Solar Photovoltaic (PV) Installation Permit in Unincorporated Summit County, Utah
Unincorporated Summit County requires a Building Permit for solar PV installations, per the County Building Department's official page: 'Permits are also required for solar PV installations.' Unlike the general residential/commercial Building Permit (which is priced off the ICC Building Valuation Data table and a non-public multiplier), the County's own Building Department Fee Schedule (Ordinance 834-P) prices solar PV under a distinct 'Alternative Energy Permits' category — explicitly described in the ordinance as 'separate from the permits issued for new construction' — with a flat $700 Photovoltaic System fee. Applications are still submitted through the same EPROCESS360 online portal as all other County building permits; no standalone solar-only application form, checklist, or fee schedule document is currently published (the County's historical 'Solar ABCs' expedited-permitting checklist, once posted at DocumentCenter View 272, is now a dead link with no Wayback capture, confirmed by this verification).
Verified 2026-07-21 · Source
When you need this permit
- A County Building Permit is required for solar PV installations (residential or commercial) in unincorporated Summit County, per the Building Department's official page
- Application is submitted through the EPROCESS360 online portal (summit.co.ut.eprocess360.com) — the County does not accept paper plans or perform over-the-counter reviews, and no distinct solar-only application form is published
- Electrical interconnection work must comply with the 2023 National Electrical Code (NEC), adopted statewide per Utah Code § 15A-2-103(1)(g)
- For roof-mounted arrays, standard structural attachment/point-load documentation may be requested during plan review, consistent with the County's general Construction Plans requirements for structural elements (no solar-specific structural checklist is separately published)
- Confirm with the Building Department at (435) 336-3124 whether a given project (e.g., ground-mounted array, battery storage addition) needs additional planning/zoning review beyond the building permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical / PV Interconnection Inspection
Not separately published as a distinct solar-specific inspection sequence by the County; follows the standard electrical inspection practice documented for this jurisdiction's residential-building-permit entry (e.g., minimum two 20-amp GFCI-protected circuits required for power-to-panel work, per the County's 4-Way Inspection description).
- 2
Final
Final inspection sign-off for the PV system installation.
See the full Unincorporated Summit County inspection guide — scheduling & re-inspection fees →
Tips
- Solar PV is one of the few permit types in unincorporated Summit County with a published flat fee — $700 for a Photovoltaic System — rather than the opaque valuation-based formula used for general new construction. Compare to the schedule's other Alternative Energy Permit line items: Geo-Thermal $500, Solar Hot Water $250, Wind Generator $250.
- The ordinance describes Alternative Energy Permits as 'separate from the permits issued for new construction' — this is the applicable fee track for standalone solar/PV installations (e.g., retrofits onto an existing home), rather than folding solar into the whole-structure ICC valuation calculation used for new-build permits.
- No dedicated solar-only application form or checklist is currently published; applications go through the same EPROCESS360 portal and general Building Permit Checklists as every other permit type in this jurisdiction.
- A historical County document referencing an expedited 'Solar ABCs' checklist (Summit County was, with Park City, one of the first two Utah jurisdictions to adopt this streamlined model, per Utah Clean Energy's Solar Permitting Toolbox) is no longer reachable (DocumentCenter View 272 returns a 404, no Wayback capture found) — confirm current solar-specific submittal expectations with the Building Department at (435) 336-3124 or buildingquestions@summitcountyutah.gov.
- It is unclear from the ordinance text whether the 65% Plan Review Fee add-on applies on top of the flat $700 Photovoltaic fee, or only to the general valuation-based Building Permit Fee — the 1% Utah State Surcharge is explicitly stated to apply to 'all permits' and so does apply here.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-21.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Summit County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Summit County
Solar Photovoltaic (PV) Installation Permit in other cities
Compare solar photovoltaic (pv) installation permit fees across Utah →
Look up this fee in a different city →