Solar PV (Photovoltaic) Permit — Tooele, Utah · Requirements sheet
Verified 2026-07-21 · Source: https://www.tooelecity.gov/services/finance/fees.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV (Photovoltaic) Permit in Tooele, Utah
Tooele City does not publish a distinct solar or photovoltaic permit category, application, or fee line item. Rooftop and ground-mounted solar PV installations are permitted through the same Building Permit (for structural/mounting work) plus standard electrical permitting (for the interconnection wiring), billed under the same IBC-rate valuation-based fee mechanism used for all other building and trade work.
Verified 2026-07-21 · Source
When you need this permit
- Installation of a rooftop or ground-mounted solar photovoltaic (PV) system at a residential or commercial property
- Structural/mounting scope reviewed under the same state-mandated 2024 IBC / 2021 IRC used for general building permits (Utah Code § 15A-2-103)
- Electrical interconnection work reviewed under the 2023 NEC via standard electrical permitting
- Subject to the same IBC-rate valuation-based fee as other building/trade work
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Tooele City Fee Schedule (current as of July 17, 2026 revision; Show full citationHide
Tooele City Fee Schedule (current as of July 17, 2026 revision; PDF downloaded and full-text searched 2026-07-21), Building section, 'Building Permit Plan Reviews' ('IBC rate' for Single-Family Residence, Multi-Family Residence, Commercial, and Industrial) and 'Other: All Other Plans — Per IBC.' No separate 'Solar,' 'Photovoltaic,' or 'PV' line item exists anywhere in the Fee Schedule; solar PV work is billed under this general IBC-rate valuation mechanism, the same mechanism documented for EV charger/EVSE installations in the ev-charger-permit entry.Review timeline
Inspection process
- 1
Structural / Mounting Inspection
Verifies panel mounting/attachment to the roof or ground-mount structure against submitted plans; all inspections require 1 working day advance notice per the Tooele City Building Permit application form.
- 2
Electrical Inspection
Verifies the PV interconnection wiring, inverter, and disconnect against the 2023 NEC; General Purpose inspection fee is $50 (Fee Schedule, Building section).
See the full Tooele inspection guide — scheduling & re-inspection fees →
Tips
- Tooele City has no separate solar/PV fee category and no dedicated solar permit application — confirmed by downloading and full-text searching the current Fee Schedule PDF, the finance/fees.php page, the Building Permit Fees Information Sheet, and the Applications & Forms page (2026-07-21); solar installations are billed under the same IBC-rate valuation table used for all other building/trade work, matching the note already on the residential-building-permit entry.
- Rooftop or ground-mounted PV requires a Building Permit (structural/mounting) plus standard electrical permitting (interconnection) — confirm with Community Development, (435) 843-2132, whether a given installation needs a combined submittal or two separate permits.
- Tooele City publishes no solar-specific submittal form and no itemized solar fee — solar goes through the general permit process here. Other Utah jurisdictions do publish dedicated solar forms and solar fee lines, so don't reuse another city's solar packet or fee estimate on a Tooele project.
- A 1% state surcharge and a Plan Check Fee (65% of the Permit Fee, per the March 2015 Information Sheet) apply on top of the base valuation fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-21.
Fee schedules
Applications & forms
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Tooele building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Tooele's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Tooele yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Tooele lands. Privacy.
Other permits in Tooele
Solar PV (Photovoltaic) Permit in other cities
Compare solar pv (photovoltaic) permit fees across Utah →
Look up this fee in a different city →