Commercial Building Permit — Grantsville, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://www.utah.gov/pmn/files/1205659.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit in Grantsville, Utah
Required for new commercial and industrial construction in Grantsville, regulated by the state-adopted 2024 IBC with Utah amendments (Utah Code § 15A-2-103(1)(a), effective 7/1/2026). Grantsville's Consolidated Fee Schedule publishes a distinct 'Commercial/Industrial Building Permit Fees' table, separate from its Single Family Dwelling and Multi-Family tables, most recently amended by Ordinance 2024-30 (approved 11/6/2024) for the Building Permit Fee rate and Ordinance 2024-37 (adopted 12/4/2024) for the Plan Check Fee rate.
Verified 2026-07-19 · Source
When you need this permit
- New commercial or industrial construction, or any work regulated by the adopted 2024 IBC with Utah amendments
- Complete building permit application per Utah Code Title 15A completeness requirements, including applicant/general contractor contact information
- Site plan showing lot size and dimensions, setbacks, hard surface areas, existing/proposed utilities, and street names
- Construction plans and drawings including structural, electrical, mechanical, and plumbing design
- Engineering structural calculations stamped and signed by a Utah-licensed engineer
- Commercial accessory structures over 120 sq ft require their own permit, per Grantsville's Accessory Structure Requirements (a lower no-permit threshold than the 200 sq ft residential one)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing / Spot Footing Inspection
Footing must be formed with steel hung in place, on natural ground without fill material; a Soils Observation Report is required prior to or at time of this inspection, per Grantsville's All Residential and Commercial Inspection List.
- 2
Foundation Inspection
Formed with steel tied in place, including all concrete-to-structure straps required by plans.
- 3
Under Slab Plumbing / Heating / Electrical Inspections
All under-slab piping, ductwork, and electrical must be left fully exposed until inspected.
- 4
Four-Way Rough Inspection
Rough framing, electrical, HVAC, and plumbing complete, done before insulation is installed.
- 5
Final Inspection (and Off-Site Final)
Done when the structure is ready for occupancy; both the in-house Final and Off-Site Final inspections must pass for Occupancy to be released.
See the full Grantsville inspection guide — scheduling & re-inspection fees →
Tips
- Grantsville does not publish a distinct Commercial Submittal Checklist online (only a New Residential Building Submittal Checklist for SFD and the shared 'All Residential and Commercial Inspection List' were found as of 2026-07-19) — confirm exact document requirements with the Building Department, (435) 884-1691.
- Commercial accessory structures over 120 sq ft require their own permit — a lower no-permit threshold than the 200 sq ft residential accessory-structure threshold, per Grantsville's Accessory Structure Requirements.
- The Commercial/Industrial Plan Check Fee rate (.0049 x valuation) is higher than the Single Family Dwelling rate (.0040 x valuation); the Building Permit Fee rate (.0068 x valuation) is identical across both tables.
- Commercial/Industrial impact fees are assessed per building square footage or per fixture unit (e.g., Public Safety Fee $953.80/1,000 sq ft, Transportation Impact Fee $1,029.43/1,000 sf) rather than per dwelling unit as on the residential tables.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Grantsville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Grantsville.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Grantsville
Commercial Building Permit in other cities
Compare commercial building permit fees across Utah →
Look up this fee in a different city →