Certificate of Occupancy / Change of Use — Unincorporated Summit County, Utah · Requirements sheet
Verified 2026-07-23 · Source: https://www.summitcountyutah.gov/262/Building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Certificate of Occupancy / Change of Use in Unincorporated Summit County, Utah
Unincorporated Summit County does not operate a standalone "change of use" permit separate from its Certificate of Occupancy (C.O.) process. Per Snyderville Basin Development Code Section 10-3-20(J) (Certificates of Occupancy) -- this file's own localAmendments entry already documents Section 10-3-20 as this jurisdiction's countywide Building Permit and Certificate of Occupancy provision -- a Certificate of Occupancy is required "before any structure or premises, or part thereof, hereafter erected, changed, converted, moved, altered or enlarged wholly or in part, may be used or occupied," making a change of use itself one of the events that triggers a required C.O. For commercial tenant spaces specifically, a change of use is also a documented trigger in this file's commercial-tenant-improvement-permit entry (it requires a Site Plan, and a change-of-use remodel must be designed by a Utah-licensed architect), so a genuine change-of-use project in an existing commercial building generally proceeds through that Commercial Tenant Improvement / Tenant Finish permit process (or, for a change of use with no construction work, directly through a standalone C.O. application) rather than through a separately named "change of use permit." This entry documents the County's own Certificate of Occupancy requirements, directly sourced from its "Items needed to receive a Certificate of Occupancy" checklist (updated 11/25, confirmed live 2026-07-22).
Verified 2026-07-23 · Source
When you need this permit
- A Certificate of Occupancy is required before any structure or premises "erected, changed, converted, moved, altered or enlarged wholly or in part" may be used or occupied -- quoted directly from Snyderville Basin Development Code Section 10-3-20(J)(1)
- If a building permit was required for the work, construction reflected in the approved building permit must be fully completed before a C.O. can issue (Section 10-3-20(J)(1)(a))
- If no building permit was required (e.g., a pure change of use with no construction), the use itself must conform to the Development Code and all other applicable statutes/ordinances, or qualify as a valid legal nonconforming use under Section 10-8-1 (Section 10-3-20(J)(1)(b))
- All applicable impact fees and other regulatory fees and requirements must be paid before a C.O. is issued (Section 10-3-20(J)(1)(c))
- An application for a Certificate of Occupancy must be submitted to the Building Official on the form provided by the County, accompanied by the required processing fee (Section 10-3-20(J)(2)) -- re-chased 2026-07-23, no dollar figure for this processing fee exists as a distinct line item anywhere in either the complete Building Department Fee Schedule (12 items) or the complete Community Development Department Fee Schedule (25 items) of Ordinance 834-P (verified-negative, both schedules read in full); for projects requiring a building permit it is functionally covered by that permit's own Building Permit Fee (0.0075 of construction valuation, $100 minimum)
- Final Building and Engineering inspections are required prior to C.O. issuance for new construction; a final Engineering inspection is not required for a tenant improvement, per the County's own "Items needed to receive a Certificate of Occupancy" checklist
- A Final Fire Inspection report is required for all permits for a dwelling unit, verifying life-safety systems, access methods, and identification; if fire sprinklers were required, a Final Fire Sprinkler Inspection report from the applicable fire district (Park City Fire District, North Summit Fire District, or South Summit Fire District -- see this file's fire-sprinkler-alarm-permit entry) is also required
- Water/sewer final approval requirements depend on the utility source: no final water approval is needed for a well (but the well log must be uploaded with final documents); a final approval letter/authorization to use is required from the applicable water system (e.g., Mountain Regional Water, Gorgoza); a final approval letter from Snyderville Basin Water Reclamation District is required for sewer-served projects; and Final Wastewater Approval from the Summit County Health Department is required for septic systems
- Planning Department approval is only required for projects that require a final site plan submitted through Planning (e.g., retail stores, hotels, condos, townhomes, apartments) -- this excludes most single-family dwellings, per the County's C.O. checklist
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Building Inspection
Required prior to C.O. issuance for new construction, per the County's C.O. checklist; see this file's residential/commercial building-permit entries for the full inspection sequence leading up to this step.
- 2
Final Engineering Inspection
Required prior to C.O. issuance for new construction; not required for a tenant improvement project.
- 3
Final Fire Inspection
Performed by the applicable local fire district (not the County Building Division) to verify life-safety systems, access, and identification; if fire sprinklers were required, a separate Final Fire Sprinkler Inspection is also required.
- 4
Building Official Premises Inspection
Per Development Code Section 10-3-20(J)(3), the building official inspects the subject premises as part of reviewing the C.O. application before notifying the applicant of the determination.
See the full Unincorporated Summit County inspection guide — scheduling & re-inspection fees →
Tips
- Summit County does not have a separately named "change of use permit" -- a change of use is one of the events that triggers the Certificate of Occupancy requirement under Development Code Section 10-3-20(J)(1) ("erected, changed, converted, moved, altered or enlarged"), and for commercial tenant spaces it is more commonly handled through this file's Commercial Tenant Improvement / Tenant Finish permit entry (which requires a Site Plan and, for a change-of-use remodel, a Utah-licensed architect) rather than as its own application type.
- If no building permit is required for a pure change of use (no construction), the use itself must still conform to the Development Code or qualify as a valid legal nonconforming use before a C.O. can issue.
- Re-chased 2026-07-23: confirmed as a verified-negative, not just an unread gap, that no distinct C.O. processing-fee line item exists in either complete department fee schedule of Ordinance 834-P -- for projects requiring a building permit, the processing fee is absorbed into that permit's own Building Permit Fee (now directly confirmed: 0.0075 of construction valuation, $100 minimum, per item 2 -- see this file's residential/commercial/tenant-improvement-permit entries); for a pure change-of-use C.O. with no building permit, no fee amount is published at all. Confirm directly with the Building Department before budgeting.
- Water/sewer sign-off requirements for a C.O. vary by utility source -- well (log upload only), piped water system (final approval letter), sewer district (Snyderville Basin Water Reclamation District letter), or septic (Summit County Health Department Final Wastewater Approval) -- confirm which applies to a specific parcel early, since these can be the longest lead-time item.
- Planning Department sign-off on a C.O. is not universal -- it only applies to projects that required a final site plan through Planning (retail, hotels, condos, townhomes, apartments), which excludes most single-family dwellings, per the County's own C.O. checklist.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Summit County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Summit County
Certificate of Occupancy / Change of Use in other cities
Compare certificate of occupancy / change of use fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Summit County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Summit County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →