2026; Utah Code § 15A-2-103(1)(h); Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n); not itemized in Richfield's own materials, added here per statute since this record had previously omitted it entirely; 2023 National Electrical Code (NEC) — current statewide electrical code; Utah Code § 15A-2-103(1)(g) did NOT change this edition in the 7/1/2026 amendment; NOTE (2026-07-16 re-verification): The Utah Code § 15A-2-103 version effective 7/1/2026 (superseded 1/1/2027) took effect 15 days before this re-verification. This entry previously described the 2024-cycle codes in future tense ('takes effect July 1, 2026'); that date has now passed, so IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now stated as CURRENT (2024/2024/2024/2024/2024/2024/2024), while IRC (2021) and NEC (2023) remain unchanged and were already correctly stated. Richfield publishes no city-specific code-edition page (its FAQ and Forms & Applications pages, live-checked 2026-07-16, do not mention code editions at all), so this record continues to rely solely on the statewide statute rather than a lagging city page — there is no city-page conflict to record for Richfield.. Local amendments apply — see the Richfield overview page for the full list.

Very little, per the city's own data: its 2021 RFP states only 1 commercial building permit was issued in 2019 and 1 in 2020, compared to 69 and 125 residential permits those same years.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Richfield building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Richfield.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.

Richfield's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Richfield yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Richfield lands. Privacy.